Snag List Project Certification Department

Project Name

T.No: 140/2013 3x 20MVA Al Batha Primary substation project


at Batina Governorate

Contractor

M/s Eastern Overseas

Site Visit Date based on


Compliance submission

16/12/2015

Attended MZEC Engineers

Mr.S.Idhayathullah

MZEC Project Manager


Contractor Attended DCRP
Approved Testing &
Commissioning Engineer
Project Manager

Mr. Merlin

Snag List Issued date

23-12-2015

Mr. Dinesh
Mr.Karthik

Continue from previous snag list number


SL.N
o
1

Snag Points

Date of
Completio
n

Ferrule shall be provided for CT star Point before


primary injection test
TB group marker shall be provided for respective
place

Witness
name &
signature
MZEC

Priority
Class ref
Note (**)
A

No ferrule provided for CT star


point wires
One common TB group
marker is used for two row
TBs

11KV switchgear foundation bolts shall be tighten

11KV switchgear shall be cleaned

Page 1 of 3 Tender no. 140/2013 Al Batha S/S snag list#1

Remarks

Gland earthing to be done for control cable gland in

11kV switchgear wherever required


Testing facility shall be provided for 11KV CT&VT

circuit
CT&VT TB shall be separated

Presently both TBs fixed in


same row without segregation
Presently all cores arranged in

CT TB shall be separated based in cores

common row without


segregation

In 11KV station T/F actual CT ratio is 100-200/1A


9

where as mentioned in tender 50-100/1A to be

clarified
10

11

12

13

Rubber mat shall be provided 11KV

In 11KV I/C & B/S sych.selector switch obstruct CB

closing suitable switch shall be provided


BUS-A VT Y-phase core interchanged to be rectified

with suitable ferrule


11KV VT FAT to be provided

Remaining/pending tests

Sl No

Description

Page 2 of 3 Tender no. 140/2013 Al Batha S/S snag list#1

Date of
Completio
n

Witness
name &
signature
MZEC

Priority
Class ref
Note (**)

Remarks

Note;**

A - Point need completion prior to Energization


B - Points need completion (not connected with Energization) Action Plan for its completion should be provided after
issuance of snag points undertaking of the same should be provided for its completion.
C - Discussion, Clarification and action - remaining scope work.
Prepared By
Salim Khalfan Al Mayahi
Commissioning Engineer

Head of certification Dept. (MZEC)

S.Idhayathullah
Received By: Name & Signature

Page 3 of 3 Tender no. 140/2013 Al Batha S/S snag list#1

Project Engineer MZEC