Professional Documents
Culture Documents
Sntesis del captulo 9 del texto gua( hasta 15 lneas ): Advanced MRP
Preguntas
Jacobs, F. R., Berry, W. L., Whybark, D. C., & Vollmann, T. E. (2011). Manufacturing Planning and
Control for Supply Chain Management. United States: McGraw Hill
Captulo 9
1. Cules son los trade-offs bsicos al momento de definir un tamao de lote dentro
de un ambiente MRP?
2. Cules son las tcnicas de tamao de lote ms utilizadas?
3. Cules son los tipos de incertidumbre en MRP?
4. Cmo se puede hacer uso de buffers para lidiar con la incertidumbre?
5. Por qu los sistemas MRP estn sujetos a nerviosismo?
6. Cmo enfrentan las empresas el nerviosismo presente en un sistema MRP?
Hopp, W. J., & Spearman, M. L., (2008) Factory Physics (3 rd ed), Long Grove, IL: Waveland
Press, Inc.
7. Por qu los Scheduled receipts son ajustados antes que cualquier net requirement
es calculado?
8. Cul es las reglas de tamao de lote mostradas resulta en menor inventario?
Problemas
1. End item A has a planned lead time of 2 weeks. There are currently 120 units on hand
and no scheduled receipts. Compute the planned order releases for A. The MPS is
shown:
Week
Demand
(a)
(b)
(c)
(d)
1
41
2
44
3
84
4
42
5
84
6
86
7
7
8
18
9
49
10
30
Using lot-for-lot.
Using part-period balancing, where the ratio of setup cost to holding cost is 200
Rework (a) with 50 units of safety stock. What is different from (a)?
Rework (a) with a planned lead time of two periods and a safety lead time of one period.
What is different from (a)?
(e) (Challenge) Compute the planned order releases using Wagner-Whitin, where the ratio of
setup cost to holding cost is 200.
(f) Using the fixed order period method and two periods
2. Generate the MRP output for items 200, 300, and 400 using the following information:
(Note: End item A is the same as in Problem 1)
Bills of material:
-
1
41
2
44
3
84
4
42
5
84
6
86
7
7
8
18
9
49
Item
A
200
Amou
nt on
Hand
120
300
300
140
400
200
Amou
nt on
Order
0
200
100
100
100
0
Due
3
5
4
7
Lot-Sizing
Lead
Rule
Time
(Setup/Hol
(Weeks)
d)
2
PPB(200)
2
Lot-for-lot
2
Lot-for-lot
Lot-for-lot
10
30
3. A part structure, lead time (weeks), and on-hand quantities for product A are shown in the
following figure:
Inventory on
Part
Hand
Lead time
B
(1)
F(1)
A
0
1
B
1
C(1)
D(1) 102 G(1) H(1)
C
2
D
5
1
E(1)
E(1)
E
4
1
F
5
1
C(1)
G
1
3
H
10
1
From the information shown, generate net requirements for each part to produce 10 As in
week 8 using lot-for-lot.
4. You are product planner for product A (in problem 3). The field service manager, Al
Trostel, has just called and told you that the requirements for B and F should each be
increased by 10 units for his repair requirements in the field.
a) Prepare a list showing the quantity of each part required to produce the requirements
for the service manager and the production request of 10.
b) Prepare a net requirement plan by date for the new requirements (for both production
and field service), assuming that the field service manager wants his 10 units of B
and F in week 6 and the 10 production units in week 8.
5. You have been notified via fax that the lead time for component G of product A (problem
3), has increased to 4 weeks.
a) Which items have changed and why?
b) What are the implications for the production plan?
c) As production planner, what can you do?
3
40
5
30
6
70
7
20
9
10
10
80
11
12
50
6. Develop a lot-for-lot solution and calculate total relevant costs for the data in the table.
7. Develop and EOQ solution and calculate total relevant costs for the data in the preceding
table. Stockout costs equal $10 per unit.
8. Develop a PPB solution and calculate total relevant costs for the data in the preceding
table.
9. Prepare an ordering system that always orders 100 units the week prior to a shortage (a
fixed order quantity of 100) with setup at $100 and holding cost at $1 per unit per period.
What is the cost of this ordering system?
1
35
Gross Requirements
Scheduled receipts
Projected on hand
2
30
3
40
4
0
5
10
6
40
7
30
8
0
9 10
30 55
3
5
Net requirements
Planned order
receipts
Planned order
releases
10. Prepare an alternative ordering system that orders every 3 weeks for 3 weeks ahead (a
periodic order quantity). Use the same costs as in problem 9. What is the cost of this
ordering system?
1
35
Gross Requirements
Scheduled receipts
Projected on hand
Net requirements
Planned order
receipts
Planned order
releases
3
5
2
30
3
40
4
0
5
10
6
40
7
30
8
0
9 10
30 55
11. Prepare an alternative ordering system of your own design that uses the same costs as
in problem 9. Can you do better than the previous costs?
1
35
Gross Requirements
Scheduled receipts
Projected on hand
2
30
3
40
4
0
5
10
6
40
7
30
8
0
9 10
30 55
3
5
Net requirements
Planned order
receipts
Planned order
releases
Nota:
El trabajo estar escrito a doble espacio. El participante debe venir preparado para socializar sus
inferencias, fundamentndolas; no es suficiente presentar el trabajo por escrito o mandarlo, si
acaso no puede asistir a la clase.
Se solicita correccin idiomtica en redaccin y ortografa.
El trabajo llevar la firma del participante.
* OSC: El trabajo se escribir utilizando oraciones de sentido completo.
Nota: Las calificaciones se afectarn por impuntualidad en la entrega, falta de presentacin del trabajo en
la clase, trabajo incompleto, carencia de citas sobre las fuentes consultadas, plagio, correccin idiomtica
(redaccin, ortografa), etc.