Scheduling for 1 large pit

Rebar
3790 kg
Fabricating rebar - 10 person 2000 kg ( 2 days)

Foundation formwork
3536 m cube
10 person
Preparing/ fabricating formwork include rebar 2 days
Removal of formwork - 1 day

Structural formwork
6462 m cube
10 person
Preparing/ fabricating formwork include 3 days
Removal of formwork 1 days

Concreting works
1969 m cube
Foundation 1 day (may delayed)
Structural 2 days (may delayed)

Total workdays : 15 days