The list of quantities of components, ingredients, and materials required to produce a product is the
engineering change notice. bill-of-materials. master schedule. purchase order. ____________ allows a segment of the master schedule to be designated as "not to be rescheduled."
Regenerative MRP Time fence System nervousness Pegging A lot-sizing technique that generates exactly what was required to meet the plan is
economic order quantity. lot-for-lot. the Wagner-Whitin algorithm. part period balancing. Breaking up the order and running part of it ahead of schedule is known as
operations splitting. lot splitting. overlapping. pegging. The difference between a gross material requirements plan (gross MRP) and a net material requirements plan (net MRP) is
the net MRP includes consideration of the inventory on hand, whereas the gross MRP does not.
the gross MRP includes consideration of the inventory on hand, whereas the net MRP does not.
the gross MRP doesn't take taxes into account, whereas the net MRP includes the tax considerations.
the gross MRP may not be computerized, but the net MRP must be computerized. A phantom bill-of-materials is a bill-of-materials developed for
a module that is a major component of a final product. a final product for which production is to be discontinued. the purpose of grouping subassemblies when we wish to issue "kits" for later use. a subassembly that exists only temporarily. Which of the following lot-sizing techniques is likely to prove the most complex to use?
part period balancing (PPB) the Wagner-Whitin algorithm economic order quantity (EOQ) lot-for-lot When a bill-of-materials is used in order to assign an artificial parent to a bill-of- materials, it is usually called a
pick list. planning bill-of-materials. phantom bill-of-materials. modular bill-of-materials. The operations manager has several tools available to deal with MRP system nervousness. Those tools are
time fences and pegging. buckets with back flush. pseudo bills and kits. net and gross requirements. An MRP system that provides feedback to the capacity plan, master production schedule, and production plans is called
load report. system nervousness. lot-sizing. closed-loop MRP. A time-phased stock-replenishment plan for all levels of a supply chain is called
ERP. MRP II. MRP. DRP. Which of the following is an advantage of ERP?
requires major changes to the company and its processes is simple enough that companies have an easy time adjusting to it creates commonality of databases is very inexpensive to purchase Use the product structure tree and the inventory records to determine how many item Cs should be ordered in order to produce 20 phones. Item On- Hand A 5 B 5 C 5 D 25 E 4 F 20
105 120 115 97 Use the product structure tree and the lead time information (in weeks) to determine when an order for Fs should be placed to deliver phones in week 10 if the phones require 2 weeks to assemble. Assume there is no starting inventory for any component or end item. Item Lead Time A 2 B 1 C 3 D 2 E 3 F 2
week 3 week 2 week 5 week 4 A(n) ________ system provides feedback to the capacity plan, master production schedule and production plan. load closed-loop Wagner-Whitin efficient consumer response Which of these pieces of information isNOTcontained in a bill of material?
raw materials to be used quantities of components physical dimensions lead times A report that shows the resource requirements in a work center for all currently assigned work as well as all planned and expected orders is a
MRP II report. back flush report. closed-loop report. load report.