You are on page 1of 14

Federal Register / Vol. 71, No.

238 / Tuesday, December 12, 2006 / Rules and Regulations 74667

(ii) Take all cash and trade discounts, revised ceiling that shall constitute the prior to the final payment under the contract
rebates, allowances, credits, salvage, ceiling price for performance under this are contract financing payments. Contract
commissions, and other benefits. When contract. When and to the extent that the financing payments are not subject to the
unable to take advantage of the benefits, the ceiling price set forth in the Schedule has interest penalty provisions of the Prompt
Contractor shall promptly notify the been increased, any hours expended and Payment Act.
Contracting Officer and give the reasons. The material costs incurred by the Contractor in (2) The designated payment office will
Contractor shall give credit to the excess of the ceiling price before the increase make interim payments for contract financing
Government for cash and trade discounts, shall be allowable to the same extent as if the on the lllll [Contracting Officer insert
rebates, scrap, commissions, and other hours expended and material costs had been day as prescribed by agency head; if not
amounts that have accrued to the benefit of incurred after the increase in the ceiling prescribed, insert ‘‘30th’’] day after the
the Contractor, or would have accrued except price. designated billing office receives a proper
for the fault or neglect of the Contractor. The (f) Audit. At any time before final payment payment request. In the event that the
Contractor shall not deduct from gross costs under this contract, the Contracting Officer Government requires an audit or other review
the benefits lost without fault or neglect on may request audit of the vouchers and of a specific payment request to ensure
the part of the Contractor, or lost through supporting documentation. Each payment compliance with the terms and conditions of
fault of the Government. previously made shall be subject to reduction the contract, the designated payment office is
(7) Except as provided for in 31.205–26(e) to the extent of amounts, on preceding not compelled to make payment by the
and (f), the Government will not pay profit vouchers, that are found by the Contracting specified due date.
or fee to the prime Contractor on materials. Officer or authorized representative not to (i) Interim payments on contracts for
(c) If the Contractor enters into any have been properly payable and shall also be services. For interim payments made prior to
subcontract that requires consent under the subject to reduction for overpayments or to the final payment under this contract, the
clause at 52.244–2, Subcontracts, without increase for underpayments. Upon receipt Government will make payment in
obtaining such consent, the Government is and approval of the voucher designated by accordance with the Prompt Payment Act (31
not required to reimburse the Contractor for the Contractor as the ‘‘completion voucher’’ U.S.C. 3903) and prompt payment
any costs incurred under the subcontract and supporting documentation, and upon regulations at 5 CFR part 1315.
prior to the date the Contractor obtains the compliance by the Contractor with all terms (End of Clause)
required consent. Any reimbursement of of this contract (including, without Alternate I (FEB 2007). If a labor-hour
subcontract costs incurred prior to the date limitation, terms relating to patents and the contract is contemplated, the Contracting
the consent was obtained shall be at the sole terms of paragraphs (f) and (g) of this clause), Officer shall add the following paragraph (i)
discretion of the Government. the Government shall promptly pay any to the basic clause:
(d) Total cost. It is estimated that the total balance due the Contractor. The completion (i) The terms of this clause that govern
cost to the Government for the performance voucher, and supporting documentation, reimbursement for materials furnished are
of this contract shall not exceed the ceiling shall be submitted by the Contractor as considered to have been deleted.
price set forth in the Schedule, and the promptly as practicable following completion [FR Doc. 06–9610 Filed 12–6–06; 8:45 am]
Contractor agrees to use its best efforts to of the work under this contract, but in no BILLING CODE 6820–EP–S
perform the work specified in the Schedule event later than 1 year (or such longer period
and all obligations under this contract within as the Contracting Officer may approve in
such ceiling price. If at any time the writing) from the date of completion.
Contractor has reason to believe that the (g) Assignment and Release of Claims. The DEPARTMENT OF DEFENSE
hourly rate payments and material costs that Contractor, and each assignee under an
will accrue in performing this contract in the assignment entered into under this contract GENERAL SERVICES
next succeeding 30 days, if added to all other and in effect at the time of final payment ADMINISTRATION
payments and costs previously accrued, will under this contract, shall execute and
exceed 85 percent of the ceiling price in the deliver, at the time of and as a condition NATIONAL AERONAUTICS AND
Schedule, the Contractor shall notify the precedent to final payment under this SPACE ADMINISTRATION
Contracting Officer giving a revised estimate contract, a release discharging the
of the total price to the Government for Government, its officers, agents, and 48 CFR Parts 2, 10, 12, 16, and 52
performing this contract with supporting employees of and from all liabilities,
reasons and documentation. If at any time obligations, and claims arising out of or [FAC 2005–15; FAR Case 2003–027; Item
during performing this contract, the under this contract, subject only to the II; Docket 2006–0020, Sequence 22]
Contractor has reason to believe that the total following exceptions:
RIN 9000–AK07
price to the Government for performing this (1) Specified claims in stated amounts, or
contract will be substantially greater or less in estimated amounts if the amounts are not
Federal Acquisition Regulation; FAR
than the then stated ceiling price, the susceptible of exact statement by the
Contractor shall so notify the Contracting Contractor. Case 2003–027, Additional Commercial
Officer, giving a revised estimate of the total (2) Claims, together with reasonable Contract Types
price for performing this contract, with incidental expenses, based upon the AGENCIES: Department of Defense (DoD),
supporting reasons and documentation. If at liabilities of the Contractor to third parties
General Services Administration (GSA),
any time during performing this contract, the arising out of performing this contract, that
Government has reason to believe that the are not known to the Contractor on the date and National Aeronautics and Space
work to be required in performing this of the execution of the release, and of which Administration (NASA).
contract will be substantially greater or less the Contractor gives notice in writing to the ACTION: Final rule.
than the stated ceiling price, the Contracting Contracting Officer not more than 6 years
Officer will so advise the Contractor, giving after the date of the release or the date of any SUMMARY: The Civilian Agency
the then revised estimate of the total amount notice to the Contractor that the Government Acquisition Council and the Defense
of effort to be required under the contract. is prepared to make final payment, Acquisition Regulations Council
(e) Ceiling price. The Government will not whichever is earlier. (Councils) have agreed on a final rule
be obligated to pay the Contractor any (3) Claims for reimbursement of costs amending the Federal Acquisition
amount in excess of the ceiling price in the (other than expenses of the Contractor by Regulation (FAR) to implement section
Schedule, and the Contractor shall not be reason of its indemnification of the 1432 of the National Defense
obligated to continue performance if to do so Government against patent liability),
jlentini on PROD1PC65 with RULES4

would exceed the ceiling price set forth in including reasonable incidental expenses,
Authorization Act for Fiscal Year 2004.
the Schedule, unless and until the incurred by the Contractor under the terms Title XIV of the Act, referred to as the
Contracting Officer notifies the Contractor in of this contract relating to patents. Services Acquisition Report Act of 2003
writing that the ceiling price has been (h) Interim payments on contracts for other (SARA), amended section 8002(d) of the
increased and specifies in the notice a than services. (1) Interim payments made Federal Acquisition Streamlining Act of

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00013 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74668 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

1994 (FASA) to expressly authorize the and the circumstances under which findings in their comments in response
use of time-and-materials (T&M) and these arrangements are used. Interested to the ANPR, proposed rule, public
labor-hour (LH) contracts for certain parties offered a variety of written meetings, and SARA Panel hearings.
commercial services under specified observations in response to the ANPR OFPP advised the Councils that it is
conditions. and proposed rule. See the Federal designating all categories of services
Register at 70 FR 56320 on September (i.e., any service) as being available for
DATES: Effective Date: February 12,
26, 2005. In addition, a number of acquisition on a T&M and LH basis
2007.
interested parties provided oral because the findings made in
FOR FURTHER INFORMATION CONTACT: For comments during the public meetings conjunction with the rulemaking
clarification of content, contact Mr. that were held on October 19, 2004 and indicate that: (1) services under any
Jeremy Olson, at (202) 501–3221. Please October 18, 2005, to facilitate an open general categorization of services, such
cite FAC 2005–15, FAR case 2003–027. dialogue with Government procurement as those examined by the GAO, are
For information pertaining to status or policy officials. commonly sold to the general public on
publication schedules, contact the FAR OFPP and several Council staff a T&M and LH basis under certain
Secretariat at (202) 501–4755. members also received a briefing from conditions; and (2) use of T&M and LH
SUPPLEMENTARY INFORMATION: the Government Accountability Office contracts under these conditions may be
(GAO) on a survey the GAO conducted in the Government’s best interest.
A. Background
late last year to determine how often However, OFPP further advised that its
This final rule amends the Federal commercial companies use T&M and LH designation is limited to the same
Acquisition Regulation to implement contracts in their commercial practices, circumstances that exist when T&M and
section 1432 of the National Defense either as a buyer or a provider. The GAO LH contracting is commonly used to sell
Authorization Act for Fiscal Year 2004 received 23 responses to its survey. services to the general public and where
(Pub. L. 108–136). Title XIV of the Act, Some of the responses came from the other prerequisites set forth in
referred to as the Services Acquisition Fortune 500 companies. Although section 8002(d) have been met. OFPP
Reform Act of 2003 (SARA), amended responses were limited, the GAO concluded, in view of the findings, that
section 8002(d) of the Federal indicated that they represented buying the identification of effective boundaries
Acquisition Streamlining Act of 1994 practices from a relatively wide range of for the use of T&M and LH contracts is
(FASA) (Pub. L. 103–355, 41 U.S.C. 264) industries, including airline, automotive a function of the specific circumstances
to expressly authorize the use of time- and truck manufacturers, automotive surrounding the acquisition rather than
and-materials (T&M) and labor-hour and truck parts, business services, the specific type of service being sold.
(LH) contracts for commercial services communications equipment, computer OFPP requested that the Councils reflect
under specified conditions. hardware, computer services, electric its designation in the final FAR rule.
Section 8002(d)(3) of the Act limits utilities, insurance, major drugs Specifically, OFPP requested that the
use of T&M and LH contracts to the (pharmaceutical), money center bank, rule allow an agency to purchase any
following categories of commercial non-profit financial services, oil and commercial service on a T&M or LH
services: gas, regional bank, retail (grocery and basis if it has completed a determination
• Commercial services procured for technology), scientific and technical and findings (D&F) containing sufficient
support of a commercial item, as instruments, and semiconductor. facts and rationale to justify that a firm-
described in 41 U.S.C. 403(12)(E). Finally, OFPP reviewed testimony fixed pricing arrangement is not
• Any other category of commercial offered to the Acquisition Advisory suitable. With respect to the contents of
services that is designated by the Panel established pursuant to section the required D&F, OFPP advised the
Administrator of Office of Federal 1423 of SARA to evaluate commercial Councils that the rationale supporting
Procurement Policy (OFPP) on the basis practices and other acquisition-related use of a T&M or LH contract for
that— issues. The Panel specifically sought commercial services must establish that
1. The commercial services in such input regarding industry’s use of T&M a T&M or LH contract is being used
category are of a type of commercial and LH contracts. See http:// under the same conditions where the
services that are commonly sold to the www.acquisition.gov/comp/aap/ private sector would commonly rely on
general public through use of T&M or index.html. these arrangements—namely, where it is
LH contracts; and OFPP made three main findings from not possible at the time of placing the
2. It would be in the best interests of these inputs. First, commercial services contract or order to accurately estimate
the Federal Government to authorize are commonly sold on a T&M and LH the extent or duration of the work or to
use of T&M or LH contracts for purchase basis in the marketplace when anticipate costs with any reasonable
of the commercial services in such requirements are not sufficiently well degree of certainty. In addition, if the
category. understood to complete a well-defined need is of a recurring nature and is
In furtherance of its statutory scope of work and when risk can be being acquired through a contract
responsibilities, OFPP worked in managed by maintaining surveillance of extension or renewal, OFPP expects,
coordination with the Councils on a costs and contractor performance. consistent with FAR 7.103(r), that the
series of questions for the advance Second, these same services are also D&F reflect why knowledge gained from
notice of proposed rulemaking (ANPR), commonly sold on a fixed-price basis. the prior acquisition could not be used
the proposed rule, and the notices of Third, a few types of services are sold to further refine requirements and
public meeting published in the Federal predominantly on a T&M and LH acquisition strategies in a manner that
Register at 69 FR 56316 on September basis—specifically, emergency repair would enable purchase on a fixed-price
20, 2004 and at 70 FR 56318 on services. By their nature, emergency basis.
September 26, 2005, to obtain repair services are difficult to capture in OFPP reminded the Councils that
jlentini on PROD1PC65 with RULES4

information describing how T&M and a well-defined scope of work and agencies will also need to comply with
LH contracts are used commercially. In therefore are not generally conducive to the other limitations set forth in
particular, the questions elicited purchase on a fixed-price basis. Industry 8002(d)—i.e., the service is acquired
information on the types of services that associations, representing a wide range under a contract awarded using
are commonly acquired on this basis of service industries, supported these competitive procedures, the contract or

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00014 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations 74669

order includes a ceiling price that the accounting requirements on commercial interest of the Government) implement
contractor exceeds at its own risk, and T&M contracts (see Comment 4.b.(7)(b)). the statute in a clear and concise
any subsequent change in the ceiling (c) Paragraph (i)(1)(ii)(C)—Excluded manner.
price is authorized only upon a indirect costs as a type of cost that could Comment: Support OFPP’s conclusion
determination, documented in the be reimbursed at actual costs since the that the use of T&M/LH contracts
contract file, that it is in the best interest indirect costs will be reimbursed at the should not be limited to a list of specific
of the procuring agency to change the fixed amount in the schedule(see categories of services. Many types of
ceiling price. Finally, OFPP requested Comment 4.b.(8)(a)). commercial services are sold and
that the rule include appropriate (d) Paragraph (i)(1)(ii)(D)(1)—Revised purchased on both T&M/LH and firm
additional mechanisms that help the rule to allow contracting officers to fixed-price (FFP) basis depending on the
agencies manage risk by maintaining establish the types of other direct costs circumstances of the particular project.
surveillance of costs and contractor (ODC) that will be reimbursed at actual There are no general rules or practices
performance, since effective costs and the fixed amounts for indirect that restrict use of T&M/LH to any
surveillance is emphasized in costs at the order level on indefinite specific service categories. Regardless of
commercial use of T&M and LH delivery indefinite quantity (IDIQ) the service type, there are often times
contracts. contracts. The type of ODC that will be when work cannot be sufficiently
The Councils concur with OFPP’s needed to perform an order and any defined at contract award to provide for
findings and conclusions and have fixed amount for indirect costs may meaningful firm-fixed prices.
shaped the rule accordingly. need to be established on an order-by- Comment: Limit as much as possible
DoD, GSA, and NASA published an order basis (see Comment 4.b.(8)(a)). the types of services eligible to be
advance notice of public rulemaking (e) Paragraph (i)(4)(ii)(A)—Revised the procured on a commercial T&M/LH
(ANPR) in the Federal Register at 69 FR rule to recognize that companies use basis. A list of the types of services
56316 on September 20, 2004 and a both paper-based and electronic commonly sold using commercial T&M
proposed rule at 70 FR 56318 on timecards (see Comment 4.b.(9)(b)). vehicles would help contracting officers
September 26, 2005. Comments were (f) Paragraph (u)—Eliminated the chose the appropriate contract type and
received from 13 respondents in subcontract consent provisions because draft the required D&F.
response to the proposed rule. The the provisions were unduly restrictive, Response: As discussed above,
Councils considered all of the inappropriate, and the provisions could OFPP’s decision is based on its findings
comments and recommendations in have permitted the Government to that— (a) commercial services are
developing the final rule. The Councils inappropriately impact a company’s commonly sold on a T&M and LH basis
made the following changes to the rule commercial reputation (see Comment in the marketplace when requirements
as a result of the public comments and 4.b.(6)(a)). are not sufficiently well understood to
deliberations: complete a well-defined scope of work
(1) 16.601(d)—Added a requirement Public Comment and when risk can be managed by
for the head of contracting activity to The public comments are discussed maintaining surveillance of costs and
approve any D&Fs that would extend below: contractor performance; (b) these same
the period of performance beyond five Comment: Commercial Item services are also generally offered on a
years for both commercial and non- Definition. Agree with deleting the fixed-price basis; and (c) a few types of
commercial T&M contracts to help exclusion of ‘‘services that are sold services are sold predominantly on a
ensure T&M contracts are only used based on hourly rates without an T&M and LH basis—specifically,
when no other type of contract is established catalog or market price for a emergency repair services. Based on
suitable, to maximize the use of fixed specific service performed or a specific these findings, OFPP recommended to
price commercial contracts consistent outcome to be achieved’’ from the the Councils that the rule allow an
with the statute, and to avoid protracted definition of a commercial item to be agency to purchase any commercial
use of non-commercial time-and- consistent with SARA. service on a T&M or LH basis if it has
materials contracts after experience Comment: Market Research. Agree completed a determination and findings
provides a basis for firmer pricing. with adding ‘‘type of contract’’ to the (D&F) containing sufficient facts and
(2) Clause 52.212–4 Alternate I— examples provided for determining rationale to justify that a firm-fixed
(a) Paragraph (i)(1)(ii)(B)—Eliminate practices of firms engaged in producing, pricing arrangement is not suitable.
the provisions that only permitted distributing, and supporting commercial OFPP stated that this conclusion is
reimbursement of subcontract costs at items because it assists with the consistent with the statutory
the hourly rates in the contract schedule implementation of SARA. requirement in section 8002(d) that
when the subcontractors are listed in contracting officers must execute a D&F
contract because the provisions were Appropriate Use that establishes that no contract type is
problematic and contrary to standard Comment: Support OFPP’s decision to suitable before pursuing one of these
commercial practice (see Comment restrict commercial T&M/LH contracts arrangements. The Councils agree with
4.b.(6)(a)). Instead added provisions that to circumstances where no other OFPP’s finding and shaped the rule
require the subcontract to be reimbursed contract type is suitable instead of accordingly. The Councils do not
at the hourly rates prescribed in the developing a list of commercial services believe it is practical or feasible to
contract except when the employees commonly sold on a T&M/LH basis. The develop and maintain a comprehensive
performing the work do not meet the conditions for using commercial T&M/ list of services sold on a T&M/LH basis
qualifications specified in the contract. LH contracts (i.e., the contracting officer because many services may be sold on
(b) Paragraph (i)(1)(ii)(C)(2)— executes a determination and finding both a T&M/LH and fixed price basis
Eliminated the provisions that required that no other contract type is suitable, depending on the circumstances of the
jlentini on PROD1PC65 with RULES4

commercial contractors to give the the contract includes a ceiling price that acquisition. The rule clearly provides
Government credit for rebates, refunds, the contractor exceeds at its own risk, that commercial T&M/LH contracts can
or discounts that ‘‘accrued to’’ the and subsequent changes in the ceiling only be used when the other
contractor because the provision could price only authorized upon a commercial services’ contract types are
have imposed unique Government determination that it is in the best not suitable.

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00015 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74670 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

Comment: Clarify whether basis to be consistent with non- an interpretation that the D&F condition
competitive procedures means ‘‘full and commercial T&M/LH contracts. can be limited to a dollar threshold. The
open competition’’ or ‘‘limited Commercial T&M/LH contracts pose no statute requires a D&F for T&M/LH
competition’’ when the competition is greater risk to the Government than non- contracts regardless of the dollar
conducted with as many sources as commercial T&M/LH contracts. amount.
practicable under one of the authorities Comment: The rule contradicts and
goes beyond the intent of SARA by Nonconforming
listed in FAR 6.302.
Response: Sole source commercial potentially creating, in practice and Comment: Paying for reperformance,
T&M/LH contracts are not authorized. effect, a prohibition on the use of T&M excluding profit, is a significant
Commercial T&M/LH contracts may be contracts. Specifically, the rule adds improvement over the ANPR and
awarded under the statutory authorities administrative burden and procedural properly reflects commercial practices.
that permit contracting without complication to the use of T&M The parties will be permitted to tailor
providing for full and open competition. contracts which would inhibit the use of the provision pursuant to FAR 12.302
When these authorities are used, these contracts as a practical contracting when customary commercial practices
contracting officers are required to tool, e.g., requiring a D&F for each T&M provide different warranty terms.
solicit offers from as many potential task order is beyond the intent of Comment: Except for the default 10
sources as is practicable under the Section 1432 and appears to show little percent profit rate, the proposed
circumstances. Nothing in this rule confidence in the business judgment of provisions are the same as those used
requires ‘‘full and open’’ competition. contracting officers. for non-commercial T&M contracts.
Comment: Restrict the use of T&M Comment: Develop an approval level These provisions contain significant
contracts to when it is not ‘‘practicable’’ for D&Fs commensurate with the risk to departures from terms typically found
instead of not ‘‘possible’’ at the time of the Government. in the commercial marketplace. The
placing the contract or order to Response: The Councils acknowledge proposed 10 percent default profit rate
accurately estimate the extent or that the rule contains additional is irrelevant if the contracting officer
duration of the work or to anticipate requirements for commercial T&M/LH knows the contractor’s profit rate.
costs with any reasonable degree of IDIQ D&Fs than those required for Contracting officers could terminate the
certainty. It may be ‘‘possible’’ to noncommercial T&M/LH IDIQ D&Fs. contract or retain another contractor to
estimate the duration and cost of work While the Councils recognize these complete the work as provided in FAR
but impracticable given the time and additional requirements may be more 52.246–6(f) and (g) if a contractor is
effort that would be required, the burdensome, the Councils believe the expending best efforts and still not
urgency of the work, and the agencies additional requirements are needed to performing properly. Require
competing priorities. encourage the preference for the use of contracting officers to better focus on
Response: T&M contracts comprise fixed price contracts for commercial the requirements of FAR 7.105, Contents
the highest contract type risk to the items. In addition, the Councils believe of Written Acquisition Plans, rather
Government. As such, they should only additional controls are needed to ensure than adopting the proposed inspection
be used when it is not possible at the both commercial and non-commercial and acceptance clause.
time of award to estimate accurately the T&M contracts are only used when no Comment: Contractors are under less
extent or duration of the work or to other type of contract is suitable. The budgetary pressure to perform under a
anticipate costs with any reasonable Councils revised the rule to require T&M contract than a FFP contract and
degree of confidence. Also, restricting head of contracting activity approval for should be held to as stringent quality
the use of T&M contracts to when it is any D&Fs that extend the performance standards as FFP contracts. Paying for
not ‘‘possible’’ is consistent with the period beyond five years for both rework will not discourage ‘‘shoddy
requirements for non-commercial T&M commercial and non-commercial T&M work’’ since the contractor will be
contracts. contracts. reimbursed, without profit, for its costs.
Comment: Establish a $100,000 Develop an appropriate profit
Determination and Finding (D&F) threshold for D&F to recognize a percentage based on historical data or
Comment: Delete the minimum D&F reasonable level at which tangible some other measure to avoid a potential
requirements for justifying no other deliverable would be expected. unintended consequence of establishing
contract type is suitable because Comment: Exempt small purchases at a 10 percent profit standard for T&M
specifying the minimum requirements or below the five million dollar contracts. A 10 percent profit may be
imposes a potentially greater burden on commercial item threshold at FAR excessive for low risk T&M contracts.
contracting officers than the 12.203 from the D&F requirements. This Response: The comments reflect a
corresponding provisions for non- threshold allows agencies to use varying set of commercial practices for
commercial T&M/LH contracts. Delete simplified acquisition procedures up to nonconforming supplies and services.
the requirement to execute a D&F for five million dollars for commercial item The ANPR required contractors to repair
each order when the indefinite-delivery acquisitions. The Councils have or replace rejected supplies or reperform
contract is priced on a T&M/LH or FFP discretion to implement the statutory rejected services at no cost to the
basis because it is inconsistent with provisions addressing D&Fs. See Government. Public commenters on the
FAR 1.602–2 which stipulates Chevron, U.S.A. v. Natural Resources ANPR said requiring contractors to
‘‘contracting officers should be allowed Defense Council, Inc., 467 U.S. 837, 844 repair or replace rejected supplies or
wide latitude to exercise business (1984). reperform rejected services at no cost to
judgment.’’ SARA requires a D&F to Response: When a statute is silent or the Government imposed more contract
justify the contract type, not the use of ambiguous with respect to a certain risk on the contractor than the non-
the contract once justified. issue, agencies have discretion to commercial clause. The Government is
jlentini on PROD1PC65 with RULES4

Comment: Eliminate the requirement interpret the statute in a reasonable essentially imposing a fixed-price level
for approval one level above the manner, consistent with its legislative of risk. Combining a ceiling price that
contracting officer for a commercial history. However, the statute is not contractors exceed at their own risk and
T&M/LH IDIQ contract that only allows ambiguous and the legislative history a requirement that the contractor use
for issuance of orders on a T&M/LH contains nothing which would support ‘‘best efforts’’ to perform within the

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00016 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations 74671

ceiling price means contractors are and that the price for that ‘‘type of subcontracts on commercial contracts
required accomplish a certain result work’’ will be the prime contract’s labor includes ‘‘transfers of commercial items
(i.e., performance of the work specified rate which may be blended or other rate. between divisions, subsidiaries, or
in the Schedule) within a specified Reimburse subcontract labor at the affiliates of a contractor or
dollar amount (i.e., the ceiling price). schedule labor rates without subcontract subcontractor’’ to be consistent with
The Councils agreed that contractors are consent when the subcontractor FASA which specified interdivisional
generally only required to use ‘‘best personnel satisfy the qualification and transfers for commercial items are to be
efforts’’ to accomplish the desired other requirements for the labor treated as subcontracts (see FAR
results within the established ceiling categories for which the contractor is 12.001). Clarify the provisions that
price on both commercial and non- seeking compensation. T&M/LH allow contractors to be reimbursed for
commercial T&M contracts as opposed contracts specify the required labor
its own material at the contractor’s
to FFP contracts which requires qualifications. Whether the person
contractors to accomplish stated results filling the position is an employee of the established catalog or the market price
within the fixed price. Therefore, the prime or a subcontractor, the includes services that meet the
Councils revised the proposed rule to be qualifications must be met. The definition of a commercial item at FAR
consistent with the non-commercial Government has already determined the 2.101. Do not object to appropriate
T&M requirements. The 10 percent price for the ‘‘type of work’’ to be fair subcontractor disclosure requirements
default profit rate will only be used and reasonable by competition. Include when the contractor does not have an
when the contracting officer does not interdivisional transfers and approved purchasing system and the
know the contractor’s actual profit rate, subcontracted labor costs as elements of subcontract will be cost-reimbursement,
which may be commonplace in ‘‘time’’ instead of ‘‘materials’’ to allow time-and-materials, labor-hour, or letter
competitive awards. Contractors are prime contractors to recover adequate contract (see FAR 44.201(b)(1)) but the
under less budgetary pressure to compensation for the time and resources Government should not interject its
perform under a T&M than a FFP it expends on administering authority over the prime contractor’s
contract. However, it is not appropriate subcontracts and for the financial determination of how to accomplish the
to hold contractors to the same exposure is assumes for its work being bid and awarded.
standards used on FFP contracts. The subcontractor’s performance. Recommend the Councils instead
risk of ‘‘shoddy work’’ is inherent to all Comment: Appreciate the Councils consider a notification requirement
‘‘best efforts’’ type contracts. efforts to clarify the treatment for without the need for formal contract
Accordingly, T&M/LH contracts are subcontracts and interdivisional amendment. In the commercial world,
only authorized when no other contract transfers but recommends reimbursing sellers are generally free to delegate
type is suitable. The 10 percent default all subcontract labor at the schedule
their duties to subcontractors as they see
profit rate is arbitrary, not necessarily labor rates to avoid confusion over
fit. In the Government world, agencies
representative of the actual profit rates. whether the costs are reimbursable as
make these determinations in the
However, the rate is intended to protect ‘‘material’’ or ‘‘labor.’’ Separately
the Government by helping to ensure address the proper treatment for evaluation of a contractor’s proposal
profit is not paid for replacement or subcontracts and interdivisional labor to and through oversight of awarded work.
reperformance. avoid inevitable disputes over whether The Government could be exposed to
Comment: The proposed rule does not the costs should be treated as ‘‘labor’’ or claims for delay or disruption when the
address reimbursement of costs for ‘‘material.’’ Contractors frequently contractor is attempting to substitute
providing accommodations to the require use of subcontractors for any one qualified subcontractor for another
Government for testing and inspections number of reasons included to: and approvals are improperly denied or
at contractor and subcontractors’ (a) Secure specific skill sets; unreasonable delayed. The Councils
facility. Fairness dictates that the (b) Augment an existing workforce; concerns that the basis for ‘‘best value’’
Government reimburse contractors and (c) Use small and/or small, determination used to award the
subcontractors for reasonable costs disadvantaged businesses to meet contract may be altered by contractors
incurred for the required socioeconomic goals; adding or substituting subcontractors
accommodations. (d) Incorporate small business after award do not justify the provisions
Response: The costs for providing innovative solutions; and that limit reimbursement of subcontract
accommodations to the Government for (e) Replace subcontractors during costs to those listed in the contract or
testing and inspecting at contractor and contract performance for failure to those subsequently approved by the
subcontractors’ facilities are generally achieve the prime contractor’s contracting officer. The question is not
included in the fully burdened labor performance standards.
one of reimbursement but of
rate. Prime contractors may not know
which subcontractors will be used to Government payment for services
Subcontracts and Interdivisional Labor perform the work since T&M contracts rendered. The attendant administrative
Comment: Reimburse subcontract are used when it is not possible to procedures in the proposed rule might
labor at the schedule labor rates without estimate accurately the extent or impede the contractor’s ability to
listing the subcontractors in the contract duration of work at the time of award. deliver services in accordance with the
for standard commercial services, e.g., Contractors will not know at the time of terms of the contract. The ‘‘consent to
‘‘on-call’’ IT installation and repair award which subcontractors may be subcontract’’ provisions and payment
services in support of commercial IT used to fulfill ‘‘on call’’ or ‘‘on demand’’ limitations significantly increase the
products. Reimburse subcontract labor services. It is unfair to require risk to contractors for meeting contract
at the schedule labor rates without contractors to perform services without deliverables. The administrative and
jlentini on PROD1PC65 with RULES4

listing the subcontractors in the contract knowing in advance whether the financial burden of establishing and
when the contractor’s proposal indicates necessary subcontractors can be brought maintaining a list of subcontractors that
that some of the work may be performed to task and how the contractor will be can be reimbursed at the hourly
by subcontractors that meet the reimbursed. Expand the definition of schedule rates increases contract
contract’s qualification requirements ‘‘subcontract’’ to clarify that execution risk.

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00017 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74672 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

Comment: Consent to subcontract is rates. Subcontractors have reported commercial practices and the intent of
inconsistent with the underlying intent primes charging prime contractor labor FASA. Further, the proposed rule failed
of commercial acquisitions. rates for the subcontractor’s labor while to fully consider the implications of
Coalition and Comment: Reimburse paying the subcontractors significantly subsequently altering the elements
interdivisional transfers at the schedule lower rates. Vendors should make a included in the catalog or market prices.
hourly rates like subcontract labor. The reasonable profit on services provided The catalog or market prices will be
proposed rule restricts reimbursement to the Government but there is no determined fair and reasonable based on
for interdivisional transfers (e.g., justification for unduly enriching competition. Subsequent modifications
transfers from divisions, subsidiaries, contractors by allowing them to charge to the elements of those prices could
and affiliates under the common control their own higher rates for subcontract impact the overall pricing integrity and
of the commercial contractor) to cost, effort. Permitting contractors to bill their the fair and reasonable determination.
without profit or fee, unless the established rates for work they Finally, limiting reimbursement to
interdivisional transfer meets the subcontract out will likely have the actual costs discourages subcontracting
definition of a commercial item at FAR unintended consequence of creating and would have a negative impact on
2.101. Commercial contractors will be new vendor organizations developed small businesses. Small businesses
required to identify the actual costs, solely to extract higher profits from traditionally receive approximately 35
potentially subjecting their allowability Government projects. Contractors that percent of subcontracts on Government
to a determination under the cost believe the Government is best served prime contracts and only 24 percent of
principles. Commercial contractors by permitting the wide use of prime Government contracts.
should have the ability to use any of subcontracts are free to do so in FFP Reimbursing subcontracts at actual costs
their resources without penalty of profit agreements. Revise or restate in a clearer is not consistent with the treatment on
erosion. These contracts have fashion the provisions regarding all other flexibly priced Government
commercial market reference points and reimbursement for subcontract efforts at contracts where prime contractors are
disallowing profit discourages vendors proposed FAR 52.212–4(i)(1)(ii)(B) paid profit on subcontract costs.
from using their best employees to meet because the provisions are difficult to Restricting reimbursement of
the Government’s needs. follow. subcontract costs to actual costs ‘‘as
Comment: Revise the instructions for Response: The methodology in the long as those costs do not exceed the
reimbursing subcontracts at the proposed rule was problematic and prime’s rates’’ is not equitable or fair.
schedule rate to clearly permit the contrary to standard commercial Upon further consideration, the
listing of actual or ‘‘potential’’ practice. Councils believe it is appropriate to
subcontractor name(s) since the First, the rule permitted reimburse commercial subcontracts at
subcontractors listed for reimbursement reimbursement of commercial materials, the schedule labor rates without listing
at the schedule hourly rates may reflect including subcontracts and
the subcontracts when the contractor’s
a pool of ‘‘potential’’ subcontractors that interdivisional transfers, at the
established catalog or market price
may or may not actually work on the contractor’s established catalog or
includes the price of its subcontracts for
contract. market price. At the same time, the rule
Comment: Reimburse all subcontract the reasons discussed above. The
limited reimbursement of qualifying
costs at the schedule hourly rates Councils revised the rule accordingly. In
commercial subcontracts to actual costs
without requiring contracting officer addition, the Councils believe imposing
unless the subcontracts were listed in
consent to be consistent with subcontract consent requirements on
the contract for reimbursement at the
commercial practices. these commercial subcontracts is
hourly schedule rates. For some
Comment: Reimburse subcontract unduly restrictive and inappropriate
commercial companies, the established
efforts requiring consent only if proper catalog or market price for its and revised the rule accordingly. If a
advance consent is obtained. Do not commercial material (including contracting officer failed to provide a
allow contracting officers to subcontracts and interdivisional timely consent or disagreed with the
retroactively grant consent for transfers) is the prime contractor’s subcontract award, the Government
subcontracts. established catalog or market price for could wrongly affect contract
Comment: Restrict reimbursement of labor. Reimbursing commercial performance and potentially impact a
subcontract costs to actual costs because materials at actual cost is inconsistent company’s commercial reputation. The
the prime contractor could subsequently with commercial practices and contrary Councils also revised the rule to
negotiate lower rates with to the statutory preference for recognize that subcontracts under FAR
subcontractors that were authorized to acquisitions of commercial items and Part 12 include transfers of commercial
be paid at the schedule rates and the the intent of FASA, i.e., established items between divisions, subsidiaries,
Government would pay excessive prices acquisition policies more closely and affiliates of a contractor or
for subcontracted effort that may be of resembling those of the commercial subcontractor to be consistent with FAR
a level less than that envisioned by the marketplace. In addition, subcontracts 12.001. Finally, the Councils did not
Government. Reimbursement at the under FAR Part 12 include transfers of believe it was necessary to clarify that
schedule rates encourages contractors to commercial items between divisions, qualifying services are commercial
maximize profit by subcontracting out subsidiaries, or affiliates of a contractor items since the definition of commercial
more of the effort at lower subcontract or subcontractor. While the actual costs items at FAR 2.101 clearly identifies the
rates. Government will expend for subcontracts other than services that meet the definition of
additional resources to monitor the interdivisional transfers can be easily commercial services.
quality and efficiency of subcontract determined from an independent third Comment: Agree subcontract consent
labor since the subcontract effort will party invoice, actual costs for applies only to costs that are directly
jlentini on PROD1PC65 with RULES4

not be readily apparent when billed at interdivisional transfers can only be charged to the contract and not
the schedule rates. determined using the procedures of FAR overhead expenses and G&A but
Comment: Restrict reimbursement of Part 31. Imposing FAR Part 31 recommend explicitly stating so in the
subcontract costs to actual costs as long requirements on commercial final rule to avoid future questions
as those costs do not exceed the prime’s interdivisional transfers is contrary to about the application of this provision.

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00018 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations 74673

Response: As noted above, the final eliminate the two contradictory amounts recovered under the contracts
rule does not require subcontract methods for reimbursing indirect costs. for those elements of cost.
consents. The proposed rule permits Comment: Clarify which contracting
reimbursement at a fixed amount but officer (the contracting officer who
Material Costs awards the contract or the one that
also defines indirect costs as an element
Comment: Agree there should be no of material costs that can only be awards the task order) has the authority
‘‘most favored customer’’ pricing reimbursed at actual costs unless the and ability to make determination on
requirement because it is a barrier for material meets the definition of the method for reimbursing subcontract
market entry and inconsistent with the commercial item. efforts and the allowability of ODC and
Government pricing policies at FAR Response: The Councils revised the indirect costs for IDIQ or Multiple
Subpart 15.4. rule to eliminate the contradictory Award Schedule (MAS) contracts.
Comment: Refunds. Reimbursement methods. Instead of excluding indirect Response: As stated in the alternate
of material at actual costs less any costs from the definition of materials, clause at (i)(1)(ii)(D)(1) and (2) of
rebates, refunds, or discounts received the Councils revised the provisions in 52.212–4, Alternate I, the contracting
by or accrued to the contractor is the alternate clause at FAR 52.212–4, officer awarding the indefinite delivery
contrary to commercial practice which Alternate I (i)(1)(ii)(D)(2) to exclude contract can authorize other contracting
does not rely on cost accounting indirect costs from being reimbursed at officers to determine how ODC and
information. If an accrual entry is made actual cost. indirect costs will be reimbursed.
at all, the accrual is typically identified Comment: Agree with the provisions Comment: Revise the rule to clarify
to more global considerations (e.g., total that permit reimbursement of indirect ODC and indirect costs will only be
volume of purchases), not individual costs at a fixed price on a pro-rata basis recovered as stand alone elements of
contract actions. The reference to over the period of contract performance costs if the amounts are not also
accruals and other cost accounting data but recommend clarifying that the fixed included in the loaded labor rates.
is not appropriate. price could be adjusted as new work is Response: ODC and indirect costs
Comment: Delete the requirement for added and also allowing contractors to should only be recovered as separate
commercial companies to give the be reimbursed at the Government elements of costs if they are excluded
Government credit for rebates from approved percentage mark-up for non- from the schedule labor rates. However,
interdivisional labor since the divisions commercial contracts. Cost Accounting contracting officers will not always
will likely have little visibility into the Standards (CAS) covered contractors are know the elements of costs included in
other business units. required to allocate material handling in the schedule labor rates since
Comment: Delete the requirement to accordance with their approved commercial T&M/LH contracts can only
provide the Government credit for accounting practices. Material handling be awarded using competitive
rebates on commercial T&M contracts. rates are well-recognized in Federal and procedures. Generally, contracting
Vendors typically provide some services commercial markets. The Councils are officers are precluded from obtaining
(e.g., maintenance on standard proposing to reimburse indirect costs at detailed cost information on these types
equipment) through the organizational a fixed price because of concerns over of acquisitions. However, contracting
resources of their commercial business. violating the cost-plus-a-percentage-of- officers will know the proposed amount
Federal entities have little visibility into cost prohibition. Material handling rates for indirect expenses and the types of
those business units, creating a dilemma do not add fee or any other price ODC proposed to be reimbursed at
as to how to account for a rebate. component to cost and therefore could actual costs for each competing
Response: The Councils do not not be considered a cost-plus-a- contractor during the proposal
believe it is appropriate to require percentage-of-cost violation. evaluation phase.
unique Government accounting Recommend revising the coverage to Government Oversight
requirements for materials on permit contractors to recover material
commercial T&M/LH contracts. The handling provided it is excluded from Comment: The right to interview
Councils revised the rule to only require the hourly rates. contractor employees is unreasonable
contractors to reduce the costs of Response: If new work is added, a intrusive and contrary to customary
material for any rebates, refunds, or fixed amount may be added for indirect commercial practice. Notwithstanding a
discounts that are identifiable to the expenses if appropriate. Nothing in the statement by the Councils to the
contract. rule prevents contract changes. The contrary, no similar right exists in the
Comment: Revise the proposed approved percentage mark-up for non- FAR for any contract type. The audit
provisions to say modification to items commercial contracts is subject to the clause at FAR 52.215–2 gives the
that meet the definition of commercial allowability provisions of FAR Part 31. contracting officer the right to examine
items at FAR 2.101 are reimbursed at The Councils believe it is more ‘‘records and other evidence’’ to verify
‘‘price’’ instead of ‘‘actual costs’’ for to appropriate to reimburse indirect costs claimed costs. Records are not defined
be consistent with FAR Subpart 15.4. without imposing the requirements of to include interviews and it is hard to
Response: Depending on the FAR Part 31 to be consistent with believe ‘‘other evidence’’ includes
circumstance of a particular acquisition, commercial practices. While the employee interviews. This new right
it may be appropriate to pay ‘‘price’’ commenter disagrees, the Councils lacks precedent in the FAR. Not even
instead of ‘‘costs’’ for modifications to believe use of a fixed rate violates the the Offices of Inspector General under
commercial items. To provide cost plus percentage of cost contract the Inspectors General Act has this
maximum flexibility to the contracting prohibition. CAS covered contractors authority. The Government does not
officer, the Councils revised the rule to already allocate material handling and need this newly created contractual
permit reimbursement at either price or other indirect costs to commercial and right because the Government already
jlentini on PROD1PC65 with RULES4

cost. non-commercial FFP contracts in has this right in cases of alleged fraud
accordance with their disclosed or wrongdoing pursuant to its subpoena
Indirect Costs and Other Direct Costs accounting practices. While the costs powers under applicable statutes. The
Comment: Exclude indirect costs from are allocated to those FFP contracts, the Government should rely on the invoices
the definition of material costs to allocation may be different from the which are required, under penalty of

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00019 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74674 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

law, to be accurate. The right to surveillance of Government contracts Training would be more appropriately
interview employees is not required by and are required by DCAA’s Mandatory addressed in agency training materials.
SARA or any other law. This authority Annual Audit Requirements (MAARs).
Withholds
also conflicts with FASA which requires The Government should not have to
commercial item contracts contain only allege wrongdoing to interview Comment: Explicitly state contracting
those terms and conditions that are contractor employees when their labor officers cannot withhold on commercial
required by law or customary in the hours are included on invoices T&M/LH contracts because some
commercial marketplace. There is no submitted to the Government. The contracting officers may elect to
provision in SARA for this approach, a Councils do not believe that SARA or withhold even though the practice is not
fact recognized by Defense Contract FASA requires the Government to make specifically allowed by the payment
Audit Agency (DCAA) in its April 9, payments based on actual hours clause.
2004 ‘‘GSA Schedule’’ memorandum. incurred without being able to verify the Response: We do not contemplate
Comment: Commercial T&M/LH employees actually worked the hours withholds in commercial contracts but
contracts are subject to a strict oversight charged. The Councils have carefully there may be circumstances, at the
process performed by company project considered existing requirements for contracting officer’s discretion, where
managers that are accountable for the T&M contracts as well as differences withholds are appropriate.
successful completion of the work. between commercial and non- Contractor Purchasing System Review
Comment: Oppose the rule because commercial contracts. The Councils (CPSR)
commercial contracts will not be subject believe that the rule provides the proper
to full oversight and audit provisions. Comment: The proposed rule
balance between the need to verify prohibits contractors with firm fixed-
To protect taxpayer interests, compliance with contract terms and the
commercial T&M/LH contracts should price (FFP) or FFP with economic price
need to minimize access to contractor adjustment (EPA) contracts from
be subject to full oversight, audits, and records. Finally, the Councils believe
CAS. Additionally, the commercial obtaining approved purchasing systems
the oversight provided in the rule will thereby creating a ‘‘class of contractor’’
T&M contracts need clauses for refunds provide sufficient information to verify
or price reduction so the Government that can never obtain an approved
the validity of amounts claimed on the purchasing system. This new class of
can recoup overages identified in the contract without the oversight
audit. contractors will have more oversight in
requirements in FAR and CAS that are terms of subcontractor approval and
Comment: Remove the restriction that
imposed on noncommercial T&M/LH approval of subcontract modifications.
limits the Government’s access to
contracts. These contractors are currently exempt
records to those listed in the contract
because the Government should not Comment: Define the term ‘‘original from the subcontract approval process—
limit its access to records. timecards’’ broadly enough to an exemptions supported by FASA and
Response: The rule permits, but does encompass both paper-based and FARA.
not require, contracting officers to have electronic timecards because many Comment: Do not impose CPSR on
access to contractor employees. While companies use electronic timecards. commercial contractors because doing
such access may not be a standard Response: The Councils revised the so may deter commercial companies
commercial practice, the Councils final rule to provide access to original from doing business with the
believe employee interviews may be timecards (paper-based or electronic). Government. Commercial contractors
necessary in some cases to verify the Comment: Provide contracting officers may not perform sufficient Government
hours claimed by the contractor. specific guidance regarding what prime business to justify the establishment of
According to one commenter in oversight efforts are adequate for a CPSR.
response to the ANPR, requiring access subcontracts listed in the contract and Response: The objective of a
to contractor employees is a standard reimbursed at the schedule rates. contractor purchasing system review
commercial practice for T&M Contracting officers may lack the (CPSR) is to evaluate the efficiency and
contracting. The provisions for access to expertise or time to assess the existence effectiveness with which the contractor
contractor employees are no broader or quality of a contractor’s mechanism spends Government funds. The review
than what is currently provided for to oversee the qualifications and hours provides the cognizant contracting
under non-commercial T&M contracts. worked by subcontractor employees. officer a basis for granting, withholding,
FAR 52.215–2, Audit and Records— The only way to substantiate or withdrawing approval of the
Negotiation, provides the Government qualifications and hours worked is contractor’s purchasing system. Under
the right to examine and audit all through examination of payrolls and the existing FAR requirements, the
records and other evidence sufficient to resumes for each subcontractor. Government does not review a
reflect properly all cost claimed to have Response: The prime contractor is contractor’s purchasing system if all the
been incurred or anticipated to be responsible for the oversight of its contractor’s Governments sales are
incurred directly or indirectly in subcontractors. When requested by the commercial FFP and FFP EPA contracts.
performance of the contract. The Government, the contractors are The same is true if all a contractor’s
Government routinely conducts required to substantiate invoices Government sales are non-commercial
employee interviews and other audit (including any subcontractor hours competitively awarded firm-fixed-price
procedures to verify that labor costs at reimbursed at the hourly rate in the and competitively awarded fixed-price
contractor locations having fixed-price, schedule) by evidence of actual with economic price adjustment
cost-reimbursement, incentive, non- payment, individual daily job contracts. For these types of contracts,
commercial time-and-material and labor timecards, records that verify the the Government has no reason to
hour, commercial, or price employees meet the qualifications for evaluate the efficiency and effectiveness
jlentini on PROD1PC65 with RULES4

redeterminable contracts are charged to the labor categories specified in the with which the contractor spends
the correct contract and not contract, or other substantiation Government funds since the amounts
inappropriately shifted to the flexibly specified in the contract. Contracting paid to the contractor are not affected by
priced Government contracts. Employee officers can seek the advice of the the efficiency and effectiveness of the
interviews are part of DCAA’s normal cognizant audit office when needed. contractors’ purchasing practices. The

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00020 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations 74675

proposed rule did not impose a CPSR departures from standard commercial costs with any reasonable degree of
requirement but simply recognized that practices, contrary to the spirit of FASA certainty. If it is possible to estimate the
contractors who otherwise have and in violation of FAR 12.301(a)(2) that extent or duration of work or anticipate
approved purchasing systems require require commercial item contracts to costs with a reasonable degree of
less oversight of their subcontractors only include those clauses determined certainty, T&M/LH contracts should not
because the contractor’s overall system to be consistent with customary be used.
provides adequate controls and commercial practices. Other provisions Comment: The use of the term
procedures to protect the Government. of the rule extend the Government’s ‘‘schedule’’ may be confusing to some
However, the Councils revised the rule audit and oversight inappropriately and who understand it to refer to MAS or
to eliminate the subcontract consent unnecessary. Deeply concerned that the FSSs contracts. The subcontract
requirement which means subcontracts proposed rule will undercut the intent reimbursement provisions that permit
for T&M contracts awarded pursuant to of SARA by creating what effectively reimbursement of subcontracts at the
FAR Part 12 will be excluded from amounts to a prohibition on the use of hourly rates prescribed in the schedule
CPSRs. T&M contracts. The rule adds could be interpreted to mean there are
significant administrative burden, separate subcontract rates on MAS
Cost Accounting Standards (CAS) procedural complications, and certain contracts. Clarify the final rule the term
Comment: Do not apply CAS and significant financial disincentives. is not meant to connote MAS contracts.
other onerous Government-only Recommend the Councils reconsider the Response: The term is used
requirements to commercial T&M/LH entire approach to T&M contracting and throughout the FAR and widely
contracts because doing so is counter to the expansive rulemaking in the understood by contracting professionals.
acquisition reform legislation that proposed rule. Also, recommend the The Councils are unaware of any issues
envisions the Government purchasing Councils hold additional public with its interpretation and does not
more like its commercial counterparts. meetings to provide the public believe changing the term could be
Congress exempted commercial item additional opportunities to explain the confusing to contracting professionals.
contracts from CAS; however, the CAS submitted comments. Recommend This is not a significant regulatory
Board only exempted FFP and FFP EPA delaying issuance of a final rule until action and, therefore, was not subject to
contracts. Agree the Councils lack the the Acquisition Advisory Panel has review under Section 6(b) of Executive
authority to make CAS changes but released its report and Order 12866, Regulatory Planning and
recommend the Councils implement the recommendations since there may be a Review, dated September 30, 1993. This
statute and treat T&M contracts as conflict between their recommendations rule is not a major rule under 5 U.S.C.
covered by the existing CAS exclusions. and this rule. 804.
Response: The decision as to whether Response: The Councils reviewed
public comments and held two public B. Regulatory Flexibility Act
CAS applies to commercial T&M/LH
contracts rests with the CAS Board. The meetings, obtaining a very complete The Regulatory Flexibility Act, 5
Councils have limited the imposition of picture of the views of interested parties U.S.C. 601, et seq., applies to this final
other Government-only requirements to on this rule, and have determined it is rule. The Councils prepared a Final
the maximum extent practicable. The appropriate to go forward with a final Regulatory Flexibility Analysis (FRFA),
Councils do not believe commercial rule. It is highly unlikely that further and it is summarized as follows:
T&M/LH contracts are currently comments or public meetings would 1. Statement of need for, and objectives of,
exempted by any CAS exemption and provide any information or opinions not the rule.
already provided and evaluated. This final rule revises the Federal
therefore cannot simply waive the
Comment: Concur. Acquisition Regulation to allow contracting
requirements of CAS. officers to award Time and Material and
Comment: Industry does not prefer
Total Cost Labor Hour (T&M/LH) contracts when
T&M contracts and would avoid them
procuring commercial items. This FAR case
Comment: The rule establishes a for IT work. was initiated to implement Section 1432 of
notification procedure much like the Response: T&M/LH contracts the National Defense Authorization Act for
limitation of cost and limitation of represent the highest contract type risk Fiscal Year 2004 (Pub. L. 108–136).
funds clauses for non-commercial items. and industry, like the Government, 2. Summary of significant issues raised by
Since this rule involves contracts for avoids using them to the maximum the public comments in response to the
commercial items, suggest it instead extent practicable. However, there are Initial Regulatory Flexibility Analysis
refer to ‘‘Total Price.’’ circumstances when these contract (IRFA), a summary of the assessment of the
Response: While the rule relates to types are needed and used. agency of such issues, and a statement of any
Comment: The main difference changes made in the proposed rule as a
commercial T&M/LH contracts, some result of such comments.
material and ODC will be reimbursed at between the commercial market and the
Thirteen (13) comments were received
‘‘cost’’ not ‘‘price.’’ Therefore, the rule is the rule only requires the from the public in response to the proposed
Councils did not revise the title as contractor to use its ‘‘best efforts’’ to rule. One of the most significant areas of
suggested. perform within the ceiling. There is no controversy in the proposed rule issued for
consumer in the commercial market that public comment concerned the matter of
General Comments would blindly allow a car repair shop to labor provided by subcontractors. The
Comment: Do not support the rule in work on their car for up to $1,000 proposed rule required that the prime
its present form. without any guarantee that the car will contractor be reimbursed at actual cost for all
Comment: In a number of areas, the be fixed. subcontractors providing labor under the
proposed rule simply imports into this Response: T&M/LH contracts, contract, unless a subcontractor was
commercial items regulation many of commercial and non-commercial, are specifically authorized under the prime
contract by inclusion on a list of
jlentini on PROD1PC65 with RULES4

the terms and conditions already used ‘‘best effort’’ contracts that can only be subcontractors to be reimbursed at the prime
by the Government when purchasing used when it is not possible at the time contract labor hour rate. Public commenters
non-commercial T&M/LH contracts. of placing the contract or order to complained that this procedure created major
This action results in the inclusion of accurately estimate the extent or administrative burdens and, because
provisions that are significant duration of the work or to anticipate reimbursement at actual cost did not permit

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00021 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74676 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

prime contractors to obtain profit of those that the prime contractor be reimbursed at PART 10—MARKET RESEARCH
subcontracts, it would significantly reduce actual cost for all subcontractors providing
the use of subcontractors. The commenters labor under the contract, unless a 10.001 [Amended]
pointed out that the subcontractors at issue subcontractor was specifically authorized ■ 3. Amend section 10.001 by removing
are commonly small businesses. under the prime contract by inclusion on a from paragraph (a)(3)(iv) ‘‘as terms’’ and
The final rule eliminates this feature list of subcontractors to be reimbursed at the
regarding payment of labor subcontractors at
adding ‘‘as type of contract, terms’’ in its
prime contract labor hour rate. Public
actual cost and use of a list of approved commenters complained that this procedure place.
subcontractors. The final rule provides that a created major administrative burdens and, ■ 4. Amend section 10.002 by revising
prime contractor can provide qualifying labor because reimbursement at actual cost did not paragraph (b)(1)(iii) to read as follows:
hours under the contract through use of permit prime contractors to obtain profit of
subcontractors and the government will pay 10.002 Procedures.
those subcontracts, it would significantly
the prime contract labor hour rate, without reduce the use of subcontractors. The * * * * *
use of any pre-authorization list in the commenters pointed out that the (b) * * *
contract. Prime contractors will be able to subcontractors at issue are commonly small (1) * * *
include profit on this labor and there will be businesses. (iii) Customary practices, including
no special administrative approvals required. The final rule eliminates this feature warranty, buyer financing, discounts,
The final rule approach eliminates the part regarding payment of labor subcontractors at contract type considering the nature and
of the proposed rule that was most actual cost and use of a list of approved
objectionable to small entities.
risk associated with the requirement,
subcontractors. The final rule provides that a etc., under which commercial sales of
3. Description of, and an estimate of the prime contractor can provide qualifying labor
number of, small entities to which the rule hours under the contract through use of
the products or services are made;
will apply or an explanation of why no such subcontractors and the government will pay * * * * *
estimate is available. the prime contract labor hour rate, without
This rule will apply to small and large use of any pre-authorization list in the PART 12—ACQUISITION OF
entities that accept Time-and-Material or contract. Prime contractors will be able to COMMERCIAL ITEMS
Labor-Hour contracts for commercial items. include profit on this labor and there will be
Because this rule is the first FAR no special administrative approvals required. ■ 5. Revise section 12.207 to read as
authorization for use of these types of The final rule approach eliminates the part follows:
contracts for commercial items, no history is of the proposed rule that was most
available on the number of awards made to objectionable to small entities. 12.207 Contract type.
small businesses. However, the Federal (a) Except as provided in paragraph
Interested parties may obtain a copy
Procurement Data System (FPDS) data from (b) of this section, agencies shall use
FY 2004 show that small businesses received of the FRFA from the FAR Secretariat.
The FAR Secretariat has submitted a firm-fixed-price contracts or fixed-price
approximately 50 percent of the 42,840 contracts with economic price
noncommercial item T&M/LH awards made copy of the FRFA to the Chief Counsel
and approximately 30% of the $17 Billion for Advocacy of the Small Business adjustment for the acquisition of
obligated under those awards. Administration. commercial items.
4. Description of the projected reporting, (b)(1) A time-and-materials contract or
recordkeeping, and other compliance C. Paperwork Reduction Act labor-hour contract (see Subpart 16.6)
requirements of the rule, including an may be used for the acquisition of
The Paperwork Reduction Act does
estimate of the classes of small entities commercial services when—
not apply because the changes to the
which will be subject to the requirement and (i) The service is acquired under a
the type of professional skills necessary for FAR do not impose information
contract awarded using—
preparation of the report or record. collection requirements that require the (A) Competitive procedures (e.g., the
The rule would require contractors to approval of the Office of Management procedures in 6.102, the set-aside
maintain records to support invoices and Budget under 44 U.S.C. 3501, et procedures in Subpart 19.5, or
presented to the Government for payment. seq.
Such records would include original
competition conducted in accordance
timecards, the contractor’s timekeeping List of Subjects in 48 CFR Parts 2, 10, with Part 13);
procedures, distribution of labor, invoices for 12, 16, and 52 (B) The procedures for other than full
material, and so forth. These are standard and open competition in 6.3 provided
records maintained by any company, large or Government procurement. the agency receives offers that satisfy
small, and the fact that the contract would Dated: December 4, 2006. the Government’s expressed
require that these records be made available Linda K. Nelson, requirement from two or more
to the Government should not place any responsible offerors; or
Deputy Director, Contract Policy Division.
additional record keeping burden on the (C) The fair opportunity procedures in
entity. ■ Therefore, DoD, GSA, and NASA 16.505, if placing an order under a
5. Description of steps the agency has amend 48 CFR parts 2, 10, 12, 16, and
taken to minimize significant economic
multiple award delivery-order contract;
52 as set forth below: and
impact on small entities consistent with the
■ 1. The authority citation for 48 CFR (ii) The contracting officer—
stated objectives of applicable statutes,
including a statement of the factual, policy, parts 2, 10, 12, 16, and 52 continues to (A) Executes a determination and
and legal reasons for selecting the read as follows: findings (D&F) for the contract, in
alternative adopted in the final rule and why Authority: 40 U.S.C. 121(c); 10 U.S.C. accordance with paragraph (b)(2) of this
each of the other significant alternatives to chapter 137; and 42 U.S.C. 2473(c). section (but see paragraph (c) of this
the rule considered by the agency was section for indefinite-delivery
rejected. PART 2—DEFINITIONS OF WORDS contracts), that no other contract type
Public comments submitted in response to AND TERMS authorized by this subpart is suitable;
the proposed rule were reviewed and
(B) Includes a ceiling price in the
substantial policy adjustments to the rule 2.101 [Amended]
jlentini on PROD1PC65 with RULES4

were made as a result. One of the most contract or order that the contractor
significant areas of controversy in the ■ 2. Amend section 2.101 in paragraph exceeds at its own risk; and
proposed rule issued for public comment (b), in the definition ‘‘Commercial (C) Authorizes any subsequent change
concerned the matter of labor provided by item’’, by removing the second sentence in the ceiling price only upon a
subcontractors. The proposed rule required in the introductory text of paragraph (6). determination, documented in the

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00022 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations 74677

contract file, that it is in the best interest shall be approved one level above the (i) Signed by the contracting officer
of the procuring agency to change the contracting officer. Placement of orders prior to the execution of the base period
ceiling price. shall be in accordance with Subpart or any option periods of the contracts;
(2) Each D&F required by paragraph 16.5. and
(b)(1)(ii)(A) of this section shall contain (d) The contract types authorized by (ii) Approved by the head of the
sufficient facts and rationale to justify this subpart may be used in conjunction contracting activity prior to the
that no other contract type authorized with an award fee and performance or execution of the base period when the
by this subpart is suitable. At a delivery incentives when the award fee base period plus any option periods
minimum, the D&F shall— or incentive is based solely on factors exceeds three years; and
(i) Include a description of the market other than cost (see 16.202–1 and (2) The contract includes a ceiling
research conducted (see 10.002(e)); 16.203–1). price that the contractor exceeds at its
(ii) Establish that it is not possible at (e) Use of any contract type other than own risk. The contracting officer shall
the time of placing the contract or order those authorized by this subpart to document the contract file to justify the
to accurately estimate the extent or acquire commercial items is prohibited. reasons for and amount of any
duration of the work or to anticipate ■ 6. Amend section 12.301 by adding a subsequent change in the ceiling price.
costs with any reasonable degree of sentence after the first sentence in Also see 12.207(b) for further limitations
certainty; and paragraph (b)(3) to read as follows: on use of Time-and-Materials or Labor
(iii) Establish that the requirement has Hour contracts for acquisition of
been structured to maximize the use of 12.301 Solicitation provisions and
contract clauses for the acquisition of commercial items.
firm-fixed-price or fixed-price with
commercial items. * * * * *
economic price adjustment contracts
* * * * * ■ 9. Revise section 16.602 to read as
(e.g., by limiting the value or length of
(b) * * * follows:
the time-and-material/labor-hour
(3) * * * Use this clause with its
contract or order; establishing fixed 16.602 Labor-hour contracts.
Alternate I when a time-and-materials or
prices for portions of the requirement) Description. A labor-hour contract is a
labor-hour contract will be awarded. *
on future acquisitions for the same or variation of the time-and-materials
**
similar requirements. contract, differing only in that materials
(iv) Describe actions planned to * * * * *
■ 7. Amend section 12.403 by revising
are not supplied by the contractor. See
maximize the use of firm-fixed-price or 12.207(b), 16.601(c), and 16.601(d) for
fixed-price with economic price paragraph (d)(1)(i) to read as follows:
application and limitations, for time-
adjustment contracts on future 12.403 Termination. and-materials contracts that also apply
acquisitions for the same requirements. to labor-hour contracts. See 12.207(b)
(3) See 16.601(d)(1) for additional * * * * *
(d) * * * for the use of labor-hour contracts for
approval required for contracts expected certain commercial services.
(1) * * *
to extend beyond three years. (i)(A) The percentage of the contract
(c)(1) Indefinite-delivery contracts PART 52—SOLICITATION PROVISIONS
price reflecting the percentage of the
(see Subpart 16.5) may be used when— AND CONTRACT CLAUSES
work performed prior to the notice of
(i) The prices are established based on
the termination for fixed-price or fixed- ■ 10. Amend section 52.212–4 by—
a firm-fixed-price or fixed-price with
price with economic price adjustment ■ a. Revising the date of the clause;
economic price adjustment; or
(ii) Rates are established for contracts; or ■ b. Adding a new sentence after the
(B) An amount for direct labor hours third sentence in the introductory text
commercial services acquired on a time-
(as defined in the Schedule of the of paragraph (a); and
and-materials or labor-hour basis.
(2) When an indefinite-delivery contract) determined by multiplying the ■ c. Adding Alternate I;
contract is awarded with services priced number of direct labor hours expended ■ The revised and added text reads as
on a time-and-materials or labor-hour before the effective date of termination follows:
basis, contracting officers shall, to the by the hourly rate(s) in the Schedule;
maximum extent practicable, also and 52.212–4 Contract Terms and
* * * * * Conditions—Commercial Items.
structure the contract to allow issuance
of orders on a firm-fixed-price or fixed- * * * * *
price with economic price adjustment PART 16—TYPES OF CONTRACTS CONTRACT TERMS AND CONDITIONS—
COMMERCIAL ITEMS (FEB 2007)
basis. For such contracts, the ■ 8. Amend section 16.601 by adding a (a) Inspection/Acceptance. * * * If repair/
contracting officer shall execute the D&F sentence to the end of paragraph (c) replacement or reperformance will not
required by paragraph (b)(2) of this introductory text and revising paragraph correct the defects or is not possible, the
section, for each order placed on a time- (d) to read as follows: Government may seek an equitable price
and-materials or labor-hour basis. reduction or adequate consideration for
Placement of orders shall be in 16.601 Time-and-materials contracts. acceptance of nonconforming supplies or
accordance with Subpart 8.4 or 16.5, as * * * * * services. * * *
applicable. (c) Application. * * * See 12.207(b) * * * * *
(3) If an indefinite-delivery contract for the use of time-and-material (End of clause)
only allows for the issuance of orders on contracts for certain commercial Alternate I (FEB 2007). When a time-and-
a time-and-materials or labor-hour basis, services. materials or labor-hour contract is
the D&F required by paragraph (b)(2) of contemplated, substitute the following
* * * * *
this section shall be executed to support paragraphs (a), (e), (i) and (l) for those in the
(d) Limitations. A time-and-materials basic clause.
jlentini on PROD1PC65 with RULES4

the basic contract and shall also explain contract may be used only if— (a) Inspection/Acceptance. (1) The
why providing for an alternative firm- (1) The contracting officer prepares a Government has the right to inspect and test
fixed-price or fixed-price with economic determination and findings that no all materials furnished and services
price adjustment pricing structure is not other contract type is suitable. The performed under this contract, to the extent
practicable. The D&F for this contract determination and finding shall be— practicable at all places and times, including

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00023 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74678 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

the period of performance, and in any event to believe that the employee is habitually prescribed in the contract by the number of
before acceptance. The Government may also careless or unqualified. direct labor hours performed. Fractional parts
inspect the plant or plants of the Contractor (7) This clause applies in the same manner of an hour shall be payable on a prorated
or any subcontractor engaged in contract and to the same extent to corrected or basis.
performance. The Government will perform replacement materials or services as to (B) The rates shall be paid for all labor
inspections and tests in a manner that will materials and services originally delivered performed on the contract that meets the
not unduly delay the work. under this contract. labor qualifications specified in the contract.
(2) If the Government performs inspection (8) The Contractor has no obligation or Labor hours incurred to perform tasks for
or tests on the premises of the Contractor or liability under this contract to correct or which labor qualifications were specified in
a subcontractor, the Contractor shall furnish replace materials and services that at time of the contract will not be paid to the extent the
and shall require subcontractors to furnish all delivery do not meet contract requirements, work is performed by individuals that do not
reasonable facilities and assistance for the except as provided in this clause or as may meet the qualifications specified in the
safe and convenient performance of these be otherwise specified in the contract. contract, unless specifically authorized by
duties. (9) Unless otherwise specified in the the Contracting Officer.
(3) Unless otherwise specified in the contract, the Contractor’s obligation to (C) Invoices may be submitted once each
contract, the Government will accept or reject correct or replace Government-furnished month (or at more frequent intervals, if
services and materials at the place of delivery property shall be governed by the clause approved by the Contracting Officer) to the
as promptly as practicable after delivery, and pertaining to Government property. Contracting Officer or the authorized
they will be presumed accepted 60 days after (e) Definitions. (1) The clause at FAR representative.
the date of delivery, unless accepted earlier. 52.202–1, Definitions, is incorporated herein (D) When requested by the Contracting
(4) At any time during contract by reference. As used in this clause— Officer or the authorized representative, the
performance, but not later than 6 months (or (i) Direct materials means those materials Contractor shall substantiate invoices
such other time as may be specified in the that enter directly into the end product, or (including any subcontractor hours
contract) after acceptance of the services or that are used or consumed directly in reimbursed at the hourly rate in the
materials last delivered under this contract, connection with the furnishing of the end schedule) by evidence of actual payment,
the Government may require the Contractor product or service. individual daily job timecards, records that
to replace or correct services or materials that (ii) Hourly rate means the rate(s) prescribed verify the employees meet the qualifications
at time of delivery failed to meet contract in the contract for payment for labor that for the labor categories specified in the
requirements. Except as otherwise specified meets the labor category qualifications of a contract, or other substantiation specified in
in paragraph (a)(6) of this clause, the cost of labor category specified in the contract that the contract.
replacement or correction shall be are— (E) Unless the Schedule prescribes
otherwise, the hourly rates in the Schedule
determined under paragraph (i) of this (A) Performed by the contractor;
shall not be varied by virtue of the Contractor
clause, but the ‘‘hourly rate’’ for labor hours (B) Performed by the subcontractors; or
having performed work on an overtime basis.
incurred in the replacement or correction (C) Transferred between divisions,
(1) If no overtime rates are provided in the
shall be reduced to exclude that portion of subsidiaries, or affiliates of the contractor
Schedule and the Contracting Officer
the rate attributable to profit. Unless under a common control.
approves overtime work in advance, overtime
otherwise specified below, the portion of the (iii) Materials means— rates shall be negotiated.
‘‘hourly rate’’ attributable to profit shall be 10 (A) Direct materials, including supplies (2) Failure to agree upon these overtime
percent. The Contractor shall not tender for transferred between divisions, subsidiaries, rates shall be treated as a dispute under the
acceptance materials and services required to or affiliates of the contractor under a Disputes clause of this contract.
be replaced or corrected without disclosing common control; (3) If the Schedule provides rates for
the former requirement for replacement or (B) Subcontracts for supplies and overtime, the premium portion of those rates
correction, and, when required, shall disclose incidental services for which there is not a will be reimbursable only to the extent the
the corrective action taken. [Insert portion of labor category specified in the contract; overtime is approved by the Contracting
labor rate attributable to profit.] (C) Other direct costs (e.g., incidental Officer.
(5)(i) If the Contractor fails to proceed with services for which there is not a labor (ii) Materials.
reasonable promptness to perform required category specified in the contract, travel, (A) If the Contractor furnishes materials
replacement or correction, and if the computer usage charges, etc.); that meet the definition of a commercial item
replacement or correction can be performed (D) The following subcontracts for services at FAR 2.101, the price to be paid for such
within the ceiling price (or the ceiling price which are specifically excluded from the materials shall be the contractor’s established
as increased by the Government), the hourly rate: [Insert any subcontracts for catalog or market price, adjusted to reflect
Government may— services to be excluded from the hourly rates the—
(A) By contract or otherwise, perform the prescribed in the schedule.]; and (1) Quantities being acquired; and
replacement or correction, charge to the (E) Indirect costs specifically provided for (2) Any modifications necessary because of
Contractor any increased cost, or deduct such in this clause. contract requirements.
increased cost from any amounts paid or due (iv) Subcontract means any contract, as (B) Except as provided for in paragraph
under this contract; or defined in FAR Subpart 2.1, entered into (i)(1)(ii)(A) and (D)(2) of this clause, the
(B) Terminate this contract for cause. with a subcontractor to furnish supplies or Government will reimburse the Contractor
(ii) Failure to agree to the amount of services for performance of the prime the actual cost of materials (less any rebates,
increased cost to be charged to the Contractor contract or a subcontract including transfers refunds, or discounts received by the
shall be a dispute under the Disputes clause between divisions, subsidiaries, or affiliates contractor that are identifiable to the
of the contract. of a contractor or subcontractor. It includes, contract) provided the Contractor—
(6) Notwithstanding paragraphs (a)(4) and but is not limited to, purchase orders, and (1) Has made payments for materials in
(5) above, the Government may at any time changes and modifications to purchase accordance with the terms and conditions of
require the Contractor to remedy by orders. the agreement or invoice; or
correction or replacement, without cost to the (i) Payments. (1) Services accepted. (2) Makes these payments within 30 days
Government, any failure by the Contractor to Payment shall be made for services accepted of the submission of the Contractor’s
comply with the requirements of this by the Government that have been delivered payment request to the Government and such
contract, if the failure is due to— to the delivery destination(s) set forth in this payment is in accordance with the terms and
(i) Fraud, lack of good faith, or willful contract. The Government will pay the conditions of the agreement or invoice.
misconduct on the part of the Contractor’s Contractor as follows upon the submission of (C) To the extent able, the Contractor
jlentini on PROD1PC65 with RULES4

managerial personnel; or commercial invoices approved by the shall—


(ii) The conduct of one or more of the Contracting Officer: (1) Obtain materials at the most
Contractor’s employees selected or retained (i) Hourly rate. advantageous prices available with due
by the Contractor after any of the Contractor’s (A) The amounts shall be computed by regard to securing prompt delivery of
managerial personnel has reasonable grounds multiplying the appropriate hourly rates satisfactory materials; and

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00024 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations 74679

(2) Give credit to the Government for cash obligated to continue performance if to do so completion invoice, and supporting
and trade discounts, rebates, scrap, would exceed the ceiling price set forth in documentation, shall be submitted by the
commissions, and other amounts that are the Schedule, unless and until the Contractor as promptly as practicable
identifiable to the contract. Contracting Officer notifies the Contractor in following completion of the work under this
(D) Other Costs. Unless listed below, other writing that the ceiling price has been contract, but in no event later than 1 year (or
direct and indirect costs will not be increased and specifies in the notice a such longer period as the Contracting Officer
reimbursed. revised ceiling that shall constitute the may approve in writing) from the date of
(1) Other Direct Costs. The Government ceiling price for performance under this completion.
will reimburse the Contractor on the basis of contract. When and to the extent that the (6) Release of claims. The Contractor, and
actual cost for the following, provided such ceiling price set forth in the Schedule has each assignee under an assignment entered
costs comply with the requirements in been increased, any hours expended and into under this contract and in effect at the
paragraph (i)(1)(ii)(B) of this clause: [Insert material costs incurred by the Contractor in time of final payment under this contract,
each element of other direct costs (e.g., travel, excess of the ceiling price before the increase shall execute and deliver, at the time of and
computer usage charges, etc. Insert ‘‘None’’ shall be allowable to the same extent as if the as a condition precedent to final payment
if no reimbursement for other direct costs will hours expended and material costs had been under this contract, a release discharging the
be provided. If this is an indefinite delivery incurred after the increase in the ceiling Government, its officers, agents, and
contract, the Contracting Officer may insert price. employees of and from all liabilities,
‘‘Each order must list separately the elements (4) Access to records. At any time before obligations, and claims arising out of or
of other direct charge(s) for that order or, if final payment under this contract, the under this contract, subject only to the
no reimbursement for other direct costs will Contracting Officer (or authorized following exceptions.
be provided, insert ‘None’’.’] representative) will have access to the (i) Specified claims in stated amounts, or
(2) Indirect Costs (Material Handling, following (access shall be limited to the in estimated amounts if the amounts are not
Subcontract Administration, etc.). The listing below unless otherwise agreed to by susceptible to exact statement by the
Government will reimburse the Contractor the Contractor and the Contracting Officer): Contractor.
for indirect costs on a pro-rata basis over the (i) Records that verify that the employees (ii) Claims, together with reasonable
period of contract performance at the whose time has been included in any invoice incidental expenses, based upon the
following fixed price: [Insert a fixed amount meet the qualifications for the labor liabilities of the Contractor to third parties
for the indirect costs and payment schedule. categories specified in the contract; arising out of performing this contract, that
Insert ‘‘$0’’ if no fixed price reimbursement (ii) For labor hours (including any are not known to the Contractor on the date
for indirect costs will be provided. (If this is subcontractor hours reimbursed at the hourly of the execution of the release, and of which
an indefinite delivery contract, the rate in the schedule), when timecards are the Contractor gives notice in writing to the
Contracting Officer may insert ‘‘Each order required as substantiation for payment— Contracting Officer not more than 6 years
must list separately the fixed amount for the (A) The original timecards (paper-based or after the date of the release or the date of any
indirect costs and payment schedule or, if no electronic); notice to the Contractor that the Government
reimbursement for indirect costs, insert (B) The Contractor’s timekeeping is prepared to make final payment,
‘None’).’’] procedures; whichever is earlier.
(2) Total cost. It is estimated that the total (C) Contractor records that show the (iii) Claims for reimbursement of costs
cost to the Government for the performance distribution of labor between jobs or (other than expenses of the Contractor by
of this contract shall not exceed the ceiling contracts; and reason of its indemnification of the
price set forth in the Schedule and the (D) Employees whose time has been Government against patent liability),
Contractor agrees to use its best efforts to included in any invoice for the purpose of including reasonable incidental expenses,
perform the work specified in the Schedule verifying that these employees have worked incurred by the Contractor under the terms
and all obligations under this contract within the hours shown on the invoices. of this contract relating to patents.
such ceiling price. If at any time the (iii) For material and subcontract costs that (7) Prompt payment. The Government will
Contractor has reason to believe that the are reimbursed on the basis of actual cost— make payment in accordance with the
hourly rate payments and material costs that (A) Any invoices or subcontract Prompt Payment Act (31 U.S.C. 3903) and
will accrue in performing this contract in the agreements substantiating material costs; and prompt payment regulations at 5 CFR part
next succeeding 30 days, if added to all other (B) Any documents supporting payment of 1315.
payments and costs previously accrued, will those invoices. (8) Electronic Funds Transfer (EFT). If the
exceed 85 percent of the ceiling price in the (5) Overpayments/Underpayments. (i) Each Government makes payment by EFT, see
Schedule, the Contractor shall notify the payment previously made shall be subject to 52.212–5(b) for the appropriate EFT clause.
Contracting Officer giving a revised estimate reduction to the extent of amounts, on (9) Discount. In connection with any
of the total price to the Government for preceding invoices, that are found by the discount offered for early payment, time shall
performing this contract with supporting Contracting Officer not to have been properly be computed from the date of the invoice. For
reasons and documentation. If at any time payable and shall also be subject to reduction the purpose of computing the discount
during the performance of this contract, the for overpayments or to increase for earned, payment shall be considered to have
Contractor has reason to believe that the total underpayments. The Contractor shall been made on the date that appears on the
price to the Government for performing this promptly pay any such reduction within 30 payment check or the specified payment date
contract will be substantially greater or less days unless the parties agree otherwise. The if an electronic funds transfer payment is
than the then stated ceiling price, the Government within 30 days will pay any made.
Contractor shall so notify the Contracting such increases, unless the parties agree (l) Termination for the Government’s
Officer, giving a revised estimate of the total otherwise. The contractor’s payment will be convenience. The Government reserves the
price for performing this contract, with made by check. If the Contractor becomes right to terminate this contract, or any part
supporting reasons and documentation. If at aware of a duplicate invoice payment or that hereof, for its sole convenience. In the event
any time during performance of this contract, the Government has otherwise overpaid on of such termination, the Contractor shall
the Government has reason to believe that the an invoice payment, the Contractor shall immediately stop all work hereunder and
work to be required in performing this immediately notify the Contracting Officer shall immediately cause any and all of its
contract will be substantially greater or less and request instructions for disposition of the suppliers and subcontractors to cease work.
than the stated ceiling price, the Contracting overpayment. Subject to the terms of this contract, the
Officer will so advise the Contractor, giving (ii) Upon receipt and approval of the Contractor shall be paid an amount for direct
the then revised estimate of the total amount invoice designated by the Contractor as the labor hours (as defined in the Schedule of the
jlentini on PROD1PC65 with RULES4

of effort to be required under the contract. ‘‘completion invoice’’ and supporting contract) determined by multiplying the
(3) Ceiling price. The Government will not documentation, and upon compliance by the number of direct labor hours expended
be obligated to pay the Contractor any Contractor with all terms of this contract, any before the effective date of termination by the
amount in excess of the ceiling price in the outstanding balances will be paid within 30 hourly rate(s) in the contract, less any hourly
Schedule, and the Contractor shall not be days unless the parties agree otherwise. The rate payments already made to the Contractor

VerDate Aug<31>2005 18:10 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00025 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4
74680 Federal Register / Vol. 71, No. 238 / Tuesday, December 12, 2006 / Rules and Regulations

plus reasonable charges the Contractor can DEPARTMENT OF DEFENSE Secretary of Defense, the Administrator
demonstrate to the satisfaction of the of General Services and the
Government using its standard record GENERAL SERVICES Administrator of the National
keeping system that have resulted from the ADMINISTRATION Aeronautics and Space Administration.
termination. The Contractor shall not be This Small Entity Compliance Guide
required to comply with the cost accounting has been prepared in accordance with
standards or contract cost principles for this NATIONAL AERONAUTICS AND Section 212 of the Small Business
purpose. This paragraph does not give the SPACE ADMINISTRATION Regulatory Enforcement Fairness Act of
Government any right to audit the
1996. It consists of a summary of rules
Contractor’s records. The Contractor shall not 48 CFR Chapter 1 appearing in Federal Acquisition
be paid for any work performed or costs
incurred that reasonably could have been
[Docket FAR—2006—0023, Sequence 8] Circular (FAC) 2005–15 which amend
avoided. the FAR. An asterisk (*) next to a rule
Federal Acquisition Regulation; indicates that a regulatory flexibility
[FR Doc. 06–9613 Filed 12–6–06; 8:45 am] Federal Acquisition Circular 2005–15; analysis has been prepared. Interested
BILLING CODE 6820–EP–S Small Entity Compliance Guide parties may obtain further information
AGENCIES: Department of Defense (DoD), regarding these rules by referring to FAC
General Services Administration (GSA), 2005–15 which precedes this document.
and National Aeronautics and Space These documents are also available via
Administration (NASA). the Internet at http://
ACTION: Small Entity Compliance Guide. www.regulations.gov.

SUMMARY: This document is issued FOR FURTHER INFORMATION CONTACT


under the joint authority of the Laurieann Duarte, FAR Secretariat, (202)
501–4225. For clarification of content,
contact the analyst whose name appears
in the table below.

LIST OF RULES IN FAC 2005–15


Item Subject FAR case Analyst

*I ........... Payments Under Time-and-Materials and Labor-Hour Contracts ................................................... 2004–015 Olson.
*II .......... Additional Commercial Contract Types ........................................................................................... 2003–027 Olson.

SUPPLEMENTARY INFORMATION: Time-and-Materials (T&M) and Labor- referred to as the Services Acquisition
Summaries for each FAR rule follow. Hour (LH) contracts and the policies Reform Act of 2003 (SARA), amended
For the actual revisions and/or regarding payments made under those section 8002(d) of the Federal
amendments to these FAR cases, refer to contracts. The objectives of the changes Acquisition Streamlining Act of 1994
the specific item number and subject set are to ensure fair and reasonable prices (FASA) (Pub. L. 103–355, 41 U.S.C. 264)
forth in the documents following these under T&M and LH contracts and to to expressly authorize the use of Time–
item summaries. eliminate confusion related to payment and–Materials (T&M) and Labor–Hour
FAC 2005–15 amends the FAR as amounts for subcontractor provided (LH) contracts for commercial services
specified below: labor. under specified conditions.
Item I—Payments Under Time-and- Item II—Additional Commercial Dated: December 4, 2006.
Materials and Labor-Hour Contracts Contract Types (FAR Case 2003–027) Linda K. Nelson,
(FAR Case 2004–015) This final rule implements section Deputy Director, Contract Policy Division.
This final rule revises and clarifies 1432 of the National Defense [FR Doc. 06–9612 Filed 12–6–06; 8:45 am]
policies related to award and Authorization Act for Fiscal Year 2004 BILLING CODE 6820–EP–S
administration of noncommercial item (Pub. L. 108–136). Title XIV of the Act,
jlentini on PROD1PC65 with RULES4

VerDate Aug<31>2005 20:08 Dec 11, 2006 Jkt 211001 PO 00000 Frm 00026 Fmt 4701 Sfmt 4700 E:\FR\FM\12DER4.SGM 12DER4

You might also like