Billing 2 (Arknet) - 3 - 25 - 14
Billing 2 (Arknet) - 3 - 25 - 14
PROJECT
COMPANY
BILLING NO.
:
:
:
:
:
CERTIFICATE OF BILLING
March 25, 2014
SHORE RESIDENCES
PILE DRIVING WORKS
Sta. Elena Construction and Development Corporation
Billing No. 2
PHP
265,642,492.00
2.
PHP
265,642,492.00
2.2 LESS
2.2.1 Recoupment of Downpayment
2.2.2 Retention - 10 %
2.2.3 Billing No. 1
30.80%
PHP
PHP
PHP
16,364,899.00
8,182,449.50
38,722,388.06
PHP
PHP
PHP
53,128,498.40
38,722,388.06
18,554,758.44
4.
5.
6.
___________________________
NOEL T. PEREDO
Senior Project Engineering Manager
____________________________
CHRISTIAN CARLO L. ROXAS
Engineering Division Head
LLING
pment Corporation
SMDC to SECDC
FOUR THOUSAND SEVEN
265,642,492.00
PHP
###
265,642,492.00
265,642,492.00
30.80%
81,824,495.00
PHP
81,824,495.00
PHP
63,269,736.56
PHP
18,554,758.44
16,364,899.00
8,182,449.50
38,722,388.06
53,128,498.40
38,722,388.06
18,554,758.44
PHP
110,405,644.90
PHP
155,236,847.10
Recommending Approval
________________________
ADELAIDA E. COBRES
Project Director