Professional Documents
Culture Documents
Junfei Hu
Department of Industrial and
Systems Engineering,
National University of Singapore,
Block E1A, #06-25,
1 Engineering Drive 2,
Singapore 117576, Singapore
Introduction
economic performance but fixed capacity may not be easily adaptable to capture more capacity demand, if needs are higher than
originally anticipated. This may also result in unearned revenues,
and additional opportunity costs.
Early research efforts have discussed the tradeoffs between the
benefits of deferring investments and the benefits from EoS in
capacity planning under deterministic conditions (e.g., Ref. [4]).
In reality, however, the environment may change in the future in
an unpredictable way and, therefore, uncertainties will inevitably
affect the systems lifecycle performance (e.g., total profits). To
account for uncertainties, techniques based on stochastic calculus
and programing can be used to determine strategies for optimal
capacity deployment (e.g., Ref. [5]). Uncertainties are typically
modeled using a finite number of scenarios [6]. Stochastic programing models can identify the strategy with optimal economic
performance by optimizing the expectation of the objective function over a range of scenarios. Such studies, however, often do no
account for the ability to adapt as uncertainty unfolds.
In light of the above, there is an additional value for designers,
architects, researchers, and planners to realize by exploiting ideas
of flexibility, more specifically in terms of future capacity expansion.
Flexibility is defined here as providing the right, but not the obligation, to change the system in the face of uncertainty [7]. A flexible
strategy can reduce the impact of downside uncertainties since less
capital may be required upfront (e.g., acting like an insurance policy). In addition, it may help generating more value by positioning
C 2016 by ASME
Copyright V
Related Work
2.1 Flexibility in Engineering Design. Flexibility in engineering design is a promising way to deal with uncertainty. It
011401-2 / Vol. 138, JANUARY 2016
Methodology
s:t:
d 0; 8t
(2)
(3)
C h Kh
(4)
Max ENPV
(
)
t
S
T
X
X
t t
1
ps C0 h
Rs h; ns Cts h; nts
1k
s1
t1
(5)
s.t.
t1
t
F ts nt
s ; hs hs 8s; t 1; 2; T
(8)
(9)
a
hts > ht1
Khts ht1
t1
t1
s if
s ; 8s; t 1; T
;
h
;
h
Hts F ts nt
s
s
s
0
otherwise
(6)
(10)
Equation (10) shows that the cost associated with the capacity
expansion is also calculated based on the power cost function.
The capacity expansion cost only occurs when additional modules
are added in the particular period.
3.2 Model Analysis. Once the capacity expansion model
with uncertainty and flexibility is developed, the optimum
capacity h and the optimum variables for decision rule function
F can be obtained. An example of function F that relates to
capacity expansion can be represented as follows: expand the
capacity by chU if the observed amount of waste collected in the
last year is more than a certain threshold (i.e., ht1
s bhU ). Here,
hU is the unit capacity of an expansion module. c and b are decision variables for the function F . c represents the scale of each
expansion and b represents the security level of the current
capacity; a higher b means decision-makers are keener to expand
the capacity to prevent capacity shortage.
This paper relies on a Monte Carlo simulation based algorithm
to generate the stochastic scenarios, find the optimum values for
decision variables (e.g., variables c and b), and quantify the
VOF. Three major steps are involved in the valuation: (1) generating sample scenarios (i.e., using historical data calibrated into stochastic processes); (2) exploring the design space using
enumeration techniques; and (3) calculating the VOF. Equations
(5) and (6) calculate the ENPV for a fixed design under uncertainty, which serves as a benchmark design. Equations (7)(10)
calculate the ENPV for a design with capacity expansion flexibility. The difference between the ENPVs is the VOF, which indicates the benefits of flexibly expanding the capacity under
uncertainty, as compared to a rigid optimal capacity benchmark
(i.e., the next best design alternative). A positive VOF shows an
increasing ENPV produced by such capacity expansion. Generally, decision-makers should not be willing to pay more than the
VOF to enable flexibility in a system design or architecture
VOF ENPVFlexible ENPVBenchmark
(11)
Case Study
2
See After Consolidation map at http://www.nea.gov.sg/energy-waste/wastemanagement/a-new-uniform-fee-for-waste-collection
(12)
RtD dt Pto
(13)
(14)
dt
6
X
dit
(15)
i1
(16)
6
X
dit
Dcoi DTri
Capv
i1
(17)
(18)
where x is the purity rate for the recycled food waste and r is the
residue rate. The first item of Eq. (18) calculates the quantity of
impurities and residues at year t, while the second item calculates
the quantity of waste that cannot be disposed at AD plants due to
capacity shortage. All of this waste should be sent to the
Transactions of the ASME
incineration plants for further disposal, and Cdis is the unit cost for
disposing waste in incineration plants.
The land cost CtL is calculated based on the installed capacity h.
It is estimated using the following equation:
CtL qh
(19)
where q is the unit land rental fee for installed capacity. The
operational and maintenance cost CtOM is assumed to be a proportion of the initial cost and is calculated using the following
equation:
CtOM pC0 h pKha
(20)
t1
1 kt
(21)
(22)
6
X
6
X
dit
Dcoi
Capv
i1
C0 hi
i1
(23)
T X
6
X
ARt;i ACt;i
t1 i1
1 kt
(24)
6
X
nti
t 1; 2; T; i 1; 2; 6
t 1; 2; T; i 1; 2; 6
(25)
(26)
i1
0.9. This is mainly because the benefit from EoS in the fixed centralized design exceeds the benefit from reducing transportation
costs in the fixed decentralized design (i.e., DTri 0 in the fixed
decentralized design). Since Singapore is a small city-state, the
transportation cost is not a significant portion of the total cost in
this context. Therefore, reducing transportation costs by using a
modular decentralized approach cannot counteract the benefits
from existing EoS.
Figure 1 also shows that the stronger the EoS (i.e., lower EoS
factors), the larger the fixed design should be (e.g., a 0.6, the
optimal centralized design is 1300 tpd; a 0.7, the optimal centralized design is 1000 tpd). This is because with strong EoS, it is
worth building large capacity upfront to benefit from the reduced
average cost per unit capacity. The NPVs for both centralized and
decentralized designs are negative values when EoS is characterized by a 0.9. This is because with weaker EoS (i.e., larger EoS
factor), capacity deployed upfront is more costly in present value
terms, and there is no phasing or modular flexibility exploited to
reduce such cost.
2000
X
s1
ps
C h
!
T
X
ARt;s h; nts ACt;s h; nts
1 kt
t1
(27)
d t dit
Eg
Pto
Pe
K
a
q
Definition
Unit cost for disposing
residues
Vehicle capacity for
collecting wastes per trip
Unit cost for fuel
consumption
Distance for collecting
wastes within sector i
Distance for transporting
wastes from sector i to the
main sector
Amount of recycled food
wastes at year t (in sector i)
Electricity generation rate
Unit tipping fee for food
wastes
Unit selling price for
electricity
Coefficient for cost function
EoS factor
Assumptions
S$77 /ton
This is the disposal cost which should be paid by AD plants to dispose of residues in
incineration plants [20]
25 tons
S$0.4/km
54 km
The price of diesel fuel is S$1.625 in Singapore [22]. It is assumed 1 l of diesel fuel is
able to last for 4 km of traveled distance.
It is assumed that the distances for collecting waste within the six sectors are the same
0 km, 20 km, 25 km, 0 km represents the distance to the main site. It is assumed that no additional effort is
29 km, 36 km, 40 km required for transporting the wastes to the main site if the wastes are collected within
the main site. The remaining numbers are represented as the distances from other sectors to the main site and are assumed based on Google map.
274 tpd(ton per day) The total recycled food waste in Singapore in 2013 was 100,000 tons [23]
S$65 /ton
It is assumed that the biogas generation rate is 150 m3/t [24]. The electricity conversion
rate is 35% and only 80% of the generated electricity can be sold to the power grid [21].
It is assumed to be slightly lower than Cdis to encourage organic waste separation.
S$0.27/kwh
305,288
0.8
Both coefficient K and EoS factor a are estimated based on the real data from Ref. [21].
Detailed analysis can be found in Hu and Cardin [26]. A reasonable range of EoS factor
is 0.61.
230 kWh/ton
S$816/tpd
T
k
Lifecycle period
Discount rate
15
8%
5%
70%
The residue rate for incineration technology is 10% in Singapore [27].The residue rate
for AD is assumed to be less than 10% since it has high efficiency [28].
In Singapore, the food wastes from industrial and commercial areas have about 3040%
impurities [29]
Long-term lifecycle period
A general discounted rate
Fig. 1 NPV (expressed in S$million) of fixed designs capacities (expressed in tpd) under deterministic analysis
Fig. 2 (a) Recycled food waste in each sector and (b) GBM simulation of total recycled food waste (5 out of 2000 runs)
2000
X
ps
s1
6
X
i1
C0 hi
T X
6
X
ARt;i;s hi ; ntis ACt;i;s hi ; ntis
1 kt
t1 i1
(28)
evaluation process. The capacity planning model of the centralized design that considers both flexibility and uncertainty can be
formulated as follows:
1kt
is true) AND IF the transportation cost of sector i (i 1; 2; 5)
s1
t1
(29) that transports the unmet demand (i.e., demand that is larger than
the current capacity) from sector i to the main site (Sector 6) is
larger than that of sectors j (j 6 i, j 1; 2; 5) THEN the modus.t. Eqs. (10), (12)(20), (25), and (26)
2000
X
ps
s1
6
X
C0 h0is 1 Cf
i1
!
t t
t t
t
T X
6 AR
X
t;i;s his ; nis ACt;i;s his ; nis C exp is
t1 i1
1 kt
(30)
Table 2 Design space and optimum decision rules for flexibility analysis
Design variables and decision variables
Initial capacity (tpd)
Capacity expansion threshold b
The number of expanded modular designs c
Decentralized threshold s
Values
Optimum value
[200,600]
[3, 3]
[1, 5]
[0, 5]
100
1
1
0.5
200
1
4
0.5
4.4.3 Sensitivity Analysis. To illustrate the overall system performance, a two-way sensitivity analysis is conducted. The VOF
of the flexible decentralized design is calculated (see Eq. (11))
when the discount rate changes from 8% to 20% with a 2% increment and the EoS factor changes from 0.4 to 1.0 with a 0.1 step
size. The results show that, under the same discount rate, the VOF
increases as the EoS factor increases (i.e., EoS become weaker).
This is because when EoS is weak, it is not worth building for
large capacity all at once at time zero. Hence, the ENPV of the
benchmark design decreases. In addition, there is more incentive
Table 3
ENPV
P5
P95
Std. dev.
Benchmark design
Best
22
12
30
5.6
27
21
32
3.1
29
23
34
3.2
Flexible decentralized
Flexible decentralized
Flexible decentralized
Flexible
to build small, and leverage the flexibility provided by the modularity when EoS becomes weaker, in line with Mannes [4] results.
Also under the same EoS factor a 0.8, the VOF increases when
the discount rate increases. For example, Fig. 4 clearly shows an
increasing trend, due to the fact that a higher discount rate can
largely reduce the present value of costs due to the deferral of
investment. Therefore, the higher the discount rate k, the more
incentive there is to delay expansion and leverage flexibility,
hence the higher VOF.
Conclusion
This study proposes a generic capacity planning model to generate the best strategies for deploying the capacity of flexible engineering systems under uncertainty. The form of the solution that
is the output of the proposed model provides a systematic guideline for decision-makers managing flexibility for capacity expansion in operations. The capacity planning model builds upon
existing methodologies, such as that developed by Manne [4], and
enables investigating tradeoffs between EoS and the time value of
money in the context of uncertainty and flexibility. Furthermore,
the model formalizes an approach based on decision rules to quantify the economic value of flexibility, as done in ROA. This study
is illustrated by selecting a capacity expansion strategy for WTE
systems in Singapore. The results indicate that embedding flexibility can improve the economic performance of a system and outweigh, in certain conditions, the benefits from EoS. In addition,
the decentralized design with flexibility outperforms all other
designs under stated conditions. This is because the value of the
flexible decentralized design is not only in reducing transportation
costs but also in the flexibility provided by the modularity, such as
deferring expenses, avoiding unnecessary capacity deployment,
and generating additional revenues when needed. It can also help
with the evaluation of developing decentralized designs in smallscale cities, even though the savings from transportation costs
may be low. This may alleviate concerns about over capacity supply, especially in an environment where economic growth is slowing down. A sensitivity analysis shows that strong EoS combined
with a small discount rate encourages building more capacity
now, while a weak EoS combined with a large discount rate
encourages building small capacity now with flexible modular
expansion in the future. The modeling framework can be used to
fine tune and help decision-makers select the optimum capacity
deployment strategies under different economic conditions.
Many opportunities for future research exist in addressing the
limitations of this work. One of the limitations is that the results
011401-10 / Vol. 138, JANUARY 2016
Acknowledgment
We are thankful for the financial support provided by the
National Research Foundation Singapore under its Campus for
Research Excellence and Technological Enterprise (CREATE),
which is administered by the National University of Singapore
and Shanghai Jiao Tong University. We are also grateful to Xie
Qihui for his valuable inputs on the early economic model.
References
[1] de Neufville, R., and Scholtes, S., 2011, Flexibility in Engineering Design, MIT
Press, Cambridge, MA.
[2] de Neufville, R., 2008, Lecture Notes, ESD.71: Engineering Systems Analysis
for Design, Massachusetts Institute of Technology, Cambridge, MA.
[3] Rapoza, K., 2014, Real Estate Oversupply Becoming Bigger Problem for
China, Forbes.com.
[4] Manne, A. S., 1967, Investments for Capacity Expansion: Size, Location, and
Time-Phasing, MIT Press.
[5] Ahmed, S., 2002, Semiconductor Tool Planning Via Multi-Stage Stochastic
Programming, International Conference on Modeling and Analysis in Semiconductor Manufacturing, pp. 153157.
[6] Martnez-Costa, C., Mas-Machuca, M., Benedito, E., and Corominas, A., 2014,
A Review of Mathematical Programming Models for Strategic Capacity Planning in Manufacturing, Int. J. Prod. Econ., 153, pp. 6685.
[7] Trigeorgis, L., 1996, Real Options: Managerial Flexibility and Strategy in
Resource Allocation, MIT Press.
[8] Cardin, M.-A., 2014, Enabling Flexibility in Engineering Systems: A Taxonomy of Procedures and a Design Framework, ASME J. Mech. Des., 136(1),
p. 011005.
[9] de Neufville, R., Scholtes, S., and Wang, T., 2006, Real Options by Spreadsheet: Parking Garage Case Example, J. Infrastruct. Syst., 12(3), pp. 107111.
[10] Cardin, M.-A., Ranjbar Bourani, M., and de Neufville, R., 2015, Improving
the Lifecycle Performance of Engineering Projects With Flexible Strategies:
Example of On-Shore LNG Production Design, Syst. Eng., 18(3), pp.
253268.
[11] de Neufville, R., 2000, Dynamic Strategic Planning for Technology Policy,
Int. J. Technol. Manage., 19(3), pp. 225245.
[12] Hreinsson, E. B., 2000, Economies of Scale and Optimal Selection of Hydroelectric Projects, International Conference on Electric Utility Deregulation and
Restructuring and Power Technologies (DRPT 2004), London, Apr. 47, pp.
284289.
[13] Luss, H., 1982, Operations Research and Capacity Expansion Problems: A
Survey, Oper. Res., 30(5), pp. 907947.
[14] Li, S., and Tirupati, D., 1994, Dynamic Capacity Expansion Problem With
Multiple Products: Technology Selection and Timing of Capacity Additions,
Oper. Res., 42(5), pp. 958976.
[15] Ryan, S. M., 2004, Capacity Expansion for Random Exponential Demand
Growth With Lead Times, Manage. Sci., 50(6), pp. 740748.
[16] Geng, N., Jiang, Z., and Chen, F., 2009, Stochastic Programming Based
Capacity Planning for Semiconductor Wafer Fab With Uncertain Demand and
Capacity, Eur. J. Oper. Res., 198(3), pp. 899908.
[17] Mittal, G., 2004, Real Options Approach to Capacity Planning Under
Uncertainty, Masters thesis, Massachusetts Institute of Technology,
Cambridge, MA.
[18] de Neufville, R., Scholtes, S., and Wang, T., 2006, Valuing Options by
Spreadsheet: Parking Garage Case Example, ASCE J. Infrast. Syst., 12(2), pp.
107111.
[19] Dixit, A. K., 1994, Investment Under Uncertainty, Princeton University Press,
Princeton, NJ.
[28] Evangelisti, S., Lettieri, P., Borello, D., and Clift, R., 2014, Life Cycle Assessment of Energy From Waste Via Anaerobic Digestion: A UK Case Study,
Waste Manage., 34(1), pp. 226237.
[29] Lim, R., and Ng, K., 2011, Recycling Firm IUT Global Being Wound
Up, The Business Times, Marshall Cavendish Business Information,
Singapore.
[30] Mikaelian, T., Rhodes, D. H., Nightingale, D. J., and Hastings, D. E., 2012, A
Logical Approach to Real Options Identification With Application to UAV Systems, IEEE Trans. Syst. Man Cybernet., Part A, 42(1), pp. 3247.
[31] Cardin, M.-A., Kolfschoten, G. L., Frey, D. D., de Neufville, R., de Weck, O.
L., and Geltner, D. M., 2013, Empirical Evaluation of Procedures to Generate
Flexibility in Engineering Systems and Improve Lifecycle Performance, Res.
Eng. Des., 24(3), pp. 277295.
[32] Lin, J., de Neufville, R., de Weck, O. L., and Yue, H. K. H., 2013, Enhancing
the Value of Oilfield Developments With Flexible Subsea Tiebacks, J. Pet.
Sci. Eng., 102, pp. 7383.
[33] Martin, J. D., and Simpson, T. W., 2006, A Methodology to Manage System-Level
Uncertainty During Conceptual Design, ASME J. Mech. Des., 128(4), pp. 959968.
[34] Spall, J. C., 2003, Introduction to Stochastic Search and Optimization: Estimation, Simulation, and Control, Wiley, Hoboken, NJ.