Professional Documents
Culture Documents
Formulas para La Administracion de Proyectos - May2014
Formulas para La Administracion de Proyectos - May2014
OPTRAN
IT Management and Governance
BAC (presupuesto)
100.00
Planed value
$100.00
BAC
Earned Value
$100.00
BAC
$50.00
EV
Schedule Variance
SV
$50.00
EV
$50.00
EV
Cost variance
CV
Forecast of most likely total project costs based on projects performance
Earned at completion
EAC=AC +(bottom-up ETC)
$50.00
EV
$80.00
AC
Earned at completion
EAC= AC+BAC-EV
$80.00
AC
$100.00
BAC
Earned at completion
EAC=BAC/(cumulative CPI)
Earned at completion
EAC=AC+((BAC-EV)/(cumulative CPI * cumulative SPI))
Page 1
$80.00
AC
+(
Formulas
Earned to complete
ETC
VAC
$128.00
EAC
100.00
BAC
$100.00 BAC
PERT
(P+4M+O) / 6
Pessimist
PERT SD
(P - O) / 6
Pessimistic
Communication lines
( N * ( N -1 ) / 2
Communication lines
( N * ( N -1 ) / 2
0
Periodo
Revenue
0
1
2
3
4
5
6
$
$
$
$
$
$
$
Page 2
Cost
$
$
$
$
$
$
$
Net Value
0
0
0
0
0
0
0
Formulas
Actual Cost
$80.00
0.8
% Planned complete
$80.00
0.5
(% Actual Complete)
$50.00
$80.00
0.6250
$80.00
-$30.00
$80.00
0.6250
$80.00
-$30.00
$40.00
$100.00
$50.00
EV
0.6250
$160.00
$100.00
$50.00
EV
PV
PV
AC
AC
ETC
BAC
120.00
EAC
$130.00
) /
0.6250
CPI
CPI
BAC
Page 3
0.625 =
SPI
$128.00
EAC
Formulas
$80.00
48.00
= -$
28.00
AC
$128.00
EAC
$50.00
EV
4 * Most
Optimistic
$100.00 $80.00 =
2.5
BAC
AC
TCPI
$130.00 $80.00 =
1.0000
Cuanto trabajo presupuestado queda entre cuanto dinero presupuesto (BAC) qu
EAC
AC
TCPI
For example, Carl and his siblings are working on restoring a car. The BAC is $5
calculated an EAC of $2050 using the bottom-up method to replace the BAC. So
that the car needs
0 done, they believe that they have 80% of it completed at this p
is $400, the EV, the value of the work completed, is $400.
Optimist
EAC has been calculated to replace BAC, so the TCPI formula using EAC will be
our values into the formula, TCPI = ($500 $400) / ($2050 $450) = $100 / $16
0
Index (CPI) must not fall below .0625, or it must immediately improve in order to
$400/$450 = 0.89.
n-1
n-1
Present Value
$
$
$
$
$
$
$
$
NPV
Page 4
Formulas
Page 5
Formulas
ng on restoring a car. The BAC is $500, but they clearly are going to spend more, so they
m-up method to replace the BAC. So far they have spent $450, which is the AC. Of all the work
ey have 80% of it completed at this point. Since the work is 80% complete, and 80% of the BAC
eted, is $400.
o the TCPI formula using EAC will be used, which is TCPI = (BAC EV ) / (EAC AC). Placing
$400) / ($2050 $450) = $100 / $1600 = .0625. So the projects cumulative Cost Performance
must immediately improve in order to meet the cost goal. CPI is calculated by EV/ AC =
Page 6
Formulas
Page 7
Formulas
Page 8