PAMANA Fund Status As of 31 July 2012
PAMANA Fund Status As of 31 July 2012
List of Projects
Location
TOTAL
CORDILLERA AUTONOMOUS REGION (CAR)
Project Cost
Tranche
Amount
Released
Date Released
Balance
1,565,960,000
1,020,353,602
65%
548,776,398
35%
204,275,000
148,540,000
55,735,000
Abra
5,400,000
17-Dec-11
3,600,000
Abra
Completion of Poblacion-Cayaman
Road
Poblacion, Luba
1,200,000
17-Dec-11
800,000
Abra
Sabnangan, Luba
1,800,000
17-Dec-11
1,200,000
Abra
3,600,000
17-Dec-11
2,400,000
Abra
900,000
16-Dec-11
600,000
Abra
Total
Kasalalan Bridge
Liuvelihood Projects for CPLA
Members / Pos
Liuvelihood Projects for CPLA
Members / Pos
Liuvelihood Projects for CPLA
Members / Pos
12,800,000
9,600,000
16-Dec-11
3,200,000
2,400,000
Abra
Lamao. Bucloc
Caoayan, Licuan-Baay
Licuan-baay
1,000,000
800,000
200,000
Bucloc
1,000,000
800,000
200,000
Sabnangan
2,000,000
1,600,000
400,000
Madago, Manabo
4,800,000
2,400,000
7,200,000
16-Dec-11
29-Jun-12
800,000
Page 1 of 23
Implementing Partner
Apayao
Apayao
Benguet
Benguet
Benguet
List of Projects
Total
Warehouse and solar drying facility
Cattle and goat raising
Fresh water fish production
Bulldozer
Micro-lending/small-scale mining
Warehouse and solar drying facility
Concreting and canal lining of MaragLuna Road
Opening of Marag-Calayucay Road
Lydia-Swan FMR
Warehouse and solar drying facility
Carabao and goat raising
Farm tractor
Total
Nabuangan-Paddawan Road
Taggay-Mabiga Road
Calafug-Masico Road
Completion of Guinamgaman to Ili
Road- Sito Tagtag to Sitio Annip Road
Section
Rehabilitation/Reopening of
Dangadangan-Copcopit FMR
Construction of Madaymen-Palina
Road
Total
Agricultural tramlines
Isuzu Truck
Micro-lending
Micro-lending
Location
Cacalaggan
Conner
Conner
Conner
Calafug, Conner
Emilia
Project Cost
Tranche
Amount
Released
Date Released
14,240,000 28-Dec-2011
480,000
400,000
400,000
800,000
1,840,000
480,000
Balance
3,560,000
120,000
100,000
100,000
200,000
460,000
120,000
Marag, Luna
3,000,000
2,400,000
600,000
Marag, Luna
Lydia
Malibang, Pudtol
Swan, Pudtol
Lydia, Pudtol
1,000,000
5,000,000
600,000
500,000
2,200,000
800,000
4,000,000
480,000
400,000
1,760,000
200,000
1,000,000
120,000
100,000
440,000
Nabuangan, Conner
Mabiga, Conner
Calafug, Conner
10,800,000
3,000,000
3,000,000
1,800,000
Guinamgamman, Conner
5,000,000
3,000,000
Dalipey, Bacun
2,160,000
1,080,000
3,240,000
Madaymen, Kibungan
1,800,000
Palina, Kibungan
Palina, Kibungan
Gambang, Bakun
Cabitin, Mankayan
3,600,000
1,440,000
960,000
800,000
400,000
28-Dec-2011
7,200,000
2,000,000
2,000,000
1,200,000
2,000,000
17-Dec-11
29-Jun-12
360,000
1,200,000
24-May-12
900,000
360,000
240,000
200,000
100,000
Page 2 of 23
Implementing Partner
Ifugao
List of Projects
Total
Mompolia Multi-Purpose Gymnasium
and Peace Center
Concreting of Sta. Maria Sitio BangarMateo Section
Tribal Multi-Purpose Development
Center
Minanga Community Electrification
Caragasan Tribal Center
Concreting of Junction to Caragasan
Road
Improvement of PitawanPuntagguwan Road
Ambulance - Oong-Cabbabuyan
Purchase of Mompolia-Umalbong
Ambulance
Seedling Production (Nursery)
Improvement of Junction - San
Fernando Elementary Road
Location
Project Cost
Tranche
Amount
Released
13,620,000
Date Released
16-Dec-11
Balance
9,080,000
Mompolia, Hingyon
3,200,000
1,920,000
1,280,000
3,500,000
2,100,000
1,400,000
Gohang, Banaue
4,230,000
2,538,000
1,692,000
1,000,000
1,000,000
600,000
600,000
400,000
400,000
1,000,000
600,000
400,000
O-ong, Hingyon
2,140,000
1,284,000
856,000
O-ong, Hingyon
500,000
300,000
200,000
Mompolia-Hingyon
1,000,000
600,000
400,000
1,000,000
600,000
400,000
San Fernando
4,130,000
2,478,000
1,652,000
Ifugao
Asipulo
2,400,000
16-Dec-11
1,600,000
Ifugao
Tinoc
2,400,000
16-Dec-11
1,600,000
Ifugao
Total
Improvement of Junction-Gohang
National School Road
19,740,000
16-Dec-11
4,935,000
4,130,000
3,304,000
826,000
4,130,000
3,304,000
826,000
Alfonso Lista
1,200,000
960,000
240,000
Alfonso Lista
800,000
640,000
160,000
2,000,000
1,600,000
400,000
Gohang
Gohang
Page 3 of 23
Implementing Partner
List of Projects
Livelihood Projects for CBA-CPLA
Members / POs
Livelihood Projects for CBA-CPLA
Members / POs
Livelihood Projects for CBA-CPLA
Members / POs
Livelihood Projects for CBA-CPLA
Members / POs
Livelihood Projects for CBA-CPLA
Members / POs
Livelihood Projects for CBA-CPLA
Members / POs
Mt. Province
Mt. Province
Location
Tranche
Amount
Released
Date Released
Balance
Gohang
4,015,000
3,212,000
803,000
Piwong, Hingyon
1,800,000
1,440,000
360,000
Ubao, Aguinaldo
800,000
640,000
160,000
Alfonso Lista
4,000,000
3,200,000
800,000
Alfonso Lista
800,000
640,000
160,000
1,000,000
800,000
200,000
Ambasa, Lamut
Improvement of of Bontoc-Maligcong
Maligcong, Bontoc
Road
Total
Pakang-Chalitawey communal
irrigation system
Labaan communal irrigation system
and water impounding
Liyang-Daoran communal irrigation
system
Nongob-Patalim communal irrigation
system
Project Cost
3,600,000
16-Dec-11
2,400,000
36,400,000
28-Dec-11
9,100,000
Betwagan, Sadanga
2,000,000
1,600,000
400,000
Poblacion, Sadanga
3,000,000
2,400,000
600,000
Bekigan, Sadanga
3,000,000
2,400,000
600,000
Anabel, Sadanga
3,000,000
2,400,000
600,000
2,000,000
1,600,000
400,000
Saclit, Sadanga
4,000,000
3,200,000
800,000
Sacasacan, Sadanga
3,000,000
2,400,000
600,000
Demang, Sadanga
3,000,000
2,400,000
600,000
Betwagan, Sadanga
6,000,000
4,800,000
1,200,000
Belwang, Sadanga
10,000,000
8,000,000
2,000,000
Tokok-Churao-Napo communal
irrigation system
Fokong communal irrigation system
Kabyangan communal irrigation
system
Improvement of the Betwagan Access
Road
Belwang FMR
Page 4 of 23
Implementing Partner
List of Projects
Livelihood Project for CPLA
Members/POs
Livelihood Project for CPLA
Members/POs
Livelihood Project for CPLA
Members/POs
Livelihood Project for CPLA
Members/POs
Livelihood Project for CPLA
Members/POs
Chap-ay Suspension footbridge
Location
Project Cost
Tranche
Amount
Released
Date Released
Balance
1,500,000
1,200,000
300,000
500,000
400,000
100,000
Betwagan
1,000,000
800,000
200,000
Paracelis
1,000,000
800,000
200,000
Natonin
1,000,000
800,000
200,000
Poblacion, Sadanga
1,500,000
1,200,000
300,000
Poblacion, Sadanga
Paracelis
Mt. Province
Natonin
3,200,000
28-Dec-11
800,000
Mt. Province
Improvement of Poblacion-Marat
Road
Paracelis
600,000
28-Dec-11
400,000
23,000,000
REGION IV-B
Oriental Mindoro
Total
Construction of Day Care Center
Electrification (Sitio Alabigan I)
Electrification (Sitio Bungikarot)
Construction of Multi-Purpose
Pavement
Abaca Production and Development
Concreting of FMR
Purchase of Health Equipment
13,010,000
13,390,000
2,410,000
160,000
512,000
584,000
30-May-12
30-May-12
590,000
40,000
128,000
146,000
150,000
120,000
30-May-12
30,000
350,000
880,000
50,000
280,000
704,000
40,000
30-May-12
30-May-12
30-May-12
70,000
176,000
10,000
Oriental Mindoro
Benli, Bulalacao
2,400,000
600,000
Oriental Mindoro
2,400,000
8-Feb-12
600,000
Oriental Mindoro
600,000
27-Jun-12
150,000
Page 5 of 23
Implementing Partner
Oriental Mindoro
Palawan
List of Projects
Organic goat dairy farm for Mangyan
communities
Total
Water system
Multi-purpose building, FMR
Water system
Location
Masbate
Total
Concreting of Bakiad-Sta. CruzFundado FMR
Amount
Released
Date Released
Balance
3,400,000
27-Jun-12
850,000
1,800,000
600,000
600,000
600,000
10-Apr-12
Magsaysay, Aborlan
Bukid-bukid, Bataraza
Sapa, Bataraza
7,200,000
2,400,000
2,400,000
2,400,000
220,000,000
179,260,000
112,000,000
40,740,000
28-Dec-11
28,000,000
10,000,000
8,000,000
2,000,000
20,000,000
16,000,000
4,000,000
20,000,000
16,000,000
4,000,000
50,000,000
40,000,000
10,000,000
40,000,000
32,000,000
8,000,000
Total
40,000,000
10,000,000
16,000,000
12,800,000
4,000,000
3,200,000
800,000
Cantorna, Monreal
15,000,000
12,000,000
3,000,000
15,000,000
12,000,000
3,000,000
Tranche
Panaytayan, Mansalay
REGION V
Camarines Norte
Project Cost
Behia, Magallnes
800,000
200,000
1,000,000
25-Jun-12
3,200,000
3-Aug-11
30-Mar-12
Page 6 of 23
Implementing Partner
List of Projects
Location
Project Cost
Tranche
Amount
Released
Date Released
Sorsogon
Behia, Magallnes
1,600,000
400,000
2,000,000
3-Aug-11
30-Mar-12
Sorsogon
1,600,000
3-Aug-11
2nd - 20%
Total
400,000
2,000,000
30-Mar-12
Sorsogon
2,240,000
560,000
2,800,000
3-Aug-11
30-Mar-12
Sorsogon
Sipaya, Juban
2,400,000
600,000
3,000,000
3-Aug-11
30-Mar-12
Sorsogon
Sablayan, Juban
800,000
200,000
1,000,000
3-Aug-11
30-Mar-12
Sorsogon
2,400,000
600,000
3,000,000
3-Aug-11
15-Dec-12
Sorsogon
2,000,000
500,000
2,500,000
3-Aug-11
15-Jun-12
Sorsogon
Salvacion, Irosin
1,600,000
3-Aug-11
400,000
2,000,000
15-Jun-12
2nd - 20%
Total
Balance
Page 7 of 23
Implementing Partner
List of Projects
Sorsogon
Sorsogon
Sorsogon
Location
Tranche
Amount
Released
Date Released
Balance
2,400,000
3-Aug-11
600,000
3,200,000
3-Aug-11
800,000
2,960,000
22-May-12
740,000
114,000,000
REGION VI
Negros Occidental
Project Cost
Total
Agri-based Enterprise Development
Projects
27,300,000
3,100,000
86,700,000
3-Jan-12
12,400,000
6,000,000
1,200,000
4,800,000
3,000,000
600,000
2,400,000
500,000
100,000
400,000
2,500,000
500,000
2,000,000
2,000,000
400,000
1,600,000
1,500,000
300,000
1,200,000
Page 8 of 23
Implementing Partner
Negros Occidental
Negros Occidental
List of Projects
Total
Socio-economic development
assistance and development of
settlement areas for TPG members
Location
Project Cost
Tranche
72,800,000
88,000,000
17,600,000
70,400,000
600,000
2,400,000
3,000,000
Total
Agri-based Enterprise Development
Projects
Agri-based Enterprise Development
Projects
Agri-based Enterprise Development
Projects
Agri-based Enterprise Development
Projects
Agri-based Enterprise Development
Projects
Social Preparation
Negros Oriental
Socio-economic Development
Assistance and Development of
Settlement areas for TPG members
Balance
18,200,000
2nd - 60%
Total
Negros Oriental
Date Released
32,000,000
REGION VII
Amount
Released
1,500,000
3-Jan-12
4,500,000
6,000,000
26-Jun-12
1,500,000
6,400,000
1,600,000
25,600,000
5-Jan-12
6,400,000
1,000,000
200,000
800,000
3,500,000
700,000
2,800,000
500,000
100,000
400,000
1,500,000
300,000
1,200,000
1,000,000
200,000
800,000
500,000
100,000
400,000
4,800,000
19,200,000
Tambohangin, Amlan
Page 9 of 23
Implementing Partner
List of Projects
Location
Northern Samar
Northern Samar
REGION IX
Total
Rehabilitation of Barangay Roads
Rehabilitation of Barangay Roads
Rehabilitation of Barangay Roads
Zamboanga Sibugay
Amount
Released
Date Released
180,000,000
Balance
45,500,000
24,000,000
6-Sep-11
6,000,000
156,000,000
30-Mar-12
39,500,000
56,000,000
44,800,000
16,000,000
11,200,000
13-Sep-11
4,000,000
6,670,000
5,336,000
1,334,000
6,670,000
5,336,000
1,334,000
6,660,000
5,328,000
1,332,000
Total
Seaweed Production Project
Tranche
225,500,000
REGION VIII
Zamboanga Sibugay
Project Cost
24,000,000
28-Feb-12
6,000,000
2,500,000
2,000,000
500,000
Datu Tumanggong
5,000,000
4,000,000
1,000,000
5,000,000
4,000,000
1,000,000
5,000,000
4,000,000
1,000,000
5,000,000
4,000,000
1,000,000
Page 10 of 23
Implementing Partner
List of Projects
Rehabilitation of Solar-Tambanan,
Suba Nipa Brgy. Road
Water Supply System Level II
Zamboanga Sibugay
Water System
Location
Date Released
Balance
4,000,000
1,000,000
Datu Tumanggong
2,500,000
2,000,000
500,000
600,000
1,800,000
2,400,000
8-Mar-12
29-Jun-12
600,000
1,800,000
2,400,000
19-Mar-12
29-Jun-12
Tubigan, Initao
REGION XI
Compostela Valley
Amount
Released
5,000,000
REGION X
Misamis Oriental
Tranche
Total
Multi-Purpose Gymnasium
Farmers' Convention Center
Improvement of Water System
Project Cost
Total
600,000
600,000
1,000,000
1,000,000
1,000,000
800,000
800,000
800,000
200,000
200,000
200,000
1,000,000
900,000
100,000
900,000
73,300,000
57,920,000
12,000,000
3,000,000
15,000,000
11-Jun-12
100,000
15,380,000
7-Sep-11
29-Jun-12
-
3,300,000
3,300,000
2,700,000
2,700,000
Page 11 of 23
Implementing Partner
List of Projects
Agro-Forestry Production
Rehabilitation of 3.5km FMR
Location
Camanlangan (20 has.), Bantacan
(15has.), Batinao (15 has.)
Purok 4 to Purok 2 Barangay
Panansalan, Compostela
Compostela Valley
Davao City
Davao Oriental
Davao Oriental
Project Cost
Tranche
Amount
Released
Date Released
Balance
1,500,000
1,500,000
6,000,000
6,000,000
1,500,000
1,500,000
22,400,000
600,000
29-Jun-12
2,400,000
Multi-Purpose Building
Waan, Buhangin
640,000
29-Jun-12
2,560,000
Total
Rubber Production
Rubber Production
Rubber Production
Rubber Production
5,040,000
1,392,000
1,128,000
1,392,000
1,128,000
28-Feb-12
1,260,000
348,000
282,000
348,000
282,000
14,240,000
1,280,000
28-Feb-12
3,560,000
320,000
Total
Livelihood-Rubber Production
Rehabilitation/Improvement of 15 Km
FMR from Taytayan Proper-Yapsay
Banlod Section
Rehabilitation/Improvement of9.70
km FMR from NHJ Maylaya to
Sabangan Section
Rehabilitation of 8km FMR from
Magsaysay Purok 3 to Cuabo Section
Rehabilitation/Improvement of 8km
FMR from Marayag Sitio DCS to Purok
Hayahay Section
Campawan, Baganga
5,600,000
Taytayan, Cateel
5,000,000
4,000,000
1,000,000
Malibago, Cateel
2,000,000
1,600,000
400,000
Magsaysay, Lupon
1,000,000
800,000
200,000
Marayag, Lupon
2,000,000
1,600,000
400,000
Page 12 of 23
Implementing Partner
List of Projects
Location
Rehabilitation/Improvement of 7km
FMR from San Isidro Centro to Sitio
San Isidro, Lupon
Kalasagan Section
Rehabilitation/Improvement of 8km
FMR from New Visayas Centro to Sitio New Visayas, Lupon
Tagalahi Section
Rehabilitation/Improvement of
12.1KM FMR from Campo 1, City of
Mati City
Mati to Licop to Cuabo to Matin-ao
Section, City of Mati
REGION XII
Project Cost
Tranche
Amount
Released
Date Released
Balance
2,000,000
1,600,000
400,000
1,000,000
800,000
200,000
3,200,000
2,560,000
640,000
188,043,000
59,834,400
128,208,600
600,000
7-Jun-12
2,400,000
Calumpang Lote
600,000
29-Jun-12
2,400,000
North Cotabato
Total
Pangasius Production Project
Midsayap
Building and Electrical Connection for
Liliongan, Carmen
Corn Mill
8,000,000
3,040,000
12-Oct-11
2,000,000
760,000
Total
Rehabilitation of Capayangan Road
Rehabilitation of Tumbao-Camalig
Road
North Cotabato
North Cotabato
Capayangan, Banisilan
Tumbao and Camalig, Banisilan
6,200,000
5,000,000
4,960,000
8,000,000
4,000,000
1,240,000
29-Feb-12
4,000,000
2,000,000
1,000,000
1,000,000
400,000
29-Feb-12
100,000
6,034,400
29-Feb-12
1,508,600
5,283,000
4,226,400
1,056,600
Page 13 of 23
Implementing Partner
List of Projects
Agro-Forestry Plantation
(Rubber/Coffee/ Cacao)
North Cotabato
Sarangani
Total
Warehouse
Multipurpose Center
Peace Development Center
Warehouse
Warehouse
Warehouse
Warehouse
Corn milling equipment and solar
dryer
Fish Landing with Fish Storage
2KM Concrete Road
Warehouse
Warehouse
2KM Concrete Road
Warehouse
2KM Concrete Road
Warehouse
Warehouse
Warehouse
4KM Concrete Road
Warehouse
2KM Concrete Road
Warehouse
Location
Nangaan, Kabacan
Ilian, Matalam
Kilada, Matalam
Sambolawan, Midsayap
Balatikan, Pikit
Dunguan, Aleosan
Tapodoc, Aleosan
Project Cost
Tranche
2,260,000
132,000,000 1st - 20%
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
Amount
Released
Date Released
1,808,000
26,400,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
Balance
452,000
26-Mar-12
105,600,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
Pedtad, Kabacan
6,000,000
1,200,000
4,800,000
Malingao, Midsayap
Damatulan, Midsayap
Central Labas, Midsayap
Upper Labas, Midsayap
Lomopog, Midsayap
Mudseng, Midsayap
Olandang, Midsayap
Kapinpilan, Midsayap
Kandingilan, Midsayap
Tumbras, Midsayap
Kudarangan, Midsayap
Nabalawag, Midsayap
Kadigasanp, Midsayap
Balungis, Pikit
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
4,800,000
1,200,000
3,600,000
4,800,000
Lumatil, Maasim
Lumatil, Maasim
2,000,000
200,000
1,600,000
160,000
400,000
40,000
1,000,000
800,000
200,000
Total
29-Dec-11
14-Mar-12
1,200,000
Page 14 of 23
Implementing Partner
List of Projects
Sitio Data Hopo Community Peace
Center
Footbridge
Community Peace Center (Nomoh
Integrated School)
South Cotabato
Sultan Kudarat
Total
Construction of Training Center
Construction of Training Center
Construction of Training Center
Location
Tranche
Amount
Released
Date Released
Balance
Nomoh, Maasim
1,300,000
1,040,000
260,000
Nomoh, Maasim
1,000,000
800,000
200,000
Nomoh, Maasim
500,000
400,000
100,000
Palian, Tupi
REGION XIII
Agusan del Sur
Project Cost
Total
Magkiangkang, Grace Estate, Mt. Olive,
Mt. Carmel, Calaitan and Mt. Ararat,
Bayugan
Tagubay, Mahayag and Sto. Nio,
Bayugan
600,000
1,800,000
2,400,000
27-Mar-12
11-Jun-12
2,600,000
1,400,000
600,000
600,000
11-Jun-12
600,000
125,402,400
14,216,000
10,400,000
5,600,000
2,400,000
2,400,000
31,350,600
16-Aug-11
3,784,000
2,500,000
2,000,000
500,000
2,250,000
1,800,000
450,000
2,250,000
1,800,000
450,000
1,700,000
1,360,000
340,000
2,300,000
1,840,000
460,000
2,250,000
1,800,000
450,000
500,000
216,000
284,000
Cacao Production
Rehabilitation of Tagubay-Mahayag
Road Section
Rehabilitation of JCT Sta. Irene-La
Purisima FMR
Page 15 of 23
Implementing Partner
List of Projects
Abaca Production
Rubber Production
Rehabilitation of Andanan-Bailey
Bridge
Water Supply System
Agusan del Sur
Agusan del Sur
Location
Tranche
Amount
Released
Date Released
Balance
1,270,000
1,016,000
254,000
600,000
480,000
120,000
2,000,000
1,600,000
400,000
380,000
304,000
76,000
20,000,000
28-Feb-12
5,000,000
3,200,000
28-Feb-12
800,000
100,000
80,000
20,000
3,400,000
2,720,000
680,000
500,000
400,000
100,000
Project Cost
Total
Abaca Production
Abaca Production
Abaca Production
Abaca Production
Abaca Production
ADSDPP Formulation for Manobo
Tribes
32,000,000
29-Jun-12
8,000,000
1,000,000
800,000
200,000
4,000,000
3,200,000
800,000
35,000,000
28,000,000
7,000,000
12,786,400
16-Aug-11
3,196,600
2,036,600
1,629,280
407,320
2,036,600
2,036,600
1,629,280
1,629,280
407,320
407,320
2,036,600
1,629,280
407,320
2,036,600
1,629,280
407,320
2,000,000
1,600,000
400,000
Page 16 of 23
Implementing Partner
List of Projects
Construction of Sagbayan to
Calatngan FMR
Basic Handloom Weaving, Simple
Bookeeping, Product Costing and
Pricing Techniques
Location
Amount
Released
Date Released
Balance
3,500,000
2,800,000
700,000
300,000
240,000
60,000
1,600,000
16-Aug-11
400,000
41,600,000
28-Feb-12
10,400,000
15,000,000
12,000,000
3,000,000
San Agustin
5,000,000
4,000,000
1,000,000
Tagongon, Maliksi-Soriano
9,000,000
7,200,000
1,800,000
10,000,000
8,000,000
2,000,000
Lianga
5,000,000
4,000,000
1,000,000
Marihatag
8,000,000
6,400,000
1,600,000
271,859,000
176,986,802
94,872,198
Caras-an
Bayabas
Total
Tranche
ARMM
Basilan
Project Cost
3,300,000
9,900,000
13,200,000
29-Dec-11
29-Jun-12
3,300,000
1,500,000
1,500,000
1,500,000
1,500,000
1,200,000
1,200,000
1,200,000
1,200,000
300,000
300,000
300,000
300,000
1,500,000
1,200,000
300,000
Page 17 of 23
Implementing Partner
List of Projects
Day Care Center, Warehouse, Rice
Milling Equipment and Solar Dryer
Barangay Health Center, Botika ng
Bayan, School Building/ Classroom
Women's Center, Recreation Center
Water System, School Building/
Classroom, Local Electrification
(generator/ solar)
Barangay Health Center, Multipurpose Hall, Solar Dryer
Multi-purpose Hall, School Building,
Recreation Center
Basilan
Total
Road Rehabilitation 3km
Water System level II
Water system level II, road
rehabilitation 3km
4-classroom Madraza
Water system level II, 1-classroom
school building
Multi-purpose hall
Multi-purpose hall, road rehabilitation
3km
Water System level II
Multi-purpose hall, 1-classroom
school building, water system II
Water System level II
Multi-purpose hall
30 unitsCore Shelter Housing
Multi-purpose hall
Total
Concreting of 120-meter Road
Concreting of 120-meter Road
Concreting of 120-meter Road
Location
Project Cost
Tranche
Amount
Released
Date Released
Balance
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
Pamucalin, Latawan
1,500,000
1,200,000
300,000
15,600,000
1,200,000
1,200,000
29-Dec-12
3,900,000
300,000
300,000
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
Canibungan, Lantawan
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
1,500,000
1,200,000
300,000
Cabcaban, Sumisip
1,500,000
1,200,000
300,000
Ettub-Ettub, Sumisip
Tong Umus, Tabuan Lasa
Bohe Lebang, Tipo-Tipo
Bohek, Ungkaya Pukan
1,500,000
1,500,000
1,500,000
1,500,000
1,200,000
1,200,000
1,200,000
1,200,000
300,000
300,000
300,000
300,000
Bairan, Bayang
Lumbac, Buadipuso Buntong
Alog, Lumbatan
5,400,000
200,000
200,000
200,000
29-Dec-11
21,600,000
800,000
800,000
800,000
Page 18 of 23
Implementing Partner
Maguindanao
List of Projects
Location
Pagalongan, Maguing
Paigoay, Marogong
Bagayawan, Sultan Domalondong
Tubaran Proper, Tubaran
Bangon, Buadipuso Buntong
Panggaoalupa, Calanogas
Bunkhouse, Malabang
Caramian, Masiu
Manalocon, Masiu
Balangas, Sultan Gumander
Dilausan, Tamparan
Park Area (Poblacion), Wao
Western Wao, Wao
Pagalongan, Ditsaan-Ramain
Ragayan, Poona Bayabao
Total
Concreting of Lumbac Road 120 M
Multi-Purpose Gymnasium
Water System
Multi-Purpose Gymnasium
Multi Purpose Building
Multi-Purpose Gymnasium
Concreting Pinalanka Road 360m
Concreting of Tambo Road 360m
Buadipuso Buntong
Pindogoan, Bubong
Patcalipongan, Ditsaan Ramain
Cabasaran, Madamba
Marawi, Marawi City
Abdullah Buisan, Masiu
Pinalanka-Linindigan, Pagayawan
Tambo, Piagapo
Total
Maguindanao Freshwater Fish
Hatchery
Halal Cattle Fattening
Ligawasan Organic Fertilizer
Production
Halal Techno-Demo on Dairy Goat
Production
Halal Vegetable Production
Halal Institute
Project Cost
Tranche
1,000,000
1,000,000
1,000,000
1,000,000
1,000,000
1,000,000
1,000,000
1,500,000
1,500,000
1,500,000
1,000,000
3,000,000
3,000,000
3,000,000
2,500,000
Amount
Released
Date Released
200,000
200,000
200,000
200,000
200,000
200,000
200,000
300,000
300,000
300,000
200,000
600,000
600,000
600,000
500,000
Balance
800,000
800,000
800,000
800,000
800,000
800,000
800,000
1,200,000
1,200,000
1,200,000
800,000
2,400,000
2,400,000
2,400,000
2,000,000
14,400,000
800,000
1,600,000
2,400,000
1,600,000
1,600,000
1,600,000
2,400,000
2,400,000
29-Dec-12
3,600,000
200,000
400,000
600,000
400,000
400,000
400,000
600,000
600,000
12,000,000
6-Oct-11
3,000,000
Popol, Buluan
1,510,000
1,208,000
302,000
Maslabeng, Buluan
4,850,000
3,880,000
970,000
2,780,000
2,224,000
556,000
2,500,000
2,000,000
500,000
860,000
2,000,000
688,000
1,600,000
172,000
400,000
Page 19 of 23
Implementing Partner
List of Projects
Water Hyacinth for Sustainable
Livelihood
Maguindanao
Total
Organic Fertilizer
Poultry Raising Project
Halal Feed Production
Rice Production and Post-Harvest
Facilities
Enhancing Economic Activities
Through Provision of Post Harvest
Facilities and Installation of Potable
Water System
Corn Production
Duck Production
FMR (Poblacion Buluan to PAMANA
Demo Farm in Brgy. Ginakep [rancho
road])
Construction of Multi-Purpose
Pavement and Solar Dryer with
Basketball Stand Ring
Halal Moro Delicacies
Maguindanao
Location
Poblacion, SK Pendatun
Maslabang, Buluan
Manindolo, Datu Paglas
Poblacion, SK Pendatun
Tranche
500,000
15,000,000 1st - 80%
2,365,200
1,953,630
500,000
Amount
Released
Date Released
400,000
12,000,000
1,892,160
1,562,904
400,000
Balance
100,000
29-Feb-12
3,000,000
473,040
390,726
100,000
505,170
404,136
101,034
Kabuling, Pandag
1,443,514
1,154,811
288,703
Tamar, Talayan
Ginakep, Mangudadatu
500,000
1,420,000
400,000
1,136,000
100,000
284,000
Poblacion, Buluan
1,500,000
1,200,000
300,000
2,950,000
2,360,000
590,000
1,106,486
885,189
221,297
756,000
604,800
151,200
Paglat
Poblacion, Buluan
Total
Rehabilitation of FMR
Multi-Purpose Building
Water System
School Building
Project Cost
2,483,363
3,000,000
1,121,900
1,894,737
11,100,000
33,300,000
44,400,000
1,986,690
2,400,000
897,520
1,515,790
29-Dec-11
29-Jun-12
11,100,000
496,673
600,000
224,380
378,947
Page 20 of 23
Implementing Partner
List of Projects
Multi Purpose Building with Rain
Water Collector
Rehabilitation of Tambak-Labungan
Road
Warehouse with Solar Dryer
FMR with Box Culvert
Steel (Bailey) Bridge
Warehouse with Solar Dryer
FMR with Drainage
Solar Dryer
Location
Sulu
Sulu
Total
Maimbung Integrated Market
Rehabilitation/Regravelling of PangPitogo Road
Amount
Released
Date Released
Balance
3,000,000
2,400,000
600,000
8,500,000
6,800,000
1,700,000
1,647,492
8,352,508
6,852,508
1,647,492
8,500,000
3,957,963
1,317,994
6,682,006
5,482,006
1,317,994
6,800,000
3,166,370
329,498
1,670,502
1,370,502
329,498
1,700,000
791,593
604,574
483,659
120,915
1,547,463
2,390,000
1,237,970
1,912,000
309,493
478,000
Maimbung
Kalingalang Caluang
17,486,802
12,000,000
7-Jul-11
5,486,802
Total
Tranche
Project Cost
4,372,198
3,000,000
1,372,198
3,300,000
3,600,000
6,900,000
29-Dec-11
29-Jun-12
9,600,000
Minapan, Siasi
1,500,000
900,000
1,200,000
29-Jun-12
300,000
1,500,000
900,000
1,200,000
29-Jun-12
300,000
1,500,000
900,000
1,200,000
29-Jun-12
300,000
1,500,000
1,500,000
1,000,000
500,000
900,000
1,200,000
300,000
200,000
100,000
29-Jun-12
300,000
1,200,000
800,000
400,000
Tagbak, Indanan
1,500,000
300,000
1,200,000
Page 21 of 23
Implementing Partner
List of Projects
Location
Total
Construction of Multi Purpose Hall
0.100 KM Farm to Market
Repair of Cerantes Market
Computer Building with Library
Construction of Flea Market
Water Rehabilitation
Farm-to-Market Road
Rock Causeway
Reconstruction/Rehabilitation 1-unit
2 ClassroomSchool Building
Rehabilitation Public Market
Construction of Day Care Center with
Facilities
Farm-to-Market road 1.2 KM
Concreting of 159m Road
Farm-to-Market road
Kahikukkuk, Bangguingui
Timbangan, Indanan
Tulay Zone III, Jolo
Pitogo, K. Caluang
Lugus Proper, Lugus
Niog Niog, Luuk
Tubig Gantang/ Puhagan, Panamao
Hambilan, Pandami
Tranche
Amount
Released
Date Released
Balance
1,500,000
300,000
1,200,000
1,500,000
300,000
1,200,000
3,000,000
600,000
2,400,000
16,800,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
1,200,000
29-Dec-12
4,200,000
300,000
300,000
300,000
300,000
300,000
300,000
300,000
300,000
1,500,000
1,200,000
300,000
Simbahan, Pangutaran
1,500,000
1,200,000
300,000
Pisak-Pisak, Pata
1,500,000
1,200,000
300,000
Langhub, Patikul
Bilaan, Talipao
Kamaunggi, Tapul
1,500,000
1,500,000
1,500,000
1,200,000
1,200,000
1,200,000
300,000
300,000
300,000
Panglima Sugala
4,000,000
17-Sep-11
1,000,000
4,000,000
20-Sep-11
1,000,000
7,200,000
3,600,000
10,800,000
29-Dec-11
29-Jun-12
Tawi-Tawi
Concreting of Manggis-Kapatagan
Road
Tawi-Tawi
Tawi-Tawi
Total
Project Cost
Lapid-lapid, Bongao
3,000,000
600,000
25,200,000
2,400,000
Page 22 of 23
Implementing Partner
List of Projects
Elevated Concrete Water Tank with
Purifier Machine, Community Peace
Center, Wet and Dry Market
Renovation of Health Center, 1-Unit 1
Classroom School Building, Access
Road
Concrete Footbridge, Community
Peace Center, Health Center
Rehabilitation of Bakong Rock
Causeway, Rehabilitation of 1 Unit 3Classroom School Building,
Improvement and Expansion of MultiPurpose Building
Rehabilitation of 1-Unit 3-Classroom
School Building, Concreting of
Community Access Road,
Community Peace Center, Solar Drier
and Warehouse, Footbridge
Footbridges (2), Flea Market,
Watertank
Trading Center, Boat Landing with
Pier Head, Pedestrian Walkway, Pahut
Footbridge
Rehabilitation and Regravelling of
Farm-to-Market Road
Covered Court and Open Stage
Location
Project Cost
Tranche
Amount
Released
Date Released
Balance
3,000,000
600,000
2,400,000
Sanga-sanga, Bongao
3,000,000
600,000
2,400,000
Sumangat, Bongao
3,000,000
600,000
2,400,000
Bakong, Simunul
3,000,000
2,400,000
600,000
3,000,000
2,400,000
600,000
Marang-Marang, Languyan
3,000,000
600,000
2,400,000
Tumahubong, Languyan
3,000,000
600,000
2,400,000
3,000,000
600,000
2,400,000
3,000,000
600,000
2,400,000
3,000,000
600,000
2,400,000
3,000,000
600,000
2,400,000
Page 23 of 23