Some Preliminary Inputs
Some Preliminary Inputs
Have we met with the incumbent design consultant ? this will be useful
to further understand the design intent and constraints.
2)
3)
4)
5)
6)
For chilled water bypass and VSD control for primary pumps, can you
help to elaborate on the optimal flow based on existing head load and
how the modification can take place in a live data centre environment ?
7)
8)
Any issue if the check valve are mounted closer to chiller and not at
discharge side of pump ?
9)
Noticed the BMS data spikes, can you share the experience on how this
was addressed at other site facing the same issue ?
10)
Any concern/risk of sharing the chiller load with the UPS load on a
single transformer ?
11)