Professional Documents
Culture Documents
Planned
cost
Setup
Machine
Labour
Cleaning
Painting
Electricity
180/120/240/180/180/180/-
10x3/5x2/5x4/5x3/5x3/5x3/-
943000
943001
943002
943003
943004
943005
3/2/4/3/3/3/-
10
5
5
5
5
5
Total
planned
cost
30
10
20
15
15
90
Costing Sheet
Costing sheet cosisting of control parameters such as
Costing Type
Valuation Variant
Which valuate the internal and external material
Date Control
Which specifies which date BOM and Routing to be used in the cost estimate
Qty structure control
Transfer control
60/-
The cost estimate is calculated with quantity structure. Material price is calculates as you said it is taken from BOM.
The activity cost is calculated as below.
From work center the formulas as per your standard value key. ( ex setup machine and labour ) are taken and it is multiplied with the time give
Totally the cost for any activity is calculated.
(Otherwise First Create Secondary Cost Element (T.Code KA06), Assign this Sec. Cost Element to your new Activity Type, then K
Assign Activity Type in Work Center Costing Tab & Assign Your Formula)
You can assign max. 6 Standard Values to your WC, I.e If you want to capture Power & Fuel Consumption for an Operation you can
abour ) are taken and it is multiplied with the time given in routing. From there total hrs required for any activity is calculated. This total hrs required for any acitivity is
WH)
e for Power.
ec. Cost Element to your new Activity Type, then KP26 " Change Activity / Price Planning"
ower & Fuel Consumption for an Operation you can have both parameters set as per above
is calculated. This total hrs required for any acitivity is multiplied by the charge rate hrs rate given in KP 26 for that acitivty type.
Routing
Activity type Group
Activity Type
Value (Qty)
A100
Setup
10
A200
Machine
5
A300
Labour
5
A400
Cleaning
20
A500
Painting
20
A600
Power
20
CK11N
A.Type
A200
A100
A300
A400
A500
A600
Fixed Pri
180.00
120.00
240.00
120.00
120.00
130.00
ACT_GR
Unit
15M
15M
15M
Min
Min
KWH
KP26
Total (Value X Unit)
150 Min
75 Min
75 Min
20 Min
20 Min
20 KWH
CK11N Calculation
Variable Pri Fixed Val
200.00
450.00
150.00
150.00
300.00
300.00
150.00
2,400.00
150.00
2,400.00
150.00
2,600.00
Variable
500.00
187.50
375.00
3,000.00
3,000.00
3,000.00
In Hr/Min
2.5 Hrs
1.25 Hrs
1.25 Hrs
20 Min
20 Min
20 KWH
Tot Value
950.00
337.50
675.00
5,400.00
5,400.00
5,600.00
OP7B
OP19
OP54
http://www.erpgreat.com/production/set-parameter-and-work-center-formula.htm
Variable Price
150.00
200.00
300.00
150.00
150.00
150.00
Cost centerS_ALR_87013611
info
KL01