You are on page 1of 28

Traceability

System

Management

Software Requirements Specification


Draft Version 1.0

Page 1 of 28

Contents
1.

Introduction......................................................................................................... 4

2.

Purpose............................................................................................................... 4

3.

Scope................................................................................................................... 4

4.

Definitions, Acronyms and Abbreviations............................................................4

5.

References........................................................................................................... 5

6.

Overall Description.............................................................................................. 5

7.

External Interface Requirements.........................................................................7

8.

Functional Requirements..................................................................................... 8

9.

Non Functional Requirements............................................................................11


9.1

Usability....................................................................................................... 11

9.2

Security........................................................................................................ 11

9.3

Performance................................................................................................. 12

9.4

Capacity....................................................................................................... 12

9.5

Recovery...................................................................................................... 12

9.6

Availability................................................................................................... 13

9.7

Reliability..................................................................................................... 13

9.8

Maintainability............................................................................................. 13

9.9

Portability..................................................................................................... 13

9.10 Privacy......................................................................................................... 13

Page 2 of 28

Revision History
Name

Date

Reason For Changes

Version

Ashwin,Umang,
Sapan

14/02/1
6

First documentation of the SRS document


for Defect and submission Management

Version 1.0

Page 3 of 28

1. Introduction
Traceability is a property of an element of documentation or code that indicates the
degree to which it can be traced to its origin. It is the process of recording logical
links between individual requirements and other system elements. Tracing can be
done in both forward and backward fashion. A single functional requirement can be
traced backward to its origin, such as a use case, product feature or business rule or
trace that functional requirement forward into the bits of design, code and test
cases..
It supports numerous software engineering activities like change impact analysis,
compliance verification or trace back of code, regression test selection and
requirements validation by using varied techniques. It enhances the team
productivity and provides a perspective about the project.

2. Purpose
The purpose of this Software Requirements Specification (SRS) document is to
describe the overall behavior of Traceability Management System (TMS). This SRS
defines and describes the operations, performance, and quality assurance
requirements of the TMS that is to be developed. This document also describes
the nonfunctional requirements. It also describes the design constraints and
technologies that are to be considered when the system is to be designed,
and other factors necessary to provide a complete description of the requirements
for the system. This Software Requirements Specification (SRS) captures the
complete software requirements for the system. Requirements described in this
document will be used as guidelines to develop the Traceability Management
System.

3. Scope
Traceability management tool aims at automation of the following processes:

Generation of Reports of the various processes involved in the entire course


of the product
Creation of Various Self Explanatory Models and graphs of each stage
involved in the development of the product.
The Traceability matrix is explicitly provided for facilitating overview of the
product and the completeness of the product.
A Model for Management of the Changes made in the project over a period of
time
Page 4 of 28

4. Definitions, Acronyms and Abbreviations


Abbreviation
TMS
SRS

Designation
Testing Tool Management
System
Software
Requirements
Specification

5. References

6. Overall Description
6.1

Product Perspective

Testing Management system will help users to test their codes .There would be
two columns one for expected output and actual output. If the actual output of
user doesnt matches with expected output then the user can submit their
problem by using the form. The status of defect will show pending if the defect is
not rectified and after the rectification of defect the status of problem will show
problem solved. The problem of the user is registered by a unique id and is
solved by skilled programmers. The solution is then posted by the programmers.

Page 5 of 28

Pro ject ma nag er

A dm in

Tra cea bli tyM an ge men tsy ste m

Overview of the proposed system

6.2

Product Functions

The following are the user requirements for the system


6.2.1 The tester assigned to the test case can enter the defect for the test case
by entering the following details.
6.2.1.1

Defect Description

6.2.1.2

The other details given below are automatically filled.

6.2.1.2.1 Project Name


6.2.1.2.2 Test Case Name
6.2.1.2.3 Tester Id The defect details are assigned by the tester for
the test case.
6.2.1.2.4 Programmer ID The programmer responsible for the test
case.
6.2.1.2.5 Defect open Date Current date and time
6.2.1.2.6 Status Open

Page 6 of 28

6.2.2 The Programmer assigned to the test case can view the following details
about the defect for the test case he has be assigned. The Project Manager
can view all the defect test case details.
6.2.2.1

Input

6.2.2.2

Actual Output

6.2.2.3

Expected output

6.2.2.4

Test Case ID

6.2.2.5

Project ID

6.2.2.6

Requirement ID

6.2.2.7

Defect ID

6.2.2.8

Defect Description

6.2.2.9

Tester Assigned

6.2.2.10 Assigned Date and time


6.2.2.11 Programmer Assigned
6.2.2.12 Status of the defect
6.2.2.13 Closed Date
6.2.3 The Programmer assigned to the defect can enter the solution of the
defect for the test case by entering the following details.
6.2.3.1

Defect Solution Description

6.2.3.2

The other details given below are automatically filled.

6.2.3.2.1 Defect Close Date Current date and time


6.2.3.2.2 Status - Close

6.3

User characteristics

End users should have basic knowledge of computer systems to adapt to the
form based user interfaces offered by the system with sufficient documentation
and end user training.

Page 7 of 28

TESTER: He is the person who will test the code and finds is there any
difference between actual and expected output.
PROGRAMER: He is the person who rectifies the errors and gives the
solution of problem.
PROJECT MANAGER: He can view all the defect status of all programmers.

6.4

Constraints
6.4.1 Migration of all existing problems registered by users to the database.
6.4.2 Separate database for the debugged solutions issued by programmers.
6.4.3 Solution cant be posted without getting it tested from the tester.

6.5

Assumptions and dependencies


6.5.1 Solution of the problems would only be issued to the users after they
are successfully tested by the users.

7. External Interface Requirements


7.1

User Interfaces
1

The system will provide GUI for the users.

Message display when we click on button.

Standard buttons, functions, or navigation links that will appear on


every screen, such as a help button.

7.2

Hardware Interfaces
7.2.1 To use TTMS, you will need a PC (regardless of its operating system, it
can be Windows, Linux) or Mac. The system requirements are
1. CPU: 2 x Intel Core 2 (2.66 Ghz, 128K cache)
2. RAM: 2GB
3. Minimum database space: 10GB
7.2.2 If system doesnt have touch input, a keyboard will also be required by
the user to provide input.

7.3

Software Interfaces
1

The system will have an interface with the problem posted by the
users and solution issued by programmers.
Page 8 of 28

7.4

Communications Interfaces
1

The system will use click once deployment technology of the


windows .net framework where in windows form based applications
can be accessed through http over the internet. The web Browsers
include
Internet Explorer 10, 11 & Edge
Firefox (recent versions).
Chrome, Safari, Webkit (recent versions).

Page 9 of 28

8. Functional Requirements
8.1

Use Case Diagrams

1. LOGIN

2. Requirement Tracing

Project Manager
Project Manager

3.Version Modeling

4.Traceability Matrix
Generation

Page 10 of 28

5. Report Generation

6. Model Generation by
admin

Project Manager

7. Model Generation by
Project Manager

Page 11 of 28

Project Manager

8.2

Use Case Scenario Description

Use Case ID

Use Case
Name

Log In Page

Summary

Project Manager and admin will have their log in IDs.


First they have to choose which user class they
belong to. A login page will be provided. Where they
can enter their user name and password for user
verification. The first page consists of following
Program Manager Log In
Admin Log In
After choosing the user type they will be redirected
to second page. Which consists of following
Enter Username text field
Enter Password
Forgot Password
After the user enters the details their username and
password will be verified from database. In case the user
forgets his password. Then on clicking the forgot
password link the password will be sent to his registered
Email ID.

Preconditions

User must have his credentials in the database.

Page 12 of 28

Success End
Condition

You have logged in Successfully Message is displayed to


the user.

Failed End
Condition

If User could not provide his right details.

Primary,
Secondary
Actors

Program Managers and admin who will enter the details for
verification.

Trigger

Description

Ste
p

Action

The End user opens the first login Page.

End user will select his user type.

User will be redirected to the second page.

User will enter the user name and password for


verification.

If the user name and password get verified you


have logged in successfully message will be
displayed.

In case the user forgets his username. He will click


on the forgot password link. Password will be sent
to his registered Email ID.

Page 13 of 28

Use Case ID

Use Case name Requirement Tracing


Summary

After selecting the requirement ID from the given list of


requirements in the combo box, the user accountable for the
project can trace requirement changes for the project with model
generation by choosing one of the methods (radio buttons)
given below :
1. Generate model with last n requirements.
The following options will be enabled.

TEXT FIELD: The user has to enter the number of


requirements revisions; he wants a track of from the
updated one.

2. Generate Model with revisions during selected Dates.


The following options will be enabled.

DATE CALENDAR: The FROM and TO date should be


selected from date picker and the following options can
be selected.
3. Generate Model with ALL revisions till date.
TRACK: The user can generate the model by clicking the
button TRACK and fetch the revision traces of a
particular requirement.
4.

Preconditions

Export as PDF: The user can download the model or mail


by entering the
e-mail addresses of the recipients.

The Admin or Project Manager must be authorized and

Page 14 of 28

logged in.
Success End
Condition

The Email sent Successful


displayed to the User.

Failed End
Condition

Please enter valid email address message is displayed to


the Project Manager when wrong mail Id is written.

Primary,
Secondary
Actors

Admin, Project Manager

Trigger

This use case is initiated when user clicks on Requirement


Tracing.

DESCRIPTION

Ste
p

Action

The User selects the requirement id from the combo box.

Confirmation

Message

is

The user chooses a model generation method based on


revisions.

2a

(Only one option can be selected from the three options


available.)

2b

If the user selects, Last n changes, follow step 3

2c

Else If the user selects, Select dates, follow step 4


Else If the user selects, All changes, follow step 5

The user has to enter the number of requirements


revisions, they wants a track of from the updated one in
the text field and follow step 5.

The user should select the FROM date and To date and
follow step 5.
This step will basically give the updates made during that
time period.
The User clicks on TRACK to generate a model.

The user can save the model details by clicking Export as


PDF.

Page 15 of 28

The user clicks on MAIL REPORT to mail to the recipients.


(it will direct you to the page Report_send_mail)

5a

The user enters the emails address of the recipients in the


specified text box.

5b
5c

Use Case ID

Click on Send button to send the mail and get a message


whether the mail has been send or not.

Use Case name Version Modeling


Summary

The user is supposed to enter the version id of the respective


project, it wants to generate the model for. It immediately pops
up with the recent statistics on that particular version.
Now onwards, the user will be able to generate the model and
perform various decision making and analytical process. Also,
the documentation could be downloaded as a PDF and mailed to
concerned people.

Preconditions

The Admin or Project Manager must be authorized and


logged in.

Success End
Condition

The model generated successfully and we can see about the


test cases, design, requirements for a given version.

Failed End
Condition

If the model doesnt get generated then the colors version (root
node) doesnt changes into green.

Primary,
Secondary
Actors

Admin, Project Manager

Trigger

This use case is initiated when user clicks on Version Modeling.

DESCRIPTION

Ste
p

Action

Page 16 of 28

The User selects the version id from the combo box.


The recent status pops up with details like last updated,
members involved etc.

Follow step 2.
The User clicks on Generate Model button to generate a
model.

The user can save the model details by clicking Export as


PDF.

2a
2b

As soon as user clicks on Generate Model the model gets


generated.
That model will shown in two colors red and green where
green refers to selected item for our project i.e. whatever
things are green are required for our project (test case,
design,requirement,version).

Use Case ID

Use
name

Traceability Matrix Generation

Summary

Case

The entire perspective of the project is generated using the


traceability matrix. The matrix consists of various attributes that
include system IDs, project IDs within the system as well as the
requirement IDs for the given project as well as the design
descriptions and the test cases in a form of a tabular matrix.
Whenever a change occurs in any of the attributes, an
intermediate matrix is generated upon the request of the user.
The entire details regarding a particular requirement, test case
or a design description is provided through a hyperlink enabled
on the respective attribute.
The final updated matrix is available in a pdf format for the

Page 17 of 28

managers usage.

The manager must poses a valid login address to access


the matrix.

Preconditions

The databases for the project, designers, test cases must


be predefined and permanent.

Success End
Condition

The matrix is generated and is available in a pdf format for the


usage of the project manager.

Failed End
Condition

An error message will be displayed indicating the details of the


failed condition.

Primary,
Secondary
Actors

Project Manager and a system administrator.

Trigger

This use case is initiated when Project Manager clicks on


Generate matrix.

DESCRIPTION

Ste
p

Action

The manager selects the system for which the matrix has
to be generated.

Page 18 of 28

The Project Manager clicks on the Generate matrix button.


2
3
4

The entire summary of the system is displayed to the


user.
If and when the user desires the complete details
regarding any of the attributes a hyperlink thus enabled
will perform the task.

The respective windows will be displayed containing the


attributes ID and its description.
The case when multiple test cases have to be reviewed
simultaneously, clicking on the respective check boxes,
we can submit using the submit button.

The above matrix is available to download in a PDF format


for the usage of the manager.

Use Case ID

Use
name

Report Generation

Case

Page 19 of 28

Summary

The Project Manageraccountable forthe project and admin can


generate reports for his project by choosing one of the methods
given below
METHOD 1: Report on Status of Project Components.
The following options will be enabled.

GENERATE REPORT: The project manager and admin


can generate the report and save the report as a
softcopy. Also he can take printout.

MAIL REPORT: The project manager and admin can mail


the report by entering the e-mail addresses of the
recipients.

METHOD 2: Report
selected Dates.

on

completed

components

during

The following options will be enabled.

DATE CALENDER : The FROM and TO date should be


selected and the following options can be selected

GENERATE REPORT: The project manager and admin


can generate the report and save the report as a
softcopy. Also he can take printout.

MAIL REPORT: The project manager and admin can mail


the report by entering the e-mail addresses of the
recipients.
Preconditions

The Project Managerand admin must be authorized and


Page 20 of 28

logged in.
Success End
Condition

The Email sent Successful


displayed to the user.

Confirmation

Message

is

Failed End
Condition

Please enter valid email address message is displayed to


the userwhen wrong mail Id is written.

Primary,
Secondary
Actors

Project Manager, admin

Trigger

This use case is initiated when userclicks on Generate Report.

DESCRIPTION

Ste
p

Action

The user clicks on the Generate Report button.

The user chooses a report generation method.


2
2a
2b

If he clicks on Report on
Components, follow step 4 or 5.

Status

of

Project

If he clicks on Report on completed components


during selected Dates, follow step 3.

The user should select the FROM date and To date and
follow step 4 or step 5.

4a

The user Clicks on GENERATE REPORT to generate


Report.

4b

The user can save or print the report.

Page 21 of 28

The user Clicks on MAIL REPORT to mail to the


recipients.

5a
5b

The user enters the email address of the recipients in the


specified text box.

5c
Click on Send button to send the mail.

Use Case ID

Use
name

Model Generation by admin

Case

Summary

The admin for the project can generate models for any project
by choosing the method given below
METHOD 3: Model for Project.
The following options will be enabled.

SELECT MODEL: The admin can choose any project from


the list of various projects and generate model for those
project. Also he can be able to check status of projects.

GENERATE MODEL: The admin can generate the model


by selecting the project based on project id.
Preconditions

The Admin must be authorized and logged in.

Success End
Condition

Green color Object is displayed to the Admin if a project is


completed.

Failed End
Condition

Red color object is displayed to the Admin when project is not


completed.

Page 22 of 28

Primary,
Secondary
Actors

Admin.

Trigger

This use case is initiated when Admin clicks on Model on the


home page or he clicks on generate model in the traceability
matrix.

DESCRIPTION

Ste
p

Action

1
1a
1b

2
2a

The Admin clicks Model link to go to the selection of


project page
The Admin clicks the generate model button in the
traceability matrix

The Admin chooses the project and clicks on Generate


Button.
If he clicks on Generate Model, then follow step3.

The Admin can view the model for that project.


3
If he clicks on any Object in the model, then follow Step 4.
4a
4b
4c
4d

If the Admin clicks on Project ID Object, then display the


whole model.
If the Admin clicks on Requirement ID Object, then
display that requirement, design and test cases for that
requirement.
If the Admin clicks on Design ID Object, then display
design, test cases for that design component.
If the Admin clicks on Test Case ID Object, then display
Page 23 of 28

test case.

At any stage, Admin can traverse back to Home page for


selection and viewing model of some other project.

Use Case ID

Use
name

Model Generation by Project Manager

Case

Summary

The Project Manager accountable for a project can generate


models for his project by choosing the method given below
METHOD 4: Model for Project.
The following options will be enabled.

SELECT MODEL: The Project Manager can choose


project for which he is accountable and generate model
for those project. Also he can be able to check status of
his/her project.

GENERATE MODEL: The Project Manager can generate


the model by clicking on model link on home page or
while he is analyzing the traceability matrix.
Preconditions

The Project Manager must be authorized and logged in.

Page 24 of 28

Success End
Condition

Green color Object is displayed to the Admin if a project is


completed.

Failed End
Condition

Red color object is displayed to the Admin when project is not


completed.

Primary,
Secondary
Actors

Project Manager.

Trigger

This use case is initiated when Project Manager clicks on Model


on the home page or he clicks on generate model in the
traceability matrix.

DESCRIPTION

Ste
p

Action

1
1a
1b

2
2a

The Project Manager clicks Model link to go to the


generation of project page
The Project Manager clicks the generate model button in
the traceability matrix

The Project manager chooses the project he is authorized


to view and clicks on Generate Button.
If he clicks on Generate Model, then follow step3.

The Project Manager can view the model for that project.
3
If he clicks on any Object in the model, then follow Step 4.

Page 25 of 28

If the Project Manager clicks on Project ID Object, then


display the whole model.
4a
4b

If the Project Manager clicks on Requirement ID Object,


then display that requirement, design and test cases for
that requirement.

4c

If the Project Manager clicks on Design ID Object, then


display design, test cases for that design component.

4d

If the Project Manager clicks on Test Case ID Object, then


display test case.

Project Manager can traverse back to Home page at any


time while viewing the model.

9. Non Functional Requirements


This section describes in detail all the non-functional requirements

9.1 Usability
9.1.1 The system shall allow the users to access the system from the
Internet.
9.1.2 online help will be available for the system
9.1.3 The end users will be able to able to adapt to the system with a
minimum training of 40 hours
9.1.4 Key board short cuts will be available for all functions of the system

9.2 Security
9.2.1 Login requirements 9.2.1.1
The testers and project managers will be provided access to the
system after they are registered into the database.
9.2.1.2
While logging in the system for the first time, the testers and
project managers will be provided an ID and a password.
9.2.1.3
On logging in, they can set a new password

9.2.2Password requirements
9.2.2.1
9.2.2.2

Password will be case-sensitive.


Password must have at least 6 characters,
Page 26 of 28

9.2.2.3
Password should be changed if the same password is already
taken by other user.

9.2.3 Inactivity timeouts


9.2.3.1
minutes.

System should timeout when there is no activity for 10

9.3 Performance
9.3.1 Response time
9.3.1.1
The response time will be less than 10 seconds for almost all the
processes performed in the system.

9.4 Capacity
9.4.1 Storage
9.4.1.1

Hard disk space


100 GB Content
50 GB Transaction Logs

9.5 Recovery
9.5.1 Recovery time scales
9.5.1.1

The system will be recovered within 12 hours from the down

time

9.5.2 Backup Frequencies


9.5.2.1
Details of all the processes carried out by the testers, project
manager will be stored in the back-up tapes.
9.5.2.2
All the back-up tapes will be provided to the Project Manager.
9.5.2.3
The back-up data will be updated every 10 days.

9.6 Availability
9.6.1 Hours of operation
9.6.1.1

The system will be available on all days 24*7

9.7 Reliability
9.7.1 Mean Time between Failures
9.7.1.1

The mean time between failures for the system will be 90days

Page 27 of 28

9.8 Maintainability
9.8.1 Mean Time to Recovery
9.8.1.1

The Mean Time To Recovery (MTTR) shall not exceed one day.

9.9 Portability
9.9.1 OS requirements
The system will run on windows XP / Vista / 7 / 8 / 8.1 / 10 and on MAC OS
and on LINUX.

9.9.2Browser requirements
The system will run on Internet Explorer, Internet Edge, Mozilla Firefox,
Google Chrome, Safari and UC browser.

9.10 Privacy
9.10.1 Reports cannot be accessed by end users who are not given access to
the reports
9.10.2No two users would be able to see their problems.
9.10.3Every problem registered by would have unique id.

Page 28 of 28