COSTO DE MATERIALES: NOTAS:


CEMENTO ARENA GRAVA AGUA 1 ESTA TABLA ES ÚTIL PARA OBRAS PEQUEÑAS DONDE HAY QUE ELABORAR EL CONCRETO EN OBRA
PRECIO x TON: PRECIO x CAMIÓN PRECIO x CAMIÓN PRECIO x PIPA 2 LLENAR SÓLO LOS CAMPOS EN COLOR AMARILLO
20 Bultos de 50 Kg. DE 7M3 DE 7M3 DE 4000 LTS 3 LOS COSTOS OBTENIDOS SON SÓLO DE MATERIALES
$2,200.00 $2,450.00 $2,450.00 $18.00 4 CADA QUIEN DEBERÁ AGREGAR SUS COSTOS DE OPERACIÓN E INDIRECTOS
PRECIO x BULTO: 5 ESTA TABLA DE COSTOS PUEDE USARSE PARA FINES DE PLANEACIÓN DE COMPRA DE MATERIALES Y ANÁLISIS
DE 50 KG PRECIO x M3: PRECIO x M3: PRECIO x M3: 6 LAS PROPORCIONES DE LA TABLA FUERON TOMADAS DE:
$110.00 $350.00 $350.00 $4.50 "COSTO Y TIEMPO EN EDIFICACIÓN"
DESPERDICIO: DESPERDICIO: DESPERDICIO: DESPERDICIO: CARLOS SUÁREZ SALAZAR
3% 8% 8% 30% LIMUSA - NORIEGA EDITORES MÉXICO 1997
1.03 1.08 1.08 1.30 TERCERA EDICIÓN
COSTO CON DESP. COSTO CON DESP. COSTO CON DESP. COSTO CON DESP.
$2,266.00 $378.00 $378.00 $5.85

CLASIFICACIÓN AGREGADO CEMENTO BULTOS ARENA GRAVA AGUA $$$ x M3 CON M3 CONCRETO COSTO AL CANTIDAD DE CANTIDAD DE CEM CANTIDAD DE CANTIDAD DE CANTIDAD DE COSTO AL

F´C= REVENIMIENTO MÁXIMO TONELADA DE 50 KG M3 M3 M3 DESPERDICIO REQUERIDOS: CONSTRUCTOR CEMENTO TON. BULTOS DE 50 KG ARENA EN M3 GRAVA EN M3 AGUA EN M3 CLIENTE

100 kg/cm2 8 A 10 CM 3/4" 0.260 5.20 0.500 0.680 0.195 $1,036.34 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
1 1/2" 0.254 5.08 0.470 0.700 0.190 $1,018.94 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
FIRMES Y 12 A 15 CM 3/4" 0.286 5.72 0.500 0.680 0.215 $1,095.37 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
PLANTILLAS 1 1/2" 0.280 5.60 0.470 0.700 0.210 $1,077.97 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00

150 kg/cm2 8 A 10 CM 3/4" 0.323 6.46 0.480 0.670 0.210 $1,167.85 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
1 1/2" 0.308 6.16 0.450 0.700 0.200 $1,133.80 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
FIRMES, DALAS 12 A 15 CM 3/4" 0.354 7.08 0.480 0.670 0.230 $1,238.21 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
Y CASTILLOS 1 1/2" 0.338 6.76 0.450 0.700 0.220 $1,201.90 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00

200 kg/cm2 8 A 10 CM 3/4" 0.355 7.10 0.470 0.650 0.195 $1,228.93 1.00 $1,228.93 0.36 7.10 0.47 0.65 0.20 $1,474.72
1 1/2" 0.337 6.74 0.440 0.680 0.185 $1,188.08 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
LOSAS DE 12 A 15 CM 3/4" 0.391 7.82 0.470 0.650 0.215 $1,310.62 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
ENTREPISO 1 1/2" 0.373 7.46 0.440 0.680 0.205 $1,269.78 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00

250 kg/cm2 8 A 10 CM 3/4" 0.423 8.46 0.465 0.640 0.190 $1,377.32 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
PISOS ESTRUCTURALES, 1 1/2" 0.400 8.00 0.435 0.670 0.180 $1,325.14 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
COLUMNAS, DADOS, 12 A 15 CM 3/4" 0.467 9.34 0.465 0.640 0.210 $1,477.14 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00
ZAPATAS Y TRABES 1 1/2" 0.445 8.90 0.435 0.670 0.200 $1,427.23 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 $0.00