GOVERNMENT OF ANDHRA PRADESH

PANCHAYATI RAJ ENGINEERING DEPARTMENT


VISAKHAPATNAM DISTRICT
DETAILED AND ABSTRACT ESTIMATE

Name of the Work::

Preparation charges for DPR for the work


"Providing B.T.Surface to the Road from
Lotheru Road to Sarubedda"

Grant

AP DRP

Estimate Cost

Rs. 72,000/-

Total Length

4.00 km

District

Visakhapatnam

Division

PR Paderu

Sub-Division

PIU Araku Valley

Mandal

Araku Valley

Specification Report
Specification report to accompanying the Detailed estimate for the work
"Preparation charges for DPR for the work "Providing B.T.Surface to the Road from
Lotheru Road to Sarubedda" in Araku Valley Mandal of Visakhapatnam District.
Length of the road :-

4.00

Km

Proposed Length :-

4.00

Km

Estimate cost :-

### Lakhs

The work "Providing B.T.Surface to the Road from Lotheru Road to


Sarubedda" is proposed under APDRP and for which a DPR is to be prepared. Hence this
estimate ""Preparation charges for DPR for the work "Providing B.T.Surface to the Road
from Lotheru Road to Sarubedda"" is prepared with the following provisions to accord
sanction for DPR preparation charges.
1 . Provision for survey and levelling at 20m interval including jungle clearance,
preparation of RLs, earth work quantities at 20m interval including
transportation charges and printing charges of levels, longitudinal sections,
cross sections and earth work quantities.
2 . Provision for taking Photographs of the Existing Road for every 100m or as
instructed by the Engineer in Charge incl Setting out DTP,Taking of Printouts on
A4 Size Paper and all Conveyance charges etc..,
3 . Provision for collection of Soil samples 2 no's for each KM and produced to
Laboratory for Necessary Soil tests including conveyance charges from work
spot to Lab and all labour charges etc. complete
4 . Provision towards Colour Printing of Maps, Informatory Boards, CS, LS, Traffic
Signals etc.,
5 . Provision towards DTP Charges ( Lead, data, Estimates, Designs, Drawings
etc.,), Cost of Xerox charges for the DPR and Cost of Spiral Binding.

Asst. Exe. Engineer,


PIU, Araku Valley

Dy. Exe. Engineer,


PR, Araku Valley

Executive Engineer
PR, Paderu

Superintending Engineer
PR, Visakhapatnam

DETAILED CUM ABSTRACT ESTIMATE


NAME OF THE WROK :- Preparation charges for DPR for the work "Providing
B.T.Surface to the Road from Lotheru Road to Sarubedda"
ngth :- 4.00 Km
Measurem
Amoun
ents
Description of Item
No
Qty. Rate/Per
t
L B D
No.
1
2
3
4 5 6
4
5
6
Part A - Amount Req. for Survey, Investigation, Soil testing
charges
1 Conducting Survey and Investigation incl Levels taken for earth work
@ 20mts interval and preparation of cross sections and Longitudinal
sections and plotting for 4.00KM including all labour charges for
Jungle clearance , carrying of survey instruments and other
miscellaneous items i.e. Printing of Earth work Calculation Sheets
A)
3
3000 Day
###
etc.Including
completeHire charge for jeep 1 x 3
engaged for transportation of
equipment and labour daily from
Head quarter to site (1.5km/day)

Sl.

Estimate Amount : Rs. 72000

B) Engaging of Diploma Holders


(Surveyor for Cal & Computation
of Levels) - 2No

2 x 3

500

Day

###

C) Man Mazdoor-9No (Jungle Clr4No, Chain man-4Nos, Staff


Attedent-1No
D) Engaging of Diploma Holders
for Earth work Calculations
(0.5km/one day)

9 x 3

27

300

Day

###

1 x 8

500

Day

###

E) Printing of Calculation sheets


of Levels

1 x###

104

Each 312.00

Towards Taking of Photographs of the Existing Road for every 100m


or as instructed by the Engineer Charge incl Setting out DTP,Taking
of Printouts on A4 Size Paper and all Conveyance charges etc.,
Complete.
75 Each
For Taking Photos
1
x 48
48
40 Sheet
For Printing
1
x 48
48
Sub Total
Collection of Soil sample in each KM and produced to Laboratory for
Necessary Soil tests including conveyance charges from work spot to
Lab and all labour charges etc. complete
8

3600
1920

A) Man Mazdoor - 2 samples /km


(for 4km for 8 samples)

1 x 8

day

B) Conveyance Charges
C) Soil Testing Charges (CBR,
OMC, MDD)

1 x 1

3000 each

3000

1 x 8

3700 each

29600

300

Part B - Amount Req. for Printing, Spiral Binding etc. ( Fixed


cost for any DPR)
Towards Colour Printing of Maps, Informatory Boards, CS, LS, Traffic
Signals etc.,
12
12/DPR
1 x 12
25
Towards Cost of Xerox charges for the DPR

2400

300

Black & White 4*(150)=600/DPR


Black & White 4*26*4km
Colour 4/DPR
Towards Cost of Spiral Binding

1 x###
1 x###
1 x 4
1 x 5

600
416
4

2
2
25

1200
832
100

30

150

Towards DTP Charges for Printing, Calculations ( Lead, data,


Estimates, Designs, Drawings etc.,)
1
4500
1
DPR
Limited to

Asst. Exe. Engineer,


PIU, Araku Valley

Dy. Exe. Engineer,


PR, Araku Valley

Executive Engineer
PR, Paderu

Superintending Engineer
PR, Visakhapatnam

4500
72014
72000