Cathodic Protection System Upgrading Project Phase 3 (Level 5)

Activity ID
Activity Name

CPP-1 Cathodic Protection System

Original Remaining Start


Duration Duration

2 Week Lookahead
Qtr 3, 2015

Finish
Jun

Jul

Aug

Qtr 4, 2015

Sep

Oct

Nov

Jan

Feb

Mar

367

367

20-Aug-15
20-Aug-15*

21-Aug-16

CONTRACT EFECTIVE DATE

ENGINEERNIG COMPLETION

25-Aug-15

ENGINEERNIG COMPLETION

MS1020

PROCURMENT COMPLETION

25-Aug-15

PROCURMENT COMPLETION

MS1030

COMPLETION OF HIGLEIG AREA

30-Jun-16

MS1040

COMPLETION OF BAMBO AREA

05-Jul-16

MS1050

COMPLETION OF NEEM AREA

28-Jul-16

MS1060

COMPLETION OF BAMBOO-HEGLIG PIPELINE


0

30-Apr-16*

MS1070

MECHANICAL COMPLETION

03-Aug-16

MS1080

PROVISIONAL ACCEPTANCE

21-Aug-16*

61

18-Jul-15 A

23

25-Aug-15 A 16-Sep-15 A

23

25-Aug-15 A 16-Sep-15 A

14

18-Jul-15 A

25-Aug-15

CPP-1.3.1 SITE VISIT


SITE VISIT

CPP-1.3.2 HIGLEIG FIELD ENGINEERING

COMPLETION OF BAMBOO-HEGLIG PIPELINE


MECHANICAL C
PROVIS

16-Sep-15

16-Sep-15, CPP-1.3 ENGINEERING


16-Sep-15 A, CPP-1.3.1 SITE VISIT
SITE VISIT
25-Aug-15, CPP-1.3.2 HIGLEIG FIELD ENGINEERING

18-Jul-15 A

18-Jul-15 A

Calculation for CP system HF

19-Jul-15 A

19-Jul-15 A

installation dwg for test post HF

A1030

structure dwg for test ost and HF

20-Jul-15 A

20-Jul-15 A

structure dwg for test ost and HF

A1040

drawing for anti corrosion spotwelding

21-Jul-15 A

22-Jul-15 A

drawing for anti corrosion spotwelding

A1050

installation drawing for anode bearing

23-Jul-15 A

23-Jul-15 A

installation drawing for anode bearing

A1060

installation drawing for AJB HF

24-Jul-15 A

24-Jul-15 A

installation drawing for AJB HF

A1070

drawing for cable installation HF

25-Jul-15 A

25-Jul-15 A

drawing for cable installation HF

A1080

istallation drawing for TR HF

26-Jul-15 A

26-Jul-15 A

istallation drawing for TR HF

A1090

drawing for cable to pipe line connection 1

27-Jul-15 A

27-Jul-15 A

drawing for cable to pipe line connection

A1100

specification of CP system HF

28-Jul-15 A

28-Jul-15 A

specification of CP system HF

A1110

data sheet for test post HF

20-Jul-15 A

20-Jul-15 A

data sheet for test post HF

A1120

data sheet for anode HF

24-Jul-15 A

24-Jul-15 A

data sheet for anode HF

A1130

data sheet for AJB HF

25-Jul-15 A

25-Jul-15 A

data sheet for AJB HF

A1140

data sheet for refrence elctrode

28-Jul-15 A

25-Aug-15

A1150

data sheet for T/R HF

29-Jul-15 A

30-Jul-15 A

data sheet for T/R HF

A1160

MR material requesition form

31-Jul-15 A

MR material requesition form

31-Jul-15 A

14

01-Aug-15 A 14-Aug-15 A

data sheet for refrence elctrode

14-Aug-15 A, CPP-1.3.3 BAMBO FIELD ENGINEERING

AEB1100

Calculation for CP system HF

01-Aug-15 A 01-Aug-15 A

Calculation for CP system HF

AEB1110

installation dwg for test post HF

02-Aug-15 A 02-Aug-15 A

installation dwg for test post HF

AEB1120

structure dwg for test ost and HF

03-Aug-15 A 03-Aug-15 A

structure dwg for test ost and HF

AEB1130

drawing for anti corrosion spotwelding

04-Aug-15 A 05-Aug-15 A

drawing for anti corrosion spotwelding

AEB1140

installation drawing for anode bearing

06-Aug-15 A 06-Aug-15 A

installation drawing for anode bearing

AEB1150

installation drawing for AJB HF

07-Aug-15 A 07-Aug-15 A

installation drawing for AJB HF

AEB1160

drawing for cable installation HF

08-Aug-15 A 08-Aug-15 A

drawing for cable installation HF

AEB1170

istallation drawing for TR HF

09-Aug-15 A 09-Aug-15 A

istallation drawing for TR HF

AEB1180

drawing for cable to pipe line connection 1

10-Aug-15 A 10-Aug-15 A

drawing for cable to pipe line connection

AEB1190

specification of CP system HF

11-Aug-15 A 12-Aug-15 A

AEB1200

data sheet for test post HF

13-Aug-15 A 13-Aug-15 A

AEB1210

data sheet for anode HF

07-Aug-15 A 07-Aug-15 A

data sheet for anode HF

AEB1220

data sheet for AJB HF

08-Aug-15 A 08-Aug-15 A

data sheet for AJB HF

AEB1230

data sheet for refrence elctrode

09-Aug-15 A 09-Aug-15 A

data sheet for refrence elctrode

AEB1240

data sheet for T/R HF

10-Aug-15 A 11-Aug-15 A

AEB1250

MR material requesition form

14-Aug-15 A 14-Aug-15 A

12

15-Aug-15 A 26-Aug-15 A

15-Aug-15 A 15-Aug-15 A

Critical Remaining Work

Remaining Work

Milestone

Summary

Sep

COMPLETION OF

installation dwg for test post HF

Actual Work

Aug

COMPLETION OF BAMBO AREA

Calculation for CP system HF

Calculation for CP system HF

Jul

COMPLETION OF HIGLEIG AREA

A1020

CPP-1.3.4 NEEM FIELD ENGINEERING

Jun

CONTRACT EFECTIVE DATE

A1010

CPP-1.3.3 BAMBO FIELD ENGINEERING

May

21-Aug-1

MS1010

CPP-1.3 ENGINEERING

Apr

21-Aug-1

MS1000

AEN1100

Dec

05-May-16 16:02
Qtr 3, 2016

Qtr 2, 2016

367
18-Jul-15
A 21-Aug-16
Upgrading400
Project
Phase
3 (Level
5)

CPP-1.6 MILSTONE

A1000

Qtr 1, 2016

specification of CP system HF
data sheet for test post HF

data sheet for T/R HF


MR material requesition form
26-Aug-15 A, CPP-1.3.4 NEEM FIELD ENGINEERING
Calculation for CP system HF
Page 1 of 4

TASK filter: All Activities

Primavera Systems, Inc.

Cathodic Protection System Upgrading Project Phase 3 (Level 5)


Activity ID
Activity Name

Original Remaining Start


Duration Duration

2 Week Lookahead
Qtr 3, 2015

Finish
Jun

Jul

Aug

Sep

Qtr 4, 2015
Oct

Nov

AEN1110

installation dwg for test post HF

16-Aug-15 A 16-Aug-15 A

installation dwg for test post HF

AEN1120

structure dwg for test ost and HF

17-Aug-15 A 17-Aug-15 A

structure dwg for test ost and HF

AEN1130

drawing for anti corrosion spotwelding

18-Aug-15 A 18-Aug-15 A

drawing for anti corrosion spotwelding

AEN1140

installation drawing for anode bearing

19-Aug-15 A 19-Aug-15 A

installation drawing for anode bearing

AEN1150

installation drawing for AJB HF

20-Aug-15 A 20-Aug-15 A

installation drawing for AJB HF

AEN1160

drawing for cable installation HF

21-Aug-15 A 21-Aug-15 A

drawing for cable installation HF

AEN1170

istallation drawing for TR HF

22-Aug-15 A 22-Aug-15 A

istallation drawing for TR HF

AEN1180

drawing for cable to pipe line connection 1

23-Aug-15 A 23-Aug-15 A

drawing for cable to pipe line connection

AEN1190

specification of CP system HF

24-Aug-15 A 25-Aug-15 A

AEN1200

data sheet for test post HF

18-Aug-15 A 18-Aug-15 A

data sheet for test post HF

AEN1210

data sheet for anode HF

20-Aug-15 A 20-Aug-15 A

data sheet for anode HF

AEN1220

data sheet for AJB HF

21-Aug-15 A 21-Aug-15 A

data sheet for AJB HF

AEN1230

data sheet for refrence elctrode

22-Aug-15 A 22-Aug-15 A

data sheet for refrence elctrode

AEN1240

data sheet for T/R HF

25-Aug-15 A 26-Aug-15 A

data sheet for T/R HF

AEN1250

MR material requesition form

26-Aug-15 A 26-Aug-15 A

MR material requesition form

171

194

08-Oct-15 A

26-Mar-16

150

194

08-Oct-15 A

05-Mar-16

08-Oct-15 A

12-Oct-15 A

CPP-1.4 PROCURMENT
CPP-1.4.1 ANODE
P1000

issue RFQ

P1010

issue PO

21-Oct-15 A

25-Oct-15 A

P1020

manufacturing

56

26-Oct-15 A

20-Dec-15 A

P1030

delivery to port

46

02-Jan-16 A

16-Feb-16 A

P1040

costum clerance

21-Feb-16 A 02-Sep-15

P1050

delivery to site

29-Feb-16*

05-Mar-16

150

194

08-Oct-15 A

05-Mar-16

08-Oct-15 A

12-Oct-15 A

CPP-1.4.2 TEST POST


P2000

issue RFQ

P2010

issue PO

21-Oct-15 A

26-Oct-15 A

P2020

manufacturing

56

26-Oct-15 A

20-Dec-15 A

P2030

delivery to port

46

02-Jan-16 A

16-Feb-16 A

P2040

costum clerance

21-Feb-16 A 02-Sep-15

P2050

delivery to site

CPP-1.4.3 JUNCTION BOX

29-Feb-16*

05-Mar-16

171

08-Oct-15 A

26-Mar-16 A

Qtr 1, 2016
Dec

Jan

Feb

Mar

Apr

manufacturing
delivery to port
delivery to site
05-Mar-16, CPP-1.4.2 TEST POST
issue RFQ
issue PO
manufacturing
delivery to port
delivery to site
26-Mar-16 A, CPP-1.4.3 JUNCTION BOX

12-Oct-15 A

P3010

issue PO

22-Oct-15 A

26-Oct-15 A

P3020

manufacturing

87

26-Oct-15 A

20-Jan-16 A

P3030

delivery to port

36

06-Feb-16 A 06-Feb-16 A

P3040

costum clerance

13-Mar-16 A 20-Mar-16 A

costum clerance

P3050

delivery to site

21-Mar-16 A 26-Mar-16 A

delivery to site

150

08-Oct-15 A

05-Mar-16 A

08-Oct-15 A

12-Oct-15 A

issue PO

22-Oct-15 A

26-Oct-15 A

manufacturing

56

26-Oct-15 A

20-Dec-15 A

P4030

delivery to port

46

02-Jan-16 A

16-Feb-16 A

P4040

costum clerance

21-Feb-16 A 21-Feb-16 A

P4050

delivery to site

29-Feb-16 A 05-Mar-16 A

171

08-Oct-15 A

26-Mar-16 A

CPP-1.4.5 TRANSFORMER
P5000

issue RFQ

08-Oct-15 A

12-Oct-15 A

P5010

issue PO

22-Oct-15 A

26-Oct-15 A

P5020

manufacturing

87

26-Oct-15 A

20-Jan-16 A

P5030

delivery to port

35

06-Feb-16 A 06-Feb-16 A

P5040

costum clerance

13-Mar-16 A 21-Mar-16 A

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Sep

issue PO

08-Oct-15 A

P4020

Aug

05-Mar-16, CPP-1.4.1 ANODE

P4010

Jul

issue RFQ

issue RFQ

Jun

26-Mar-16, CPP-1.4 PROCURMENT

issue RFQ

P4000

May

specification of CP system HF

P3000

CPP-1.4.4 REFERENCE ELECTRODES

05-May-16 16:02
Qtr 3, 2016

Qtr 2, 2016

issue RFQ
issue PO
manufacturing
delivery to port

05-Mar-16 A, CPP-1.4.4 REFERENCE ELECTRODES


issue RFQ
issue PO
manufacturing
delivery to port
costum clerance
delivery to site
26-Mar-16 A, CPP-1.4.5 TRANSFORMER
issue RFQ
issue PO
manufacturing
delivery to port
costum clerance

Page 2 of 4

TASK filter: All Activities

Primavera Systems, Inc.

Cathodic Protection System Upgrading Project Phase 3 (Level 5)


Activity ID
Activity Name
P5050

delivery to site

CPP-1.4.6 CABELS

Original Remaining Start


Duration Duration

2 Week Lookahead
Qtr 3, 2015

Finish
Jun

21-Mar-16 A 26-Mar-16 A

149

08-Oct-15 A

05-Mar-16 A

08-Oct-15 A

12-Oct-15 A

Jul

Aug

Sep

Qtr 4, 2015
Oct

Nov

Qtr 1, 2016
Dec

Jan

Feb

Mar

Apr

P6010

issue PO

22-Oct-15 A

26-Oct-15 A

P6020

manufacturing

56

26-Oct-15 A

20-Dec-15 A

P6030

delivery to port

46

02-Jan-16 A

16-Feb-16 A

P6040

costum clerance

21-Feb-16 A 29-Feb-16 A

costum clerance

P6050

delivery to site

29-Feb-16 A 05-Mar-16 A

delivery to site

0
194

08-Oct-15 A

05-Mar-16

P7000

issue RFQ

08-Oct-15 A

12-Oct-15 A

P7010

issue PO

22-Oct-15 A

27-Oct-15 A

P7020

manufacturing

56

26-Oct-15 A

20-Dec-15 A

P7030

delivery to port

46

02-Jan-16 A

16-Feb-16 A

P7040

costum clerance

21-Feb-16 A 02-Sep-15

P7050

delivery to site

29-Feb-16*

166

118

CPP-1.5 CONSTRUCTION

37
CPP-1.5.1 MANPOWER & EQUIPMENT MOBLIZATION
C1000

manpower & equipment moblization

CPP-1.5.2 HIGLIG FIELD CONSTRUCTION


CPP-1.5.2.2 Installation Anode Junction Box
C2040
Installation AJB
C2050

Connection the Anode Cable to AJB

CPP-1.5.2.3 Installation Negative Cable


C2060
Excavation the Cable Trench

Jun

Jul

Aug

Sep

05-Mar-16 A, CPP-1.4.6 CABELS

issue RFQ

150

May

delivery to site

P6000

CPP-1.4.7 BULK MATERIALS

05-May-16 16:02
Qtr 3, 2016

Qtr 2, 2016

issue RFQ
issue PO
manufacturing
delivery to port

05-Mar-16, CPP-1.4.7 BULK MATERIALS


issue RFQ
issue PO
manufacturing
delivery to port

05-Mar-16

delivery to site

14-Feb-16 A 28-Jul-16

28-Jul-16, CPP-1.5

14-Feb-16 A 22-Mar-16 A

22-Mar-16 A, CPP-1.5.1 MANPOWER & EQUIPMENT MOBLIZATION

37

14-Feb-16 A 22-Mar-16 A

manpower & equipment moblization

129

52

23-Feb-16 A 30-Jun-16

26
25

0
0

01-May-16 A 26-May-16 A
01-May-16 A 25-May-16 A

26-May-16 A, CPP-1.5.2.2 Installation Anode


Installation AJB

26

01-May-16 A 26-May-16 A

Connection the Anode Cable to AJB

67
43

0
0

23-Feb-16 A 30-Apr-16 A
23-Feb-16 A 06-Apr-16 A

30-Jun-16, CPP-1.5.2 HIGLIG

30-Apr-16 A, CPP-1.5.2.3 Installation Negative Cable


Excavation the Cable Trench

C2070

Laying the Cable

24

12-Mar-16 A 04-Apr-16 A

C2080

Backfilling

24

07-Apr-16 A

18
18

0
0

30-Mar-16 A 16-Apr-16 A
30-Mar-16 A 16-Apr-16 A

16-Apr-16 A, CPP-1.5.2.4 Installation Negative Junction Box


Installation NJB

18

30-Mar-16 A 16-Apr-16 A

Connection the Anode Cable to NJB

25
25

25
25

10-May-16
10-May-16*

03-Jun-16
03-Jun-16

25

25

10-May-16*

03-Jun-16

43
42

0
0

23-Feb-16 A 05-Apr-16 A
23-Feb-16 A 04-Apr-16 A

05-Apr-16 A, CPP-1.5.2.1 Installation Anode


Excavation the Anode bed

CPP-1.5.2.4 Installation Negative Junction Box


C2090
Installation NJB
C2100

Connection the Anode Cable to NJB

CPP-1.5.2.5 Installation T/R


C2110
Installation T/R
C2120

Connection the Cable to T/R

CPP-1.5.2.1 Installation Anode


C2010
Excavation the Anode bed

Laying the Cable

30-Apr-16 A

Backfilling

03-Jun-16, CPP-1.5.2.5 Installation T/R


Installation T/R
Connection the Cable to T/R

C2020

Laying the anode

24

12-Mar-16 A 05-Apr-16 A

Laying the anode

C2030

Backfilling Anode bed

24

12-Mar-16 A 05-Apr-16 A

Backfilling Anode bed

27
27

27
27

04-Jun-16
04-Jun-16*

30-Jun-16
30-Jun-16

95

95

02-Apr-16 A

05-Jul-16

26
24

0
0

08-Apr-16 A
08-Apr-16 A

04-May-16 A
02-May-16 A

24

10-Apr-16 A

04-May-16 A

26
22

0
0

06-Apr-16 A
06-Apr-16 A

01-May-16 A
27-Apr-16 A

08-Apr-16 A

01-May-16 A

CPP-1.5.2.6 Pre-Commissioning
C2130
Pre-Commissioning

CPP-1.5.3 BAMBO FIELD CONSTRUCTION


CPP-1.5.3.2 Installation Anode Junction Box
C3040
Installation AJB
C3050

Connection the Anode Cable to AJB

CPP-1.5.3.3 Installation Negative Cable


C3060
Excavation the Cable Trench
C3070

Laying the Cable

24

C3080

Backfilling

22

08-Apr-16 A

29-Apr-16 A

57
25

57
25

11-Apr-16
11-Apr-16*

06-Jun-16
05-May-16

32

32

06-May-16*

06-Jun-16

36
35

36
35

16-May-16
16-May-16*

20-Jun-16
20-Jun-16

CPP-1.5.3.4 Installation Negative Junction Box


C3090
Installation NJB
C3100

Connection the Anode Cable to NJB

CPP-1.5.3.5 Installation T/R


C3110
Installation T/R

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

30-Jun-16, CPP-1.5.2.6 Pre-C


Pre-Commissioning
05-Jul-16, CPP-1.5.3 BAMB
04-May-16 A, CPP-1.5.3.2 Installation Anode Junction Box
Installation AJB
Connection the Anode Cable to AJB
01-May-16 A, CPP-1.5.3.3 Installation Negative Cable
Excavation the Cable Trench
Laying the Cable
Backfilling
06-Jun-16, CPP-1.5.3.4 Installation Neg
Installation NJB
Connection the Anode Cable to NJB
20-Jun-16, CPP-1.5.3.5 Installation T/R
Installation T/R

Page 3 of 4

TASK filter: All Activities

Primavera Systems, Inc.

Cathodic Protection System Upgrading Project Phase 3 (Level 5)


Activity ID
Activity Name
C3120

Connection the Cable to T/R

CPP-1.5.3.1 Installation Anode


C3010
Excavation the Anode bed

Original Remaining Start


Duration Duration

2 Week Lookahead
Qtr 3, 2015

Finish
Jun

Jul

Aug

Sep

Qtr 4, 2015
Oct

Nov

Qtr 1, 2016
Dec

Jan

Feb

05-May-16 16:02
Qtr 3, 2016

Qtr 2, 2016
Mar

Apr

May

Jun

Jul

Aug

31

31

21-May-16*

20-Jun-16

26
24

26
24

02-Apr-16
02-Apr-16*

28-Apr-16
26-Apr-16

28-Apr-16, CPP-1.5.3.1 Installation Anode


Excavation the Anode bed

Sep

Connection the Cable to T/R

C3020

Laying the anode

24

24

03-Apr-16*

27-Apr-16

Laying the anode

C3030

Backfilling Anode bed

24

24

04-Apr-16*

28-Apr-16

Backfilling Anode bed

15
15

15
15

21-Jun-16
21-Jun-16*

05-Jul-16
05-Jul-16

70

70

20-May-16

28-Jul-16

36
36

36
36

20-May-16
20-May-16*

24-Jun-16
24-Jun-16

24-Jun-16, CPP-1.5.4.2 Installat


Installation AJB

35

35

20-May-16*

23-Jun-16

Connection the Anode Cable to AJB

25
25

25
25

24-Jun-16
24-Jun-16*

18-Jul-16
18-Jul-16

CPP-1.5.3.6 Pre-Commissioning
C3130
Pre-Commissioning

CPP-1.5.4 NEEM FIELD CONSTRUCTION


CPP-1.5.4.2 Installation Anode Junction Box
C4040
Installation AJB
C4050

Connection the Anode Cable to AJB

CPP-1.5.4.3 Installation Negative Cable


C4060
Excavation the Cable Trench

05-Jul-16, CPP-1.5.3.6 PrePre-Commissioning


28-Jul-16, CPP-1.5

18-Jul-16, CPP-1.5.4.3
Excavation the Cable Trench

C4070

Laying the Cable

24

24

24-Jun-16*

17-Jul-16

Laying the Cable

C4080

Backfilling

23

23

24-Jun-16*

16-Jul-16

Backfilling

45
25

45
25

25-May-16
25-May-16*

08-Jul-16
18-Jun-16

24

24

15-Jun-16*

08-Jul-16

30
30

30
30

27-May-16
27-May-16*

25-Jun-16
25-Jun-16

25

25

30-May-16*

23-Jun-16

52
40

52
40

28-May-16
28-May-16*

18-Jul-16
06-Jul-16

CPP-1.5.4.4 Installation Negative Junction Box


C4090
Installation NJB
C4100

Connection the Anode Cable to NJB

CPP-1.5.4.5 Installation T/R


C4110
Installation T/R
C4120

Connection the Cable to T/R

CPP-1.5.4.1 Installation Anode


C4010
Drilling the Anode Deep Well Bed

08-Jul-16, CPP-1.5.4.4 Ins


Installation NJB
Connection the Anode Cable to NJB
25-Jun-16, CPP-1.5.4.5 Installation T/R
Installation T/R
Connection the Cable to T/R
18-Jul-16, CPP-1.5.4.1
Drilling the Anode Deep Well Bed

C4020

Laying the anode

40

40

09-Jun-16*

18-Jul-16

Laying the anode

C4030

Backfilling Anode bed

35

35

09-Jun-16*

14-Jul-16

Backfilling Anode bed

CPP-1.5.4.6 Pre-Commissioning
C4130
Pre-Commissioning

13
13

13
13

16-Jul-16
16-Jul-16*

28-Jul-16
28-Jul-16

CPP-1.5.5 Bamboo-Heglig Pipeline

12

12

18-Apr-16

29-Apr-16

10
10

10
10

18-Apr-16
18-Apr-16*

28-Apr-16
27-Apr-16

28-Apr-16, CPP-1.5.5.1 Installation Test Post


Installation Test Post

Connection the Anode Cable to Test Post10

10

18-Apr-16*

28-Apr-16

Connection the Anode Cable to Test Post

10
10

10
10

18-Apr-16
18-Apr-16*

28-Apr-16
28-Apr-16

28-Apr-16, CPP-1.5.5.2 Installation Reference Electrode


Installation Reference Electrode

Connection the Anode Cable to Test Post10

10

18-Apr-16*

28-Apr-16

Connection the Anode Cable to Test Post

2
2

2
2

28-Apr-16
28-Apr-16*

29-Apr-16
29-Apr-16

29-Apr-16, CPP-1.5.5.3 Pre-Commissioning


Pre-Commissioning

28

28

07-Jul-16

03-Aug-16

CPP-1.5.5.1 Installation Test Post


C5010
Installation Test Post
C5020

CPP-1.5.5.2 Installation Reference Electrode


C5030
Installation Reference Electrode
C5040

CPP-1.5.5.3 Pre-Commissioning
C5050
Pre-Commissioning

CPP-1.1 COMMISSIONING
CM1000

commissioning for Higleig Field

14

14

07-Jul-16*

21-Jul-16

CM2000

commissioning for Bambo Field

10

10

15-Jul-16*

24-Jul-16

CM3000

commissioning for Neem Field

10

10

24-Jul-16*

03-Aug-16

CM4000

commissioning for Bamboo-Heglig Pipeline


8

22-Jul-16*

29-Jul-16

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

28-Jul-16, CPP-1.5
Pre-Commissioning
29-Apr-16, CPP-1.5.5 Bamboo-Heglig Pipeline

03-Aug-16, CPP
commissioning for Higleig Field
commissioning for Bambo Field
commissioning fo
commissioning for

Page 4 of 4