Professional Documents
Culture Documents
Introduction
Learning outcomes
CONSTRUCTION
CONTRACTS
IAS 11
2.
3.
4.
5.
14/08/2014
IAS11
Calculate contract revenue
Calculate contract costs
Explain how to recognize profit on
construction contract
Prepare financial statement extracts
for disclosure of construction contracts
14/08/2014
Definition of a construction
contract
,roads
14/08/2014
e contract plus
Variations in contract work and claims to
be added if
- it is probable that they will result in
revenue
- they are capable of being reliably measured
- Penalties arising from delays reduce the
contract price
14/08/2014
Types of Contracts
14/08/2014
contract(Material, labour)
Costs that are attributable to contract
14/08/2014
8/14/2014
14/08/2014
Determining the
stage of completion of a contract
percentage of completion
may be
arrived at:
1. proportion of costs incurred compared
estimated total contract costs.
2. 2.Survey
of
work performed ;
proportion of work certified to date
compared to total revenue
14/08/2014
14/08/2014
10
14/08/2014
14/08/2014
12
8/14/2014
Question
1.
Solution a
Year
2007
2008
2009
Cost incurred (K) 2,080,000
1,820,000
1,300,000
Billings
2,000,000
1,800,000
2,200,000
(work certified)
Collections
1,600,000 1,700,000
2,700,000
a) Calculate the percentage of completion if the company uses
the cost incurred to total cost method
b)Calculate the percentage of completion if the company uses
the cost incurred to total cost method
14/08/2014
13
14/08/2014
Solution b
2009
33%
14/08/2014
3,800,000
6000,000
63%
6000,000
6000,000
100%
15
14/08/2014
16
14/08/2014
14
17
14/08/2014
18
8/14/2014
Question
Solution
14/08/2014
19
14/08/2014
20
cash/accounts
payable/inventory
21
14/08/2014
Question
In January 2007 CC Construction Company was awarded
a contract to construct a clinic with a total price of K6,
000,000. Total cost for the contract were estimated to
be K5, 200,000.The contract was completed over a 3 year
period. The cost data for the contract is given below
Year
2007
2008
2009
Cost incurred (K)
2,080,000
1,820,000
1,300,000
Billings
2,000,000
1,800,000
2,200,000
Collections
1,600,000 1,700,000
2,700,000
c) Calculate the cost to be recognized in each of the
years
23
22
Solution
1.
14/08/2014
2009
(6mx1)-(2.4+2.1)
1,500,000
14/08/2014
2008
( 6m x0.75)-2.4m
2,100,000
2007
2008
2009
total Cost 5,200,000 5,200,000 5,200,000
% complete 40%
75%
100%
Cost
2,080,000 3,900,000 5,200,000
Recognized
previously
(0 )
(2,080,000) (3,900,000)
Cost
this year
2,080,000 1,820,000
1,300,000
14/08/2014
24
8/14/2014
1. Profit expected
2. Loss expected
25
14/08/2014
26
Question 1d
14/08/2014
27
14/08/2014
solution
Question 2
14/08/2014
28
CC Co is a civil engineering company. It started work on 4 road construction projects during the year
ended 31 December 2011. The following figures relate to those projects at the end of the reporting
period.
1
Contract price
9,000
8,000
3,420
2,000
Costs incurred
1,400
2,900
2,700
950
5,600
5,500
450
600
certified to date
2,800
3,600
2,280
1,000
Progress billings
2,600
3,400
1,750
1,150
Estimated costs
To completion
Value of work
29
14/08/2014
30
8/14/2014
Question 2
Solution
price
Total cost
Profit
31
Solution
14/08/2014
4
2,000
1,550
450
14/08/2014
32
4
1,000
2,000
33
14/08/2014
34
1. Gross
amount
due
from
customers represent an assetAccounts receivable
2. Gross amount due to customers
represent a liability- Deferred
income or unearned revenue
IAS 11 CONSTRUCTION CONTRACTS
3
3,420
3,150
270
Solution
14/08/2014
8,000
8,400
(400)
9,000
6,800
2,200
35
liability is:
Costs incurred to date
X
Add recognized profit
X
Less recognized lose
(X)
Less progress billing
(X)
Add bills not paid
X
Gross amount due to/from customer (X) X
Note: This represents unbilled revenue. Which will
be shown under
trade receivables
14/08/2014
IAS 11 CONSTRUCTION CONTRACTS
36
8/14/2014
Question
14/08/2014
37
Solution2
2007
39
2008
14/08/2014
40
2009
14/08/2014
38
1.
Solution
Question 1e
14/08/2014
14/08/2014
41
14/08/2014
42
8/14/2014
Income Statement
Revenue
Costs
Profit or loss
Calculated according to the rules given
above.(stage of completion)
Note :only Revenue and costs for the
period under review
14/08/2014
43
14/08/2014
X
X
(X)
(X)
3 Revenue
14/08/2014
45
14/08/2014
46
44
for project
Using the percentage completed to date (or
other formula given in the question),
calculate sales revenue attributable to
the contract for the period ( percentage
complete total contract value, less
revenue taken in previous periods).
14/08/2014
47
14/08/2014
48
8/14/2014
14/08/2014
Any questions
49
14/08/2014
50