Professional Documents
Culture Documents
Unit - 2 Pengurusan Projek
Unit - 2 Pengurusan Projek
SHCEDULE
INTRODUCTION
This unit will be discuss about the application of Bar Chart, Critical Path Method and Microsoft Project Basic Operation in the project management.
Example 2.1 From the Figure 2.1(b) below shows a simple bar graph schedule for a construction project. Calculate scheduled and actual cumulative progress and plotted for the first three weeks for physical progress of the project.
Notes: The column headed Hours indicates the estimated number of labour-hours required for each activity. The column Weight indicates the portion of the total project effort accounted for by each activity. Notice that two horizontal blocks are provided opposite each activity. The upper block (SCH) represents scheduled progress and the lower block (ACT) is used to record actual progress as work proceeds. For each block, a bar extends from starting to ending times. The number above each bar indicate percentage of activity completion at each major time division.
The Normal Progress Curve or S-Curve is shown in Figure 2.1(c). As the curve indicates, progress is slow at the beginning of a project as work is organized and workers become familiar with work assignments and procedures. Thus, only about 15% of the project is completed in the first 25% of the project time. After that, progress is made at a rather constant rate until 85% of the work is completed at the end of 75% of project time. Progress again slows as finishing work and project demobilization take place.
Figure 2.1(b)
Figure 2.1(c)
Solution: Step 1 : Calculate Weighting Factors Example, Clearing and Stripping activity required 750 labour-hours of work, which represent 4.7% of the 15,900 labour-hours required for the entire project. (750 / 15900 ) x 100% = 4.7%
Step 2 : Calculate Scheduled Cumulative Progress and plotted Cumulative progress = Activity Progress x Weight
Example calculation for the scheduled cumulative progress for the first three weeks of the project as follow. End of First Week Progress Activity 1 = (0.20 x 4.7) = 0.9% End of Second Week Progress Activity 1 + Activity 2 + Activity 3 = (0.70 x 4.7) + (0.60 x 0.9) + (0.15 x 26.4) = 7.8% End of Third Week Progress Activity 1 + Activity 2 + Activity 3 = (1.00 x 4.7) + (1.00 x 0.9) +(0.40 x 26.4) = 16.2%
Step 3 : Calculate Actual Cumulative Progress and plotted End of First Week Progress Activity 1 = (0.00 x 4.7) = 0.0% End of Second Week Progress Activity 1 + Activity 2 + Activity 3 = (0.45 x 4.7) + (0.30 x 0.9) + (0.05 x 26.4) = 3.7%
End of Third Week Progress Activity 1 + Activity 2 + Activity 3 = (1.00 x 4.7) + (1.00 x 0.9) + (1.00 x 26.4) = 16.2%
Step 4 : Draw Progress Curve Frequently, cumulative progress curves for a project are superimposed on the projects bar graph schedule as illustrated in Figure 2.1 (d).
Discuss about the effective of planning in construction management. From the Table 2.1(a) below shows that small project activities.
i.
Q2.
ii. Try to track Schedule vs Actual for physical progress of the project
No.
List of activities
2 3 4,5
-
4 2 2 1 1 0 0 0 0 0
2 Footing 3 Ground Beam 4 Slab 5 Column 6 Roof Beam 7 Brick Wall 8 M&E 9 Building Envelope 10 Ark. Finishing
6 7,8
-
9 10
-
Table 2.1(a)
2.2 CRITICAL PATH METHOD (CPM) 2.2.1 LOGICAL RELATIONSHIP OF PROJECT ACTIVITIES
Understand the order of how the job to be accomplished in the field. The planner must understand how various activities of the project related to each other in term of their logical sequence. Example preparing formwork before reinforcement could be place & than pouring concrete.
From the Figure 2.2 (d) :, Activity D has predecessors A, B & C. Only one activity is allowed between two verticles; dummy activities may be defined if necessary (with zero duration). Activities (3,5) and (4,5) are dummy activities with zero duration
In this module there are two type of network methods. There is Precedence Diagram Method (PDM) and Arrow Diagram Method (ADM) but only Arrow Diagram Method (ADM) will be discuss in detail for this unit.
Figure 2.2(e)
See the example below, Table 2.2 (a) shows list of tasks, predecessor and duration of project. Figure 2.2 (f) is a network diagram using PDM. The diagram must draw from start until end of activity.
bzzz
Task A B C D E F G H I J
Duration 5 3 3 2 4 4 2 8 5 3
iii. EF is the Earliest Time of Finish Event iv. LF is the Latest Time of Finish Event v. Activity duration (D) is the time to complete an activity
Figure 2.2 (h) and Figure 2.2 (i) shows a simple network diagram for a construction project. As mentioned earlier, the diagram graphically indicates the relationships between activities. Activities progress in the direction shown by the arrows. Good diagramming practice requires that diagrams present a clear picture of the project logic and generally flow from left to right. Arrows should not point backward, although they may point straight up or down.
Notice the dashed arrow in Figure 2.2 (h) and Figure 2.2 (i). This is called dummy activity or simply a dummy. Dummies are used to impose logic constraints and prevent duplication of activity numbers. They do not represent any work and, hence, always have a duration of zero.
Task A B C D E F G H I J
Duration 5 3 3 2 4 4 2 8 5 3
Example 2.2 From the Table 2.2 (c) and Figure 2.2 (j) below ; i. ii. iii. Calculate ES,EF,LS,LF from the project activities. Determine critical line Determine project period
Bil
List of activities
1 2 3 4 5 6 7 8
Site Clearing Setting Out Piling Pile Cap & stump Ground Beam Slab Column Roof Beam Table 2.2 (c)
Figure 2.2 (j) : Arrow Diagram Method (ADM) Solution: Step 1: Calculate ES,EF (forward pass) Forward Pass a process to find the earliest start time for all activities. Site Clearing work Node 1 & 2 Start ES at first node with 0, ES1=0 Calculate EF use this formula, EF = ES + Duration EF2 = ES1+Duration EF2 = 0+4 = 4
Setting Out work Node 2 & 3 ES2 =4 (Start from Node 2,ES2=EF2) Calculate EF use this formula, EF = ES + Duration EF3 = ES2+Duration EF3 = 4+3 = 7
Piling work Node 2 & 4 ES2 =4 (Start from Node 2,ES2=EF2) Calculate EF use this formula, EF = ES + Duration EF4 = ES2+Duration EF4 = 4+2 = 6
Dummy Node 3 & 4 ES3 =7 (Start from Node 3,ES3=EF3) Calculate EF use this formula, EF = ES + Duration EF4 = ES3+Duration EF4 = 7+0 = 7
Now we have two arrow from node 2 and node 3 meet at node 4. From the Forward Pass Theory, we must take the largest time of EF4 before continuing define ES4 for Ground Beam work. Between 6 and 7, the largest must be 7, then fill 7 in the EF4 box.
Continue calculate the ES and EF until finish (node 9) and fill in the table below.
Activity Site Clearing Setting Out Piling Pile Cap & Stump GB Slab Col RB
Duration 4 3 2 2 4 2 3 4
ES 0 4 4 4 7 11 11 14
EF 4 7 7 11 11 13 14 18
LS
LF
Roof Beam work Node 9 & 8 Start LF9 at last node with same value of EF9=18 Calculate LS use this formula : LF8 = LF9 - Duration EF2 = 18-4 = 14 LS = LF Duration
Figure 2.2(l)
From the Backward Theory, if two arrow meet at one node, take the lowest time of LF between the two value. Continue calculate the LS and LF until finish (from node 9 until 1) and fill in the table below.
Activity Site Clearing Setting Out Piling Pile Cap & Stump GB Slab Col RB
Duration 4 3 2 2 4 2 3 4
ES 0 4 4 4 7 11 11 14
EF 4 7 7 11 11 13 14 18
LS 0 4 4 4 7 12 11 14
LF 4 7 7 12 11 14 14 18
Step 3: Determine critical line / critical path Critical line / critical path are the longest paths of the planning from start to finish. Usually the activity has same duration time start and finish. From the figure 2.2 (m), this project critical for activities of site clearing, setting out, ground beam, column and roof beam. The critical line is 1-2-3-4-5-8-9 with 18 week.
Exercise 2.2 Q1. From the Table 2.2 (e) below shows list of project activity to construct the pad footing at Surau Sek Keb Sri Gading. i. ii. iii. iv. Draw the logical network of the project Calculate ES,EF,LS,LF from the project activities. Determine critical line Determine project period
Nod
List of activities
Setting Out Excavation Order/prepare concrete material Order/prepare bar reinforcement Prepare Formwork install bar reinforcement & formwork Dummy Concrete Table 2.2 (e)
2 4 1 3 4 2 2
Q2.
From the Table 2.2 (f) below shows list of small project activities those undertaken by a contractor company. i. ii. iii. Draw the logical network of the project Calculate ES,EF,LS,LF from the project activities. Determine critical line & project period
Bil
List of activities
1 2 3 4 5 6 7 8 9 10
1-2 1-3 1-6 2-4 3-5 4-6 5-6 5-7 6-8 7-8
4 1 12 10 8 8 8 4 8 7