Professional Documents
Culture Documents
cost for all external work. With the current low level of work and high fixed
cost, finishing cannot attract external sales due to cost.
In an effort to gain control of the true cost drivers of the business, the
manager of the finishing operation has implemented activity-based costing.
Tables 2 and 3 project the cost for products and volumes for one plating
operation. The problem that the finishing manager now faces is that the
manufacturing departments are about to send the 12-inch and 18-inch work
to an outside shop due to lower costs.
In implementing ABC, the manager thinks he has truly identified the proper
system. The larger parts tend to run in smaller lot sizes and generate more
paperwork. Smaller parts tend to be run in larger lot sizes and generate less
paperwork.
In a recent meeting with the management of the manufacturing department
and profit centers, it was stated that the installation of ABC is in direct
conflict with the change in the mix of work from small part to large parts and
the need to run smaller lot sizes. The manufacturing department and profit
centers would like to pursue just in time manufacturing and further reduce
the lot sizes for both small and large parts. During this meeting, the profit
centers and manufacturing departments said the impplementation of ABC
would force them to move their work out of the finishing department to
outside shops.
Table 1 Finishing Annual Cost Structure
Annual Cost
Fixed
asset
$400,000 $4,000,000 machine purchased 2
depreciation
years ago
Tank operation costs
250,000 Cost to operate tanks-fixed cost,
not volume dependent
Tank material cost
50,000 Cost
to
operate
tanks$0.0007575/inch
Variable labor cost
210,000
$910,000
3 parts
1,000,000
$0.50
6 parts
200,000
1.00
12 parts
50,000
1.20
18 parts
100,000
1.50
*this volume of work uses only 30% of capacity
$500,000
200,000
60,000
150,000
$910,000
$0.31
1.00
2.00
3.00
Activity-Based
Cost
$310,000
200,000
100,000
300,000
$910,000
$0.30
1.10
0.90
1.20
Outside Cost
$300,000
220,000
45,000
120,000
$685,000
Required:
Based on the current situation, what should you do, as a management
accountant, to help the manager solve that problem? Please make a
comprehensive analysis based on qualitative and quantitative aspects.
Explore your knowledge in management accounting tools that you learned in
the class.
Solution:
This case study ilustrates that poorly designed ABC system trying to
recover the cost of excess capacity can fail.
A. The problem is they are trying to recover a sunk cost fixed asset
depreciation of $400,000. Because volumes have fallen, the original
decision to acquire this much capacity turns out to have been wrong.
They should take a one-time charge profits by writing off some or most of
the $400,000 machine. This will then lower unit cost. Other issues include:
I.
II.
III.
IV.
Both the old absorption and new ABC accounting systems are
sending the wrong signal for short run decisions. Both system are
signaling higher cost and thus the apparent necessity to raise price.
Given the high fixed cost and decreasing volumes, this is an
incorect inference.
V.
B. In reviewing the data provided in table 2, the apperent cost drives have
been identified and properly allocated to the parts using ABC costing.
What is not apparent is that the unitized cost are misleading in the first
place. Unitized the fixed cost will cause the apparent profitability of parts
to vary with volume. This unitization is misleading and should be avoided.
Since the firm has so much excess capacity, the opportunity cost of this
capacity is close to zero. Thus, none of the depreciation on the plant
should
be
charged
to
products.
the details of the cost drives are not provided, although one can see
shifts in parts costs of up to 100 percent. The question to be asked is what
effect the changes in cost will have on the workload and whether the
costs of these drives should be reduced. If no action or effort is placed on
using the data obtained from the ABC system to reduce the cost of the
elementss, then why incur the expense of implementing ABC? The cost
and benefits of the system need to be evaluated.
C. If management is gaining a better understanding of the cost drives of the
business and implementing cost reduction activities, and the reductions
outwigh the cost of ABC, then they have not made a mistake.
they have made a mistake in the implementing process. The ABC
costing system is aimed at decision managment. However, the finishing
departement did not understand the implications of the signals that ABC
cost send to the rest of the firm (decision control) for short-run decisions.
If the departement management operated the ABC system in paralel to
the old system then they could have the information required to reduce
costs and not send the misleading signals within the firm.