Professional Documents
Culture Documents
MUMBAI DIVISION
TENDER NOTICE No. BCT/08-09/ 286 Dt.26-09-08 DOWNLOAD DOCUMENT
TENDER DOCUMENT
(NON-TRANSFERABLE)
FORWARDING LETTER
Issued to / Downloaded by : -
Note : If the tender has been downloaded from the website , the interested bidders should
write their name and address in the space above and enclose cost of tender
documents in acceptable form as mentioned in the tender documents along with
the offer.
The price of the tender document is paid for the above tender vide
DD/Money Receipt No Dated:-
Note :- (Tenderers to fill details of tender fee in form of Money Receipt for tenders
purchased in person/ by post OR Demand Draft particulars for tenders down
loaded from Web site deposited for the cost of tender)
1. For tenders sold in the office of the tender inviting authority, the tender document is
issued on request of the tenderer/s after having deposited the requisite cost of the
tender document as stated above. The tender document is issued to these
tenderers with further condition that they agree to abide by the conditions laid
down in the tender document , before submitting the tender.
2. For tender documents downloaded from the official web site of the Western
Railways, the following conditions strictly apply:-
(a) The document has been downloaded by you from the official website of
western railway http://www.wr.indianrail.gov.in for submitting the bid. A
Demand draft (separate Demand Draft other than that of Earnest Money) for
an amount equivalent to cost of tender document mentioned in tender notice
in favour of Sr Divisional Finance Manager, Western Railway, Mumbai
Central, payable at Mumbai, towards the cost of the tender document will
have to be enclosed with the tender document. In case, the offer is not
accompanied with the valid demand draft for the cost of the tender document
as detailed above, the tender will be summarily rejected.
(b) Tenderer/s to please note that the document is being allowed to be
downloaded with further condition that he/they agree to abide by the
conditions laid down in the tender document, before submitting his/their
tender.
(c) The total document from the first page to the last page where `END OF
DOCUMENT' is marked is to be downloaded and submitted along with the
offer. Otherwise the document will be treated as incomplete and therefore
invalid.
TENDER NOTICE
Divisional Railway Manager(WA) , Western Railway, Mumbai Central , Mumbai -400008
for and on behalf of the President of India, invites open sealed tenders on prescribed
form, from experienced and reputed contractors for the following work :
Name of the work : CCG-VR Sec- Removal of garbage muck etc. and disposal of the
same beyond railways limit by contractor’s own trucks/MKC’s
between the section of BA-STC.
1 Sale of tender Forms : Prescribed tender documents will be available for sale at
above mentioned office on working days between 11.00 Hrs to 17.00 hrs up to
date and time indicated above. Tender forms can be dispatched by Registered
post only if a valid request is received atleast ten days prior to date of tender
opening along with cost of tender documents. However Railway will not be
responsible for any delay in receipt of tender documents by post.
2 The tender notice and tender documents will also be available on western railway’s
official web site http://www.wr.indianrail.gov.in. The same can be downloaded and
used as tender document for submitting the tender. This facility is available free of
cost. However the cost of tender document as mentioned above has to be paid in
the form of Demand Draft issued in favour of “Sr Divisional Finance Manager,
Western Railway, Mumbai Central” , payable at Mumbai and should be enclosed
with the Tender Form while dropping the tender. In case the tender is not
accompanied with the valid Demand Draft for the cost of the tender document
downloaded, the tender will be summarily rejected.
3 The cost of tender form should be remitted with any station master of Western
Railway and original money receipt should be produced for getting the tender form
in person or by post. However for tenders downloaded from the website, only
demand draft will be accepted.
4 Tender not accompanied by the required earnest money in the requisite form as
mentioned in the tender documents shall be summarily rejected.
3 The Tendere/s must obtain for himself, on his own responsibility and at his own
expense, all information which may be necessary for the purpose of making the
Tender offer and entering into Contract.
4 The submission of the Tender shall be deemed to have been done after careful
study and examination of the Tender Document with full understanding of the
implications thereof. Any clarification required by a Tenderer shall be obtained from
the Office of the Tender Inviting Authority on any working day during office hours.
5 The tenderer(s) shall strictly adhere to the form of tender specified by the Railway.
Tenders not submitted in this form are liable to be rejected.
10 Every Tenderer shall state in the Tender his postal address fully and clearly. Any
communication sent in time to the Tenderer by post at the said address shall be
deemed to have reached the Tenderer duly and in time. He shall also give
telephone and fax number for communication. Important documents shall be sent
by Registered post. The tender shall be addressed to the tender issuing authority.
11 The complete Tender document shall be dropped in the Tender Box placed in
the Office of the Tender Inviting Authority not later than due date and time of
closing.
12 Such Tenders which cannot be dropped in the Tender Box due to large size, shall
be handed over to the Office Superintendent , tender section , of the office of the
tender inviting authority, not later than the date and time prescribed and a receipt
thereof obtained.
14 Conditional tenders are liable to be rejected. Railway however reserves the right to
reject such tenders summarily without assigning any reasons whatsoever. The
Railway also reserves the right to reject any special conditions stipulated by the
Tenderer as considered unacceptable to the Railway and can call upon the
Tenderer to withdraw such conditions. If any deviations from the General
conditions/ special conditions/ specifications are proposed by the tenderer, they
should be mentioned statement of deviation in annexure`A' and not else where in
the tender documents.
15 Evaluation of Tender:
For evaluation of Tenderer's offer, it may be necessary to seek certain
clarifications. Railway shall seek such clarification in writing or through
telegram/cable/Telex/FAX.
To,
The President of India,
Acting through
Divisional Railway Manager (WA),
Western Railway, Mumbai Central,
Mumbai -400008
2. I/We also hereby agree to abide by the General Condition of Contract corrected
upto Aug 98 with printed/advance correction slips up to no 4 and to carry out the
work according to the special conditions of contract and specifications of materials
and work as laid down by Railway in the annexed special conditions/specifications
and the Western Railway Works Hand Book Part-III,(1984 edition) corrected upto
printed/advanced correction slip number 9 dated 1.11.91, Sanitary Works
Handbook (1977 edition) corrected upto printed/advance correction slip number 1
dated 11.10.84, Schedule of Rates Part-I corrected upto printed/advance
correction slip number 2,3 dated 26.5.94&4.9.95,Schedule of Rates Part-II(1993
edition) corrected upto printed/advance correction slip number 1 dated 11.7.94, for
the present contract.
3. The requisite earnest money as specified in the tender notice is herewith
forwarded as Earnest Money. The full value of the earnest money shall stand
forfeited without prejudice to any other right or remedies in case my/our tender is
accepted and if:-
a. I/We do not execute the contract documents within 15 (Fifteen) days after
receipt of notice issued by the Railways that such documents are ready and
b. I/We do not commence the work within fifteen days after receipt of order to
that effect.
4. Until a formal agreement is prepared and executed, acceptance of this tender shall
constitute a binding contract between us subject to modifications as may be
mutually agreed to between us and indicated in the letter of acceptance of my/our
offer for this work.
3. The tenderer (s) shall quote his/their rates as a percentage above or below the
schedule of rates of the Western Railway as applicable except where he/they
is/are required to quote item rates and must tender for all the items shown in the
schedule of approximate quantities attached. The quantities shown in the attached
schedule are given as a guide and are approximate only and are subject to
variations according to the needs of the Railway. The Railway does not guarantee
work under each item of the schedule.
4. Tenders containing erasures and / or alterations of the tender documents are liable
to be rejected. Any corrections made by the Tenderer (s) in his / their entries must
be attested by him/them.
5. The works are required to be completed within the stipulated completion period
mentioned in the tender notice
6 EARNEST MONEY :
(a) The tender must be accompanied with requisite Earnest money mentioned in the
tender notice, deposited in cash or in any of the forms as mentioned below drawn
in favour of ‘Sr Divisional Finance Manager , Mumbai Central , Mumbai’ , Payable
at Mumbai., failing which the tender will be summarily rejected.
i) Deposit receipt, Pay orders and Demand drafts. These forms of earnest money
could be either of the State Bank of India or of any Nationalized Banks. No
confirmatory advice from the Reserve Bank of India will be necessary.
ii) Deposit receipt executed by the Scheduled Banks ( other than the State Bank
Of India and the Nationalized Banks ) approved by the Reserve Bank Of India
for the purpose. The Railway will not, however, accept, any such deposit
receipt without getting in writing the concurrence of the Reserve Bank Of India.
iii) The earnest money wherever it is deposited in cash should be remitted to the
Chief Cashier, Western Railway, Mumbai Central, Mumbai 400 020 and the
receipt obtained thereof should be enclosed with the tender as a proof of the
deposit of requisite earnest money. The earnest money should not be
deposited with Stations.
(b) Lumpsum/Standing Earnest money is not acceptable as EMD.
(c) The Tenderer(s) shall keep the offer open for a minimum period of validity as
mentioned in the top sheet of the tender document. It is understood that the tender
document has been sold/issued to the Tenderer(s) and the Tenderer(s) is / are
permitted to tender in consideration of the stipulation on his/their part that after
submitting his/their tender subject to the period being extended further if required
by mutual agreement from time to time, he will not resile from his offer or modify
the terms and conditions thereof in a manner not acceptable to Western Railway.
Should the Tenderer fail to observe or comply with the foregoing stipulation, the
amount deposited as Earnest Money for the due performance of the above
stipulation shall be forfeited to the Railway.
(d) If the tender is accepted, the amount of Earnest Money will be retained and
adjusted as Security Deposit for the due and faithful fulfillment of the contract. This
amount of Security Deposit shall be forfeited without prejudice to any other right or
remedies if the tenderer do not execute the contract agreement after acceptance
of the tender within 15 (Fifteen) days after receipt of notice issued by the Railways
that such documents are ready and or the tenderer do not commence the work
within fifteen days from date of issue of acceptance letter.
(e) The Earnest Money of the unsuccessful tenderer (s) will, save as here-in-before
provided, be returned to the unsuccessful tenderer(s) within a reasonable time but
the Railway shall not be responsible for any loss or depreciation that may happen
to the Security for the due performance of the stipulation to keep the offer open for
the period specified in the tender documents or to the Earnest Money while in their
possession nor be liable to pay interest thereon.
7. Rights of the Railway to deal with tender : The authority for the acceptance of the
tender will rest with the Railway. It shall not be obligatory on the said authority to
accept the lowest or any other tender and no tenderer(s) shall demand any
explanation for the cause of rejection of his/their tender nor does the Railway
undertake to assign reasons for declining to consider or reject any particular tender
or tenders.
8. If the tenderer(s) deliberately gives/give wrong information in his/their tender, or
creates/create circumstances for the acceptance of his/their tender, the Railway
reserves the right to reject such tender at any stage.
9. If the tenderer(s) expires after the submission of his tender or after the acceptance
of his tender, the Railway shall deem such tender as cancelled. If a partner of a
firm expires after the submission of their tender or after the acceptance of their
tender the Railway shall deem such tender as cancelled unless the firm retains its
character.
10. Income Tax Clearance Certificate : The tenderer(s) if possible , should also submit
along with their tender an authorised copy of the Income Tax Clearance Certificate
or a sworn affidavit duly countersigned by the Income Tax Office to the effect that
he has / they have no taxable income.
3. Security deposit will be at a flat rate of 5% of the contract value. (See para 4 of
special conditions of contract Part-I (B).
4. A new clause of performance guarantee in the form of bank guarantee for 5% of the
contract value has been introduced. ( See para 5 of Special conditions of contract Part-I(B).
1.0 GENERAL:
1.1 In these Special Conditions of Contract the following terms shall have the meaning
hereby assigned to them except where the context otherwise requires:
(a) "General Condition of Contract" shall mean General Conditions of Contract –1998
as contained in Western Railway, Engineering Department “Works Hand Book Part
I & II “ as amended vide correction slips mentioned in Tender form ) First Sheet.
(b) Standard Specifications shall mean "Western Railway specifications for materials
and Works – 1984 As laid down in Western Railway Works Hand Book Part III
1984) and Sanitary Works Hand book (1984), as amended vide correction slips
mentioned in Tender form (First sheet).
(c) Standard Schedule Items/Rates shall mean the Items/Rates in the Western
Railway Standard Schedule of Rates - 1993.
(d) All other terms shall have the same meaning as assigned to them in the General
Conditions of Contract and Standard Specifications.
i. Any footnote given by the Railway in the schedule of quantities and rates.
ii. Description of item in the Schedule of Quantities and rates.
iii. Special Specifications.
iv. Additional Special Conditions/of Contract.
v. Standard Specifications.
vi. Special Conditions of Contract.
vii. General Conditions of Contract.
1.3 Where there is any conflict in the description, Unit, rate etc. of items based on
schedule of rates, as included in the “Schedule of items, Quantities and rate “
incorporated in the tender/Contract document on the one hand and the Standard
Schedule of Rates on the other hand, Standard schedule of rates should prevail.
2.0 Every endeavor has been made to avoid any error which can materially affect the
basis of the Tender and it is understood that the Contractor has taken upon himself
and provided for the risk of any error which may be subsequently and shall make
no subsequent claim on account thereof.
3. DEVIATIONS:
3.1 Unless specifically provided otherwise in the Tender, any and all exception
which the Tenderer may have to any of the Clauses of the Special
Conditions of Contract or the additional special condition of the contract as
included in the tender shall be clearly stated. Such exceptions shall be listed
in the format, enclosed with the tender as annexure A titled “Schedule of
deviation”. If the Tenderer has no exceptions, the annexure shall be
submitted with a “Nil” statement. If the tenderer does not include the
Annexure with the Tender it shall be conclusive evidence that the Special
Conditions of Contract and the Additional Special Conditions of Contract are
entirely acceptable to the Tenderer.
3.2 Any Deviations from these Special Conditions of Contract and the Additional
Special Conditions of Contract if any stated by the Tenderer in his Tender or
subsequently introduced by the Railway shall be a part of the Contract only to
such extent as have been explicitly accepted by the Railway and incorporated
in the contract.
4 SECURITY DEPOSIT:
4.1 Security deposit will be at a flat rate of 5% of the contract value.
4.2 The Earnest money deposit of successful tenderer will be retained as a part of
security deposit. The amount over and above the Earnest money so retained to
make up the full security deposit will be recovered from each running bill at the
rate of 10% of the bill amount till the full security deposit is recovered. The
balance to make up the full security deposit will be recovered only from the
running bills. Bank Guarantee, Fixed Deposit, Government securities etc.. will
not be accepted for Security deposit.
4.3 No interest shall be payable on security deposit.
4.4 Security deposit will be returned to the contractor after
(a) an unconditional and unequivocal `No claim certificate' is signed by the
contractor and submitted to the Railway Engineer.
(b) Certification by the contract signing authority but not less than the rank of a
JA grade officer (Concerned Sr.DEN in this case) for having completed
the work satisfactorily.
5 PERFORMANCE GUARANTEE.
(a) The successful tenderer shall give a performance guarantee in form of irrevocable
bank Guarantee (issued by SBI/ any nationalized/ Schedule banks) for an amount
equal to 5% of the contract value and valid up to the expiry of maintenance period
of the contract. This shall be furnished before signing the agreement and within a
period of 15 days from the date of letter of acceptance issued by the Railway and
shall be in the format as prescribed by the Railway Engineer.
8. PLEA OF CUSTOM
The plea of custom prevailing will not on any account be permitted as an excuse for
an infringement of any of the conditions of the contract and/ or special conditions of
contract.
16. HANDING OVER WORK SITE: The site of work shall be handed over to the
contractor free of obstruction according to progress of work. Contractor however,
shall not have any claim whatsoever against the Railway for any delay in the
execution of the work, on this account except for extension of the completion
period under the General Conditions of Contract.
17. OCCUPATION AND USE OF RAILWAY LAND: Use of Railway land required by
the Contractor(s) for constructing temporary offices, quarters, hutments, etc., for
the staff and for storing materials, etc. will be permitted to him/them free by
Railway, if available. The location of these offices, hutments, stores, etc. will be
subject to the approval of the engineer or his representative. The land will be
restored to railway by the contractor(s) in the same condition as and when taken
over or in vacant condition as desired by the engineer, after completion of the work
or at any earlier day, as specified by the Engineer. The failure to do so will make
the contractor(s) liable to pay the cost incurred by the Railway for getting
possession of land. Whenever Non Railway bodies /persons are permitted to use
Railway premises with competent authority’s approval. Conservancy charges as
applicable from time to time may be levied.
18. NOTICE TO PUBLIC BODIES: The Contractor(s) shall give to the municipality,
police and other authorities all notices that may be required by law and obtain all
requisite licenses for temporary obstructions, enclosures and pay all fees, taxes
and charge which may be leviable on account of his/their operations in executing
the Contract. He/they should make good any damage to adjoining premises
whether public or private and supply and maintain any lights, etc. required at night.
20. ACCESS TO WORK SITE: Contractor shall have acquainted himself with the
availability of roads and their condition for transportation of materials, machinery,
etc. to the work sites.
21. NIGHT WORK: Further to the provisions in the General Conditions of Contract
regarding execution of work between sunset and sunrise, if the Railway is satisfied
that the work is not likely to be completed in time except by resorting to night work,
by a special order the Contractor shall carry out the work at night without
conferring any right on the Contractor for claiming for extra payment for introducing
night working. The decision of the Engineer in this regard will be final and binding
on the Contractor.
22. PROCUREMENT OF MACHINERY BY CONTRACTOR: It is entirely contractor’s
responsibility and liability to find and procure all the machinery, tools and plants
and their spare parts that are required in connection with execution of work. Delay
in procurement of such items due to their non-availability or import difficulties or
any other cause, whatsoever shall not be taken as an excuse for slow progress or
non-performance of the work.
23. HIRE OF PLANTS, MACHINERY AND OTHER FACILITIES:
The contractor shall make his arrangements for all plants and machinery,
equipment’s, including spare parts, fuel and consumable stores and all
labour required to ensure efficient and methodical execution of the works.
The rates quoted and accepted shall be deemed to be inclusive of all
charges for such items.
Without any commitment on the part of the Railway to do so, on the
contractors request, the Railway may give on hire, plant and machinery,
other facilities , equipments and tools if available separable with the
Railway. The hire charges for such equipment will be as determine by the
Railway on the terms and condition specified by the Railway.
The hire charges will be payable from the day the plant is handed over to
the day it is returned to be Railway Administration. The Contractors shall
enter into a separate agreement with the Railway in this respect and the
terms and conditions as per the agreement will be final and binding on the
contractor.
In the event of a plant or equipment or facility given on hire to the Contractor
not being returned to the Railway in a reasonably good working
order/depreciation that it would have suffered for the period of hire, the
Railway reserves right to recover 1.5 times the cost of procurement at the
If, however, the plant and machinery/other facilities equipment’s and tools
requisitioned by the Contractor are not available in Railway stock or the
Railway decides not to supply the same for reasons whatsoever, neither the
Railway shall be bound to arrange for the supply thereof nor will be
Railway's inability to supply them be accepted as an excuse for delay in the
completion of the works/or for any claims thereof.
25. DRAWINGS:
25.1 Figures and dimensions on Drawings shall supersede measurements by
scale and Drawing to a large scale shall take precedence over those to a
smaller scale. Special dimensions or directions in the specifications shall
supercedes all else.
25.2 The Railway reserves the right to alter/modify the drawings/designs to suit
site conditions. If due to changes in drawings or designs, there is any
increase/decrees in quantities in the items of schedule, payment shall be
made only for the actual quantities executed at the accepted rates. If there
is sufficient ground for granting extension to the completion period on this
account, the Railway will consider such request on the merit of each
individual case. Such circumstances shall in no way a fact or vitiate the
contract or alter the character thereof or entitle the contractor to damages
or compensation therefore.
26.1 The Contractor shall be responsible for maintaining the accuracy of the
alignment, positions, levels and dimensions of the work in accordance with
the drawings, directions or instructions given to him from time to time and
every facility shall be given to the Engineer and or his Representative for
checking of the same. The Contractor at his own cost shall rectify any error in
26.2 The work shall be set out by the contractor to the satisfaction of the Engineer
or his representative but his approval thereto shall not ,nor shall his joining
with the Contractor in setting out the work, relieve the Contractor from his
entire and sole responsibility thereof.
26.3 Maintenance of Layout: The Contractor shall also provide, fix and be
responsible for the maintenance of all stakes, templates, profiles, levels,
marks, points etc. and must take all necessary precaution to prevent these
being removed, altered or disturbed and will be held responsible for the
consequence of such removal, alterations or disturbances should the same
take place and for their efficient reinstatement.
27.4 In case the quantity of cement, steel or any other items issued by Railway
and actually used in the work is less than the quantity specified to be used,
the cost of cement, steel or any other such items not so used shall also be
recovered from the contractor at the rate stipulated in above Clause. This
action will be without prejudice to the rights of the Railway to take action
against the Contractor under the Contract for not doing the work according
to the prescribed specifications and approved Drawing.
27.5 In case of excess usage of Railway materials than those prescribed in SOR/
Specifications in tender documents/ works hand book part-III, recovery for
excess usage of Railway materials be made at double the cost of
procurement at the time issue or latest procurement rate in the division
which ever is higher increased by 7% freight & 12.5% supervision charges .
29 RATES:
29.1 The rates entered in the accepted Schedule of Quantities and Rates, are
intended to provide for works duly and properly completed as per contract
conditions and specifications for the whole of the work as described under
Scope and Details of work.
29.2 The contractor should note that the rates quoted shall accept as otherwise
provided in contact embrace all operations necessary for the satisfactory
completion of the work to finish and shall include all charges for handling,
loading, transport, lead, lift, labour housing, sanitation, materials, machinery,
tools and plants, fuel, electric power, workshop facilities, security, lighting
etc. all other expenses of every kind.
29.3 The rates as given for the different items of work are deemed to be
workable rates for the respective item of work without being dependent in
any manner whatsoever on the quantity specified against the concerned
item of work or on the rates and quantity specified for any other item of work
in Schedule of Quantities and Rates, part of the tender documents.
29.4 The rates quoted shall take into account the precautions and special
arrangements necessary for execution of works under traffic conditions, with
least disruption to traffic. No extra payment shall be admissible on this account
under any circumstances. Railway will however, arrange for blocks of traffic
during work only to the extent as considered sufficient for the works by the
Railways. The Contractor will not be entitled for any compensation, if there be
any delay in arranging these blocks or the block period be of shorter duration
as considered by the Contractor.
29.5 Service Roads: The contractor will be permitted to make use of the service
roads already existing in possession of the Railway. If construction of any
additional roads within Railway premises is considered necessary and agreed
to at contractors request ,the contractor will be required to make them at his
own cost and maintain them till the work is completed. Contractor shall
construct any service roads, required outside the Railway boundary, at his own
cost. Railway reserves the right to make use of service roads, made by the
contractor, as and when necessary without any additional payment to the
contractor. Any damages caused to the existing roads, due to use by
contractor, shall have to be made good by the contractor, at his own cost.
30 PAYMENT OF ROYALTY CHARGES: All taxes, royalty charges, etc. of whatever
nature in connection with the work including extraction and supply of rubble
stone/stone ballast/sand/moorum/earth or any other material used on the work shall
have to be borne by the Contractor. The Contractor will be required to obtain a royalty
clearance certificate from the concerned Revenue Authorities/Collector and produce
the same to the Engineer after completion of the supply but before release of the final
bill.
31 ROYALTIES AND PATENT RIGHTS:
31.1 The Contractor shall defray the cost of all royalties, fees and other payments in
respect of patents, patent rights and licenses which may be payable to
patentee, licensee or other person or corporation and shall obtain all necessary
licenses.
31.2 The contractor shall indemnify, the Railway or any agent, servant or employee
of the Railway against any action, claim or proceedings relating to infringement
use of any patent or design any alleged patent or design rights and shall pay
any royalties or other charges which may be payable in respect of any articles
or materials or part thereof included in the contract. In the event of any claim
being made or action being brought against the Railway or any agent, servant
or employee of the Railway in respect of any such matters , as aforesaid, The
contractor shall indemnify notified thereof. Provided that such indemnify shall
not apply when such infringement has taken place in complying with the
specific direction issued by the Railway but the contractor shall pay any
royalties or other charges payable in respect of any such use.
32.2 If the contractor fails to appoint a suitable agent as directed by the Railway
Engineer, the latter shall have full power to suspend the execution of works,
until such date a suitable agent is appointed and the contractor shall be held
responsible for the delay so caused to this works. The successful tenderer shall
state the name of the technical supervisor along with him technical
qualification, while it may not be necessary for the technical supervisor to
reside at site, he should be available at the site of work during the working part
of the day. Normally no change in the technical personnel during the period of
construction would be acceptable to the Railway except under very special
circumstances. The Railway reserves the right to stop the work in case the
technical supervisor of tenderer is not available.
33 COMPLETION CERTIFICATE:
33.1 The work shall not be considered to have been completed in accordance with
the terms of contract, until the Engineer incharge shall have issued a certificate
in writing to that effect. No approval of materials or workmanship or approval of
33.2 After the work is completed, the contractor/s shall give notice of such
completion to the Engineer-in-charge and on receipt of such notice the
Engineer-in-charge shall have the work inspected and if there is no defect in
the works ,shall furnish the contractor/s with a certificate indicating the date
of completion. However, if there are any defects which in the opinion of the
Engineer-in-charge are rectifiable he shall inform the contractor/s the
defects noticed. The contractor/s after rectification of such defects shall
notify the Engineer-in-charge and then the Engineer-in-charge on his part
shall have it inspected again and issue the necessary completion certificate
if the defects are rectified to his satisfaction, and if not be shall inform the
contractor/s indicating defects yet to be rectified. The time cycle as above,
shall continue.
34.2 The Railway will deduct sales tax if leviable in a particular state where the
work is going on, the gross amount of each bill while making payment to the
contractor(s). The recovery shall be governed as per the guide lines & rates
prescribed by the concerned State Government..
34.3 All taxes as prescribed by Central or State Government from time to time
shall be applicable. The contractor shall be fully responsible for payments
of all such taxes without any liability of Railway administration. Deductions
towards such taxes shall be made from the payments of the contractor
in accordance with rules in force from time to time.
35 EXCISE DUTY OR ANY OTHER TAXES/DUTIES: The contractor shall bear full
excise duty, sales tax and / or any other taxes/ duties levied by State Government
and / or Central Government/Local bodies from time to time. This would be
entirely a matter between the contractor and the State / Central Government./Local
bodies. No claim, what so ever, on this account shall be entertained by Railways.
41 ENGAGING LOCAL LABOUR: The contractor shall engage local labour for
unskilled works, as far as practicable.
42 ANTI-LARVAL WORKS: During the execution of the works against this contract
the contractors shall be responsible for anti-larval work at his/their own cost.
43 NON-ITEMIZED WORKS: Where items not covered by the schedules are to be
executed the rates for such non-itemised works shall be negotiated before the
commencement of such work or got executed through any other agency at the
discretion of the Railway Administration.
44 TIME IS THE ESSENCE OF CONTRACT: Time being the essence of contract all
the works are required to be completed in all respect as stipulated by the Railway
within the completion date. Progress shall be maintained strictly in accordance with
program given by the Engineer-in-charge from time to time.
45 LEAD AND LIFT ON RAILWAY/CONTRACTOR’S MATERIALS: Unless
otherwise specified, no lead and lift for the contractor’s material is payable for the
works executed under this contract though there are separate SOR items for the
same.
46 CUTTING/UP ROOTING OF TREES: No extra rate shall be paid for cutting or up-
rooting trees but the contractor would be authorised to take away the tree
observing the forest laws of the land.
47 ACCEPTED RATES: The rates quoted by tenderer and accepted by the Railway
Administration shall hold good till the completion of the work and no additional,
individual claim shall be admissible on account of fluctuation in market rates,
increase in taxes any other levies/tolls etc.
48 OBSERVANCE OF BONDED LABOUR SYSTEM (ABOLITION ORDINANCE
ACT, 1975): The “Bonded Labour System (Abolition Ordinance, 1975)” would
apply to the present contract. The contractors shall duly observe the provisions
thereof.
47. SAFE METHODS:
47.1 The Contractor shall at all times, adopt such safe methods of working as will
ensure safety of structures, equipment and labour. Safety rules that should
be adhered to are given as guidelines in Annexure C. If at any time, the
Railway finds the safety arrangements inadequate or method of working
unsafe, the Contractor shall take immediate corrective actions as directed
by the Engineer's representative. Any directions in the matter shall in no
47.3 The liability arising out of accidents, if any, to persons will be met by the
contractors and the Railway will not be responsible for any damage or
compensation thereof. The contractor shall follow the provisions laid down
in Contract Labour Act, 1972.
47.4 The contractor shall be entirely responsible for ensuring safety of his labour,
vehicles, plant or equipment while working along or near the track and
highways and shall programme his working so as not to interfere with the
movement of trains and road traffic. No extra payment shall be allowed to
the contractor for all safety precautions to be observed during the execution
of the work. The cost of all such precautions shall be deemed to be included
in the rates for all items of the schedule.
48.2 It shall be obligatory for the tenderer to submit his programme of work and
time schedule as to how he proposed to complete the work within stipulated
time.
48.3 Within 10 days of the acceptance of the tender and before the work is
commenced, the contractor shall have to submit a detailed programme for
each major element of the work for approval of the Engineer. The
programme shall clearly provide for and indicate the time required for the
preliminaries before starting the work and shall indicate the dates of
commencement and completion of the various sections of the work.
48.5 If the work does not commence within specified date of starting or if at the
subsequent time the rate of execution falls below the specific programme as
indicated above, the Railway Administration will have the power to
determine the end of the contract at any stage without incurring any liability
on the part of the Railway Administration for any sort of compensation for
the money invested by the contractor (s) or the loss incurred by him/them
due to such termination of the contract. In all cases of incomplete work,
either by termination of contract by the Railway Administration under
consideration stated above or due to failure on the part of contractor(s) to
complete the work within stipulated date of completion of Agreement the
Railway shall be entitled to :-
i) Forfeit the whole of such portion of the security deposit as it may
consider
ii) Encash the bank guarantee furnished as Performance Guarantee.
iii) Execute the balance work independently without risk and cost of the
original contractor. The original contractor however will be debarred from
participating in the tender for executing the balance work. In case the
failed contractor is a Joint Venture or a partnership firm , then each
member / partner of such firm would be debarred from participating in
the tender for the balance work either in his/her individual capacity or as
a partner of any other Joint venture/ partnership firm. The contractor
cannot make any legal claims against the same.
49.2 It shall be ensured that the works are carried out according to the agreed
programme and no change are made except with the prior approval or at
the instance of the Engineer.
50.2 However, for a zonal work, the maintenance period shall be three months
for each work order.
51 VARIATION IN QUANTITIES:
(b) For the first 15% increase in the value beyond 25% of agreement value, the
rates will have a reduction of 2% in the incremental value of the agreement
and for the next 10% increase in the value, the rates will have an additional
reduction of 2% in the further incremental value of the agreement.
(c) Execution of the quantities beyond (+) 50% of the overall agreement value will
not be permitted and if found necessary by the Railway administration will
only be, through fresh tenders or by negotiating fresh rates with the
contractor.
.
55. PRICE VARIATION CLAUSE: No.PVC clause shall be applicable in this contract
56. USE OF CONTRACTOR'S VEHICLE & EQUIPMENTS BY THE RAILWAY
DURING EMERGENCIES
All the available vehicles and equipments of the contractor can be drafted by the
Railway Administration in case of accidents/natural calamities involving human
lives. The payment for such drafting shall be made according to the rates as shall
be fixed by the Engineer. However, if the contractor is not satisfied with the
decision of the Engineer in this respect he may appeal to the Chief Engineer within
30 days of getting the decision of the Engineer, supported by analysis of the rates
claimed. The Chief Engineer’s decision after hearing both the parties in the matter
would be final and binding on the contractor and the Railway”.
57. SEASON TICKETS FOR THE LABOURERS OF CONTRACTOR IN MUMBAI AREA
The contractor will pay and purchase season tickets/ticket for the labourer/s for
traveling by train from place of living to place of work and back on Mumbai area
as per Railway’s extant rule.
58. NONCOMPLAIANCE WITH INSTRUCTIONS/DIRECTIVES OF ENGINEER’S
REPRESENTATIVE.
The contractor shall always comply with the instructions/directives issued by the
Engineer’s representative from time to time. In event of any non-compliance with
such instructions/directives, apart from and in addition to other remedies available
to the Railway. The Engineer’s representative may employ Railway’s workmen with
necessary equipments and recover cost of such deployment at the rate of Rs. 20
per man hour employed by the Railway irrespective of the type & grade of the
Railway employee in addition to the hire charges for the equipments used. The
decision of the Railway Engineer in this regard will be final & binding upon the
contractor.
59. PERSISTANT NON-COMPLAIANCE OF INSTRUCTIONS/DIRECTIVES OF
ENGINEER’S REPRESENTATIVE.
If the contractor does not comply with the instructions/directives of the Engineer’s
representative, apart from and in addition to other remedies available to the
Railway and without prejudice to the Railway’s rights in this regard, the Engineer’s
representative (which for the purpose of this clause shall exclude the Sectional
Engineer) can suspend the contractor’s work till the Engineer’s representative is
satisfied that the contractor is in a position/will comply with the
instructions/directives issued by the Engineer’s representative. The decision of the
Railway Engineer’s representative in this regard will be final and binding upon the
contract. The contractor shall not have any claim what so ever against the Railway
for such short/long term suspension of the contract work. During the period of
suspension, the contractor shall not in any manner attempt to carry out the work at
works site. Any such attempt by contractor will be deemed to be an unauthorised
62. Arbitration clause under para 63 & 64 of GCC amended vide correction slip No.3 is
reproduced below :-
CLAUSE 63 & 64 OF GENERAL CONDITIONS OF CONTRACT (GCC) BEEN
REVISED IN VIEW OF THE PROMULGATION OF THE ARBITRATION
CONCILIATION ORIDINANCE 1996.REVISED ARBITRATION CLAUSE IS AS
FOLLOWS: -
63 Matters finally determined by the Railway – All the disputes and differences of
any kind whatsoever arising out of or in connection with the contract, whether during
the progress of the work or after its completion and whether before or after the
determination of the contract, shall be referred by the contractor to the GM and the
GM shall within 120 days and after receipt of the Contractor’s representation make
and notify, decisions on all matters referred to by the contractor in writing provided
that matters for which provision has been made in clauses 8 (a), 18, 22(5), 39, 43(2),
45 (a), 55, 55-A(5), 57, 57A, 61 (1), 61(2) and 62 (1) to XIII (b) of General Conditions
of Contract or in any clause of the special conditions of the contract shall be deemed
as excepted matters (matters not arbitral) and decisions of the Railway authority,
thereon shall be final and binding on the contractor provided further that ‘excepted
matters’ shall stand specifically excluded from the purview of the arbitration clause.
c) The Railway shall submit its defence statement and counter claim(s), if any,
within a period of 60days of receipt of copy claims from Tribunal thereafter
unless otherwise extension has been granted by Tribunal.
(d) Place of arbitration: The place of arbitration would be within the geographical
limits of the division of the Railway where the cause of action arose or the
headquarters of the concerned Railway or any other place with the written
consent of both the parties. 64(1)(iii) No new claim shall be added
during proceedings by either party. However, a party may amend or
supplement the original claim or defence thereof during the course of arbitration
proceedings subject to acceptance by Tribunal having due regard to the delay
in making it.
64(1) (iv)
If the contractor(s) does/do not prefer his/their specific and final claims in writing,
within a period of 90 days of receiving the intimation from the Railways that the final
bill is ready for payment, he/they will be deemed to have waived his/their claim(s)
and the Railway shall be discharged and released of all liabilities under the contract
in respect of these claims.
64(2)
Obligation during pendancy of arbitration – work under the contract shall, unless
otherwise directed by the Engineer, continue during the arbitration proceedings and
not account of such proceedings provided however, it shall be opened for Arbitral
Tribunal to consider and decide whether or not such work should continue during
arbitration proceedings.
64(3)(a) (i)
In cases where the total value of all claims in question added together does not
exceed Rs. 10,00,000/- (Rs. Ten lacs only) the arbitral tribunal shall consist of a
sole arbitrator who shall be a gazetted officer of Railway not below JA grade
nominated by the General Manager. The sole arbitrator shall be appointed within 60
days from the day when a written and valid demand for arbitration is received by
GENERAL MANAGER, WESTERN RAILWAY..
64(3) (a) (ii)
In cases not covered by Clause 64 (3) (a) (i), the Arbitral Tribunal shall consist of a
panel of three Gazetted Rly. Officers not below JA Grade, or 2 Rly. Gazetted officers
not below JA Grade and a retired Railway officers not below the rank of SAG officer,
as the arbitrators. For this purpose, the Railway will sent a panel of more than 3
names of Gazetted Rly. Officers of one or more departments, of the Rly. which may
64(3) (a) (iv) The arbitral Tribunal shall have power to call for such evidence by
way of affidavits or otherwise as the Arbitral shall think proper and it shall be the duty
of the parties hereto to do or cause to be done all such things as may be necessary
to enable the Arbitral Tribunal to make the award without any delay. The arbitral
tribunal should record day to day proceedings. The proceedings should normally be
conducted on the basis of documents & written statements.
64(3)(b)(iii)
A party may apply to tribunal within 30 days of receipt of award to make an
additional award as to claims presented in the arbitral proceeding but omitted from
the arbitral award.
64.4
In case of the Tribunal, comprising of three members, any ruling or award shall be
made by majority of member of Tribunal. In the absence of such a majority the
views of the Presiding Arbitrator shall prevail.
64.5
Where the arbitral award is for the payment of money for interest shall be payable
on whole or any part of the money for any part of the money for any period till the
date on which the award is made.
64.6
The cost of arbitration shall be borne by the respective parties. The cost shall
inter-alia includes fees of the arbitrator (s) as per the rates fixed by the Rly.
Administration from time to time & the fee stall be borne equally by both the parties,
further the fee payable to the arbitrator(s) would be governed by the instructions
issued on the subject by Railway Board from time to time irrespective of the fact
whether the arbitrator(s) is/are appointed by the railway administration or by the
court of law unless specifically directed by Hon’ble court /otherwise on the matter.
64.7
Subject to the provisions of the aforesaid Arbitration and conciliation Act, 1996 and
the rules there under and any statutory modifications thereof shall apply to the
arbitration proceedings under this clause.
-End of amended clause No.63 & 64 of GCC-
ANNEXURE - A
STATEMENT OF DEVIATION
(Pl .refer Cl.3 of special conditions part-I (General) of the Tender documents)
3. Scaffolding or staging more than 3.5 meters above the ground or floor, swung or
suspended from an overhead support or erected with stationary support shall have
a guard rail properly attached bolted, braced and otherwise secured at least 1
meter high above the floor or platform or staging and extending along the entire
length thereof with only such opening as may be necessary for the delivery of
materials. Such scaffolding or staging shall be so fastened as to prevent it from
swaying from the building or structure.
5. Safe means of access shall be provided to all working platform and other working
places. Every ladder shall be securely fixed. No portable single ladder shall be
over 10 metres in length while the width between side rails in swung ladder shall in
no case be less than 300 mm for ladders upto and including 3.5 metres in length.
For longer ladders this width should be increased by at least 20 mm for each
additional metre of length. Uniform steps spacing shall not exceed 300 mm.
Adequate precautions shall be taken to prevent danger from electrical
equipments. No materials on any of the sites of work shall be so stacked or placed
as to cause danger or inconvenience to any persons or the public. The contractor
shall provide all necessary fencing and lights to protect the public from accident
and shall be bound to bear the expenses of the defense. of every suit, action or
other proceeding at Law that may be brought by any person for injury sustained
owing to neglect of the above precautions and to pay any damages and cost
which may be awarded in any suits, action or proceedings to any such persons or
which may with the consent of the contractor be paid to compromise any claim by
any such persons.
6. Demolition: Before any demolition is commenced and also during the process of
the work:
a) All roads and open areas adjacent to the work site shall either be closed or
suitably protected;
b) No electric cable or apparatus which is liable to be a source of danger over a
cable or apparatus used by the operator shall remain electrically charged;
c) All practical steps shall be taken to prevent danger to persons employed from
risk of fire or explosion or flooding;
d) No floor, roof or other part of the building shall be so overloaded with debris
or materials as to render it unsafe.
In addition,
8. The contractor shall submit the methodology proposed to be adopted for execution
of works for approval of the Railway Engineer with a view to ensure safety of
trains, passengers & workers and he shall also ensure the methods and
arrangements are actually available at site before start of work and contractor’s
supervisors and workers have clearly understood the safety aspects and
requirements to be adopted / followed while executing the work.
9. The contractor shall maintain an assurance register at each site, which shall be got
signed by both Railway supervisor as well as contractor’s supervisor in token of
their having understood the safety precautions to be observed at site.
6. This Guarantee will not be discharged due to the change in the constitution of the
bank or the Contractor (s) Supplier (s).
For ______________________
(indicate the name of Bank)
In presence of :
1. Signature _____________
Name of Block letters:______________
Address :______________
2. Signature ___________
Name in Block letters:__________________________
Address: _______________
ANNEXURE - ‘E’
I/WE THE UNDER SIGNEG HEREBY SOLEMNLY DECLARE AND CERTIFY THAT I
/WE DO NOT HAVE ANY OF OUR RELATIVE/RELATIVES EMPLOYED IN THE
WESTERN RAILWAY (ENGINEERING DEPARTMENT) EXCEPT THE NAMES
MENTIONED HEREIN UNDER :
1………………..
2………………..
3………………..
AND SO ON ………….
1) Hand receipts with date, time, truck no. or wagon no. etc shall be collected at
site from the Railway Engineer’s/representative for proof of quantity of garbage,
debris, muck, earth rubbish lifted.
2) A statement in following Performa duly signed by Engineer’s representative
submitted to the Railway Engineer by the contractor on the day following when
garbage was lifted.
1) A minimum of 200 cum of muck will have to be removed by the contractor for
lifting by muck special train in a total block of 4 hours for leading and unloading.
In any block contractor shall deploy atleast 100 labour. The penalty for short
labour shall be 30/- per head short.
2) The penalty for short fall in removal of muck shall be Rs.40/- per Cum shortfall
in proportion of block granted. For example if block is granted for 6 hours he
must have a progress of 300 cum and if in actual he goes a progress of 270
Cum the penalty shall be Rs.1200/- in this case. The penalty shall be calculated
Name of Work: CCG-VR Sec- Removal of garbage muck etc. and disposal of the
same beyond railways limit by contractor’s own trucks/MKC’s between the section of
BA-STC.
Schedule "C" (NS items)
Name of work: - CCG-VR Sec- Removal of garbage muck etc. and disposal of the
same beyond railways limit by contractor’s own trucks/MKC’s between the section of
BA-STC.
OFFER SHEET
Schedule Tenderer’s Total amount (in figure and words both)
In Figures In words
1 2 3
Schedule "C" NS
Items
Total
Note: -
1. The quantities shown in the above schedule are approximate and are as a
guide to give the tenderer(s) an idea of quantum of work involved.
2. The Railway reserves the right to increase/decrease and /or delete or includes any of
the quantities given above as per the requirement at site.
3. The tenderer(s) shall quote his/their rates against each NS items. The rates against
each NS items shall be quoted by the tenderer separately in the tender schedule
itself and calculate the total amount of each item and total of the NS items shall be
shown iin the offer sheet in words and figures against Schedule "C" NS Items.
4. In case of any discrepancy between the rates in figures and words, the rates
mentioned in words will be accepted.
5. Any discrepancy resulting due to rates per unit and amount due to
calculation mistakes the rate entered in words / figures will be treated as
final.