Professional Documents
Culture Documents
WHATLIESBENEATH???
An Overview of Claims relating to
Unforeseen Ground Conditions
NameJustin Wong |
By Justin Wong
Content of Presentation
Introduction
Foreseeable, Unforeseen and Unforeseeable Events
Ground Investigation (GI) Reports
Standard Forms of Contract
Common Law Position
Issues arising from adverse ground conditions
Recent Developments
Conclusion
Introduction
Justin Wong |
Introduction
Risk can be managed, minimized, shared,
transferred or acceptedit cannot be ignored
(Latham Report 1994)
Foreseeable,
Unforeseen and
Unforeseeable
Events
Justin Wong |
Justin Wong |
Justin Wong |
Justin Wong |
Ground Investigation(GI)
Reports
Justin Wong |
10
Justin Wong |
11
Two common
arguments raised by
contractors
12
Henry Boot
(The Contractor)
13
defined
Contract
Justin Wong |
14
Bacal
Construction
(The Contractor)
Bacal submitted the foundation design as part of its tender and formed part
of the contract documentation under an express provision in the contract.
Sand & Clay turns out to be rock (different soil type) which caused part of
the foundations to be re-designed where additional works were required.
Justin Wong |
15
Contractors Argument
Employers Argument
Held:
Held: Such
Such implied
implied term
term existed.
existed. There
There was
was aa collateral
collateral warranty
warranty that
that the
the ground
ground
conditions
conditions would
would be
be in
in accordance
accordance with
with the
the hypotheses
hypotheses upon
upon which
which the
the Contractor
Contractor had
had
been
been instructed
instructed to
to design
design the
the foundations.
foundations. Contractor
Contractor should
should be
be entitled
entitled to
to compensation.
compensation.
Justin Wong |
16
No Entitlement
Entitlement
Justin Wong |
17
CIS v Henry Boot Ltd and Others [2002] EWHC 1270 (TCC)
Whether SI reports constituted Employers Representation that the actual
groundwater levels were those contained in the report, in which the
Contractor could reasonably relied on?
Held:
A disclaimer stated that the SI report only provided an average band of
groundwater levels taken from the boreholes. The SI report did not contain
any statement sufficiently definite and unqualified to constitute a
representation of the actual groundwater level across the site.
Justin Wong |
18
Justin Wong |
19
Employers Misrepresentation
Howard Marine & Dredging Co. Ltd. v A. Ogden & Sons
(Excavations) Ltd. (1978) 2 All ER 1132 C.A.
Dumping of excavated clay at sea
using barges.
Plaintiffs manager told Defendant
that their barges could carry 1,600
tonnes (based on his memory of
the Lloyds Register), while he was
aware that the shipping documents
stated the correct figure as 1,055
tonnes.
Defendant hired the barges based
on Plaintiffs figure (1,600 tonnes).
Justin Wong |
20
Employers Misrepresentation
Howard Marine & Dredging Co. Ltd. v A. Ogden & Sons
(Excavations) Ltd. (1978) 2 All ER 1132 C.A. (Contd)
The Lloyds Register turned out to be
incorrect.
When the barges proved to be
insufficient for the job, Defendant
refused to pay the full price.
Plaintiff terminated the agreement and
sued for the outstanding payment.
Defendant made a counter-claim for
breach of collateral warranty and
negligent misrepresentation by the
Plaintiffs manager.
Justin Wong |
21
Employers Misrepresentation
Howard Marine & Dredging Co. Ltd. v A. Ogden & Sons
(Excavations) Ltd. (1978) 2 All ER 1132 C.A. (Contd)
Plaintiff argued that they had reasonable
grounds to believe in their false statement
because the Lloyds Register was the Bible.
CoA held: Plaintiff liable for breach of duty
under Sec. 2(1) Misrepresentation Act 1967.
Plaintiff had failed to prove that he had
reasonable grounds for belief in the truth of
the statement.
Reliance on the Lloyds Register was
insufficient when the correct figure was in
documentation in the Employers possession.
Justin Wong |
22
Employers Misrepresentation
Pearson and Son Ltd v Dublin Corporation (1907) AC 351
Engineer showed a wall
on the drawings going 9feet below ground, while
aware that it actually did
not go down to such
depth.
Engineer knew when
preparing the drawings
that if the tenderer
knows about the true
depth of the wall, the
tender price would be
substantially increased.
Dublin
Corporation
Foundation
of the wall
was much
shallower
Drawings
forwarded
to tenderers
Pearson
& Sons
Tender was won by P&S at a
lower price than they would
have offered if they knew the
Justin Wong |
true depth of the wall.
23
Employers Misrepresentation
Pearson and Son Ltd v Dublin Corporation (1907) AC 351(Contd)
Engineer relied on a clause which stated that the contractor should satisfy
Action for
Fraud
House of Lords held that such clause was no defence to the liability to the contractor
when the details in the drawings provided were in fact misrepresentation.
Justin Wong |
24
Justin Wong |
25
Justin Wong |
26
Justin Wong |
27
Justin Wong |
28
Justin Wong |
29
Justin Wong |
30
Justin Wong |
31
Existing Utility
Excusable
Risk
Risks associated
with underground
utilities
Proposed Utility
Utility shown on
Plans
NonExcusable
Risk
Actual Utility
Justin Wong |
32
Justin Wong |
33
Legally Impossible
Contractor has no legal rights to touch any utilities that were not part of the
works.
Justin Wong |
34
Justin Wong |
35
Relocation / diversion
work not performed
within a reasonable
period by the utility
undertaker
Cost
Contractor has to bear the financial
consequences of such non-performance.
Contractor cannot claim for expenditure
arising from disturbances to the works
caused by utility undertakers not engaged
by government under Clause 63(d)
Justin Wong |
36
Justin Wong |
37
Project involves the construction of a drainage pipe across the bed of a lake
underwater.
Borehole
Proposed
Pipe
Borehole
Borehole
LAKE
Sandy
Materials
Justin Wong |
38
Tender Price
Contractor B
Appreciates the risk,
no further investigation
works, makes some
allowance in his tender.
Contractor C
Contractor A
Risk Allowance
Justin Wong |
39
Tender Price
Contractor C
Experienced, diligent and
has
priced
the
work
required.
Contractor A
Lowest tenderer
Risk Allowance
Justin Wong |
40
Increasing tender
prices to allow
for the risks
Justin Wong |
41
Justin Wong |
42
Tender Price
Contractors A as thinly
financed, low asset contractor
who has little to lose
Risk Allowance
Justin Wong |
43
Justin Wong |
44
MTRC Form
The most equitable form of contract currently
used in Hong Kong, which reflect the
international opinion on the risk allocation for
ground conditions and obstructions.
Nature of works usually undertaken under
these forms (e.g. tunneling and underground
structures).
MTRC Form
Notice of Physical Conditions / Artificial
Cl. 38.1
Obstructions
Engineers Response to Contractors
Cl. 38.2
Notice
Engineers Decision to Contractors
claim on Additional Time and/or
Payment
Justin Wong |
45
Justin Wong |
46
Justin Wong |
47
Justin Wong |
48
Clause 13.2:
The Contractor shall be deemed prior to the date of the
Letter of Acceptance to have allowed a correct and
sufficient Tender Total and rates and prices included in the
Pricing Document to cover all his obligations
Justin Wong |
49
50
Clause 13.4
Notice of Physical
Conditions /
Artificial
Obstructions
Clause 13.5
PMs response
to the Cl.13.4
Notice
Justin Wong |
51
Justin Wong |
52
ICE Clause 12
Justin Wong |
53
Justin Wong |
54
Sheet Pile
Material
Retained
55
Justin Wong |
56
Clause 4.11
Interpretation of
data
Accuracy of data
Clause 4.12
Physical Conditions
Justin Wong |
57
Justin Wong |
58
Contractor is deemed to have inspected and examined the site only to the
extent as far as practicable, with cost and time considerations.
Justin Wong |
59
Justin Wong |
60
Employer carries the risk of physical conditions that could have been
unforeseeable by an experienced contractor at the date of tender.
FIDIC Clause 4.12 follows the well established Clause 12 of the ICE
Form
Justin Wong |
61
Clause 4.10
Clause 4.12
Verification &
Interpretation of
Data
Justin Wong |
62
Justin Wong |
63
Justin Wong |
64
Silver Book
Interpretation of Data
Contractor
Contractor
Warranty of accuracy of
information provided
Employer
Contractor
Employer
Contractor
Responsibility on
unforeseen physical
conditions
Justin Wong |
65
Both forms do not contain any provisions for unforeseen ground conditions.
Justin Wong |
66
(Clause 4.12)
(Clause 4.12)
(Clause 13.4)
Justin Wong |
67
Justin Wong |
68
No implied warranty on
the
accuracy
of
information provided by
employer, except when
the employer specifically
makes
a
misrepresentation.
Justin Wong |
69
Demolition
of
existing
Blackfriars
Employer
issued
variation
and
Justin Wong |
70
Justin Wong |
71
Justin Wong |
72
Contractor
claims
for
extra
payment beyond the lump sum
price in the tender.
Held: Contractor was not entitled to any extra payment in respect of this work.
Justin Wong |
73
Justin Wong |
74
Neither
employer
nor
contractor
had
Justin Wong |
75
Held:
Contractor shall carry out their own GI works in order to satisfy himself as to the
practicality of executing the works (including overcoming adverse ground conditions),
regardless of what information was in the employers possession.
Justin Wong |
76
Justin Wong |
77
Justin Wong |
78
Justin Wong |
79
Artificial obstruction:
running sand
uncharted utilities
Water / groundwater
Justin Wong |
80
WORKS
Construction of three mooring
dolphins and re-construction of a
damaged bathing dolphin.
INCIDENT
The jack-up barge used by the
Defendant collapsed when the
crane was slewing with a large
concrete soffit.
Justin Wong |
81
barge
have
an
ARBITRATOR
There must have been an unusual
combination of soil strength and
applied stresses at the base of the
barges legs, which constitute an
unforeseeable physical condition.
Applied stress on the barge caused a different behaviour of the ground and
substantial increase in settlement, resulted in the collapse of the barge.
Although the sub-soil type encountered was foreseen but its performance under
the applied stress of the barge was not. Such adverse physical condition could
not have been foreseen by an experienced contractor.
Contractors claim under ICE Clause 12 succeeded. The Court later upheld the
Arbitrators decision upon Employers appeal.
Justin Wong |
82
(2) Foreseeability
determining whether a condition could reasonably have been
foreseen habitually gives rise to the greatest difficulty of
interpretation in a civil engineering arbitration
Keating on Building Contract, 7th Edition, Page 991
Justin Wong |
83
(2) Foreseeability
Is a claim excluded only if an experienced contractor could have
foreseen that the conditions or obstructions must occur, or is it sufficient
that there was a possibility, however remote, that the conditions might
occur?...
It is suggested that a claim is barred only if an experienced contractor
could have foreseen a substantial risk.
(Abrahamsons Engineering Law and the I.C.E. Contracts, 4th Edition)
Justin Wong |
84
Factors
determining
whether a
risk was
substantial
85
Justin Wong |
86
Experienced
Contractor
Case 1
No
No
Case 2
No
Yes
Case 3
Yes
No
Success
of Claim
the assessment of what could or could not have been foreseen must
take into account all available sources of information, including the
actual knowledge of the real Contractor, even if this goes beyond what
an experienced contractor would know
(Keating on Building Contract, 7th Edition, Page 991)
Justin Wong |
87
Recent Developments
Justin Wong |
88
Recent Developments
MTRC
Formal Risk Management Plan
Pre-award Joint Development of Target Cost Bids
Geotechnical Baseline Reports
HKSAR Government
ETWB Technical Circular No. 17/2004
Utility Management System (UMS)
Justin Wong |
89
Even if we provide the tenderers with all the data that MTR has obtained pretender, I suggest we probably still have a better understanding of the risks at the
time of tender award than the contractor under our normal procurement process,
having had much longer to study the challenges
This is in line with the international practice where allocation of risk of unforeseen
conditions is either shared or borne by the Employer.
Justin Wong |
90
Justin Wong |
91
Justin Wong |
92
Allocation of
Contractual
Risk
Safety
Construction
Management
Methodology
Additional
Design
Investigation Development
93
Governments interest to
reduce these risks or to
minimize the overall cost
of the risks wherever
practicable.
Justin Wong |
94
Investigation / Search
after occupation
of works site
Re-measurement
Approach for
Underground Works
Justin Wong |
95
Contractor will only be compensated for delays but not Cost under GCC
Cl.63 or under any other provisions.
Justin Wong |
96
developed
(IIUMS) commissioned
Oct 1997
Sep 2002
Development of Excavation
Permit Management
System (XPMS)
Late 2006
Justin Wong |
97
Conclusion
Justin Wong |
98
Conclusion
Risk <
Contingency
If all risks
for
unforeseen
conditions
are placed
solely on
contractor
Contractor may
include a
contingency to
deal with the
conditions that
may arise
Employer will
have to pay for
such nonoccurring risk
In both events,
Employer
suffers
ultimately
Risk >
Contingency
Contractor will
be forced to
make claims to
recover the loss
or go out of
business
Justin Wong |
99
Upgrade / update
utilities records by
latest technology
Pre-contract clearing of
utilities to avoid
repeated road openings
Pre-tender
investigation for
utilities of particular
complex or
uncertain nature
Subsequent change to
the tender should
constitute a variation
100
Employers statements in
GI reports sufficiently
explicit and precise?
(Misrepresentation)
GI documentations
expressly incorporated
as part of the Contract
101
THANK YOU!!!!
Justin Wong |
102