Professional Documents
Culture Documents
The focus of O-T-S is the development and delivery of training programs for electric
power system operations personnel.
kV difference in voltage across the open circuit breaker, a large Mvar flow would suddenly occur
upon closing. The allowable voltage magnitude differences across the open circuit breaker are
system specific. However, for general guidance, a difference of a few percent is unlikely to cause
any serious problem.
1.1.2 Frequency Synchronizing Variable
If the frequencies on either side of an open circuit breaker are not matched prior to closing, a
sudden change in MW flow will appear across the circuit breaker as it is closed. The sudden MW
flow change is in response to the initial frequency difference as the system seeks to establish a
common frequency once the circuit breaker is closed. The allowable frequency difference is again
system specific. However, a general guideline would be to have the frequencies within 0.1 Hz of
each other prior to closing.
1.1.3 Phase Angle Synchronizing Variable
The third synchronizing variable - and likely the most important of the three - is the voltage phase
angle difference. If the phase difference between the voltages on either side of the open circuit
breaker is not reduced to a small value, a large MW flow increase will suddenly occur once the
circuit breaker is closed. The voltage phase angle difference is the difference between the zero
crossings of the voltages on either side of the open circuit breaker. Ideally, the voltage phase
angle should be as close to zero degrees as possible before closing the circuit breaker.
1.2 Synchronizing Examples
The importance of synchronizing cannot be overstated. All system operators should understand the
theory and practice of synchronizing. If two power systems are synchronized via an open circuit
breaker, and the synchronizing process is not done correctly, generators can be severely damaged.
Two scenarios for synchronizing follow to further describe the synchronizing process.
1.2.1 Scenario #1: Synchronizing Two Islands
The first scenario assumes that two islands are about to be connected together using the open
circuit breaker as illustrated in Figure 1. The two islands, since they are independent electrical
systems, will have different frequencies so all three of the synchronizing variables must be
monitored to ensure they are within acceptable limits prior to closing the open circuit breaker.
The system operators for the two islands will likely have to adjust generator MW output levels (or
adjust island load magnitudes) in one or both islands to achieve the desired adjustment in
frequencies and phase angles. Voltage control equipment (reactors, capacitors, etc.) may also be
used as necessary to change voltage magnitudes to within acceptable levels.
Figure 1
Synchronizing Two Islands
1.2.2 Scenario #2: Establishing the Second Tie
Once the first transmission line is closed interconnecting the two islands, the frequency will be
the same in the two areas. Therefore, one of the three synchronizing variables (the frequency) is
no longer a factor. However, as illustrated in Figure 2, the other two synchronizing variables must
still be monitored. Generation and/or voltage control equipment may be to be utilized to ensure
the phase angle and voltage magnitude differences are within acceptable limits prior to closing
the second circuit breaker. This process should be easier than closing the first transmission line
(Scenario #1) as frequency is no longer a factor.
Figure 2
Establishing the Second Transmission Tie
Figure 3
Synchroscope in a Synch Panel
Figure 4
Synchronizing System for a Substation Breaker
Operations-Training-Solutions
The focus of O-T-S is the development and delivery of training programs for electric
power system operations personnel.
Transmission lines also utilize reactive power to support their magnetic fields. The magnetic field
strength is dependent on the magnitude of the current flow in the line and the line's natural
inductive reactance (XL). It follows then that the amount of Mvar used by a transmission line is a
function of the current flow and inductive reactance. In equation form the Mvar used by a
transmission line is:
A transmission line's surge impedance loading or SIL is simply the MW loading (at a unity power
factor) at which the line's Mvar usage is equal to the line's Mvar production. In equation form we
can state that the SIL occurs when:
If we take the square root of both sides of the above equation and then substitute in the formulas
for XL (=2pfL) and XC (=1/2pfC) we arrive at:
The term
significance of the surge impedance is that if a purely resistive load that is equal to the surge
impedance were connected to the end of a transmission line with no resistance, a voltage surge
introduced to the sending end of the line would be absorbed completely at the receiving end. The
voltage at the receiving end would have the same magnitude as the sending end voltage and
would have a phase angle that is lagging with respect to the sending end by an amount equal to
the time required to travel across the line from sending to receiving end.
The concept of a surge impedance is more readily applied to telecommunication systems than to
power systems. However, we can extend the concept to the power transferred across a
transmission line. The surge impedance loading or SIL (in MW) is equal to the voltage squared (in
kV) divided by the surge impedance (in ohms). In equation form:
.
Note in this formula that the SIL is dependent only on the kV the line is energized at and the line's
surge impedance. The line length is not a factor in the SIL or surge impedance calculations.
Therefore the SIL is not a measure of a transmission line's power transfer capability as it does not
take into account the line's length nor does it consider the strength of the local power system.
The value of the SIL to a system operator is realizing that when a line is loaded above its SIL it
acts like a shunt reactor - absorbing Mvar from the system - and when a line is loaded below its SIL
it acts like a shunt capacitor - supplying Mvar to the system.
Figure 1 is a graphic illustration of the concept of SIL. This particular line has a SIL of 450 MW.
Therefore is the line is loaded to 450 MW (with no Mvar) flow, the Mvar produced by the line will
exactly balance the Mvar used by the line.
Figure 1
Surge Impedance Loading of a Transmission Loading
.
1 comment:
1.
Blog Archive
2014(3)
o
January(3)
2013(22)
o
September(2)
August(20)
visits
SynchronizationofTurboAlternatororanACgeneratoristhe
process of connecting the generator with grid power supply
which is an interconnection of large pool of generators and
powerconsumptionloads.Simplythegridisparalleloperation
ofsomenumbergeneratorswithsamefrequency.Sotoconnect
the Generator in power plant in this pool of parallel running
generators,Theincominggeneratorparameterslikefrequency,
phaseangleandvoltageshouldbematchingwiththeexisting
gridfrequency.
Beforegoingdetaildescriptionfirstletusunderstandwhatisthe
need of synchronization of generator. Generator is connected
withtheprimemoverwhichprovidestherotatingmagneticfield
andhencethisrotatingmagneticfieldwillinducesthevoltagein
thestationarypart.Thefrequencyandphaseangleofthevoltage
signaliscontrolledbytheprimemoverspeedandmagnitudeof
thevoltagesignaliscontrolledbythegeneratorexcitation.
To understand the phenomenon let us correlate the entire
operationwiththepersonwantstocatcharunningtravelbus.
Considerthetravelbusisgridpowersupplyandthepersonis
incominggenerator.Nowifthepersonwantstogetintothebus
then he should equally or little faster than the bus same the
generatortriesconnecttothegridshouldrunequallyorlittle
faster than the grid. Here the speed is measured with the
frequencybecause speed isproportional tothe frequency( 50
Hz,60Hz).Thepersonisnowrunningwiththesamespeedof
the bus but the bus door is one end of the bus and he is at
anotherendofthebussoheneedstomatchwiththedoortoget
intothebus.Likethesameifthegeneratorisrunningatthe
samefrequencyofgriditcannotbesynchronizeduntilunless
thephaseofthetwovoltagesmatches.
Effectsofpoorsynchronization:
Primemoverdamagesifthespeedandrotorangleisnot
matcheswithgridvoltagefrequencyandphaseangledueto
rapidaccelerationordeceleration.Letussupposegenerator
hastoconnectedtothegridfrequencyof60Hz.Butthe
breaker has closed with poor synchronization at the
generator frequency of 58Hz (i.e for two pole generator
speed is3480 outof 3600rated),now oncethebreaker
closes the generator is connected in the pool of parallel
generatorswhichforcestheincominggeneratortorotateat
thesamegridfrequency.Duetothissuddenaccelerationof
therotorfrom3480to3600rpmandasuddenbreakat
3600rpmdamagestherotormass.Samewayinthereverse
whenthegeneratorisrunninghigherfrequencythanthe
gridfrequency.
AlargecurrentsmaysuddenlyflowthroughtheGenerator
windingsandGeneratortransformerwindingsduetopoor
synchronizationswhichdamagesthewindings.
Therewillbepowerandvoltageoscillationsbecauseofthis
suddenaccelerationanddecelerationoftherotor.
Itmayleadstoactivationofthegeneratorprotectiverelays
whichcausesthemajorinterruptionsotheprocessshould
bestartedonceagainafterclearingtheprotection.
1 comment:
1.
very
much,
like
your
Reply
Add comment
Load more...
Newer PostOlder PostHome
Subscribe to:Post Comments (Atom)
Popular Posts
way
of
explanation.
Blog Archive
2014(3)
o
January(3)
2013(22)
o
September(2)
August(20)
visits
Home
Standards Library
Reference Library
Engineering Community
Community
All
Standards Library
Reference Library
Community
Previous in Forum: Electrical Safety Audit Next in Forum: Wire Gauge and
at a Chemical Plant
AC vs. DC Flow
Comments Format:
Indented / nested by replies
Flat / chronological
Change Mode
Subscribe to Discussion:
CR4 allows you to "subscribe" to a discussion
so that you can be notified of new comments to
Got
Something
to Say?
Ask a
Question
Start a
Discussion
Search this
Forum
Electrical
Engineering:
Go
CR4
Sections
e
BioMed
&
&
Science
Material
Engineer
ing
&
ications
cs
Electroni
n
and
ing
Engineer
Careers
ing
Engineer
General
ntation
uring
Engineer
al
ing
gies &
Technolo
Research
Program
&
ming
Engineer
ble
ing
tation
Rating Vote:
Score 1
Score 2
Score 3
Site
Directories
Forum
Directory
Blog
Directory
User Group
Directory
RSS Feeds
Score 4
Score 5
Add Vote
Subscribe
Anonymous
Poster
Rate this
Comments: Nested
CR4 Rules
of Conduct
CR4 FAQ
Site
Glossary
Who's
Online (114
right now)
Show
Members
Advertisement
Reply
V.Amb
arani.
Associate
#1
Dear Sir,
Join Date:
Nov 2007
Location:
India
Posts: 41
Good
Answers: 3
Reply to
Forum
Thread
Back to top
Previous in Forum: Electrical Safety Audit Next in Forum: Wire Gauge and
at a Chemical Plant
AC vs. DC Flow
You might be interested in: Circuit Breakers, Motor and Generator Winding
Services, Circuit Tracers
Advertisement
"You measure the size of the accomplishment by the obstacles you had to
overcome to reach your goals" -- Booker T. Washington
All times are displayed in US/Eastern (EDT) (Register to change time zone)
2015 IHS. All rights reserved. Reproduction in whole or in part without permission is
prohibited. The information contained on this site is by users for users and is provided
for information purposes only and does not constitute advice. Any views or opinions
expressed by users are personal to them and do not represent the views or opinions of
IHS. You should check any information and use your own judgment or seek expert
advice before doing or not doing anything on the basis of what you read here. IHS does
not verify or warrant the accuracy or completeness of any information on this site and,
to the extent permitted by law, IHS shall not be liable for any loss, damage or expense
incurred by reliance on it or for any dealings you have with users or other third parties
that take place using or facilitated by this site.