ODI Program P1-P3-P2-P5 Bar Chart
ODI Program P1-P3-P2-P5 Bar Chart
Activity ID
Activity Name
ODI Program
ODI - P1
15-Jul-15
BL Project
Start
BL Project
Finish
Start
Finish
24-Feb-11
13-Jul-15
24-Feb-11 A
28-Mar-17
24-Feb-11
13-Jan-14
24-Feb-11 A
30-Jul-15
2011
2012
2013
2014
2015
2016
2017
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1Q2
A1000
ENGINEERING
24-Feb-11
11-Feb-13 24-Feb-11 A
30-Jun-14 A
A1010
CONSTRUCTION
20-Sep-11
04-Dec-13 20-Sep-11 A
31-Mar-15 A
A1020
COMMISSIONING
23-Aug-13
13-Jan-14
05-Sep-14 A
30-Jul-15
25-Aug-11
14-Jul-14
25-Aug-11 A
29-Apr-16
ODI - P3
A1030
ENGINEERING
25-Aug-11
12-Aug-13 25-Aug-11 A
31-Mar-15 A
A1040
CONSTRUCTION
20-Mar-12
04-Jun-14
16-Apr-12 A
30-Mar-16
A1050
COMMISSIONING
21-Feb-14
14-Jul-14
17-Aug-15
29-Apr-16
23-Feb-12
12-Jan-15
21-Feb-12 A
27-Sep-16
ODI - P2
A1060
ENGINEERING
23-Feb-12
10-Feb-14 21-Feb-12 A
31-Mar-15 A
A1070
CONSTRUCTION
18-Sep-12
03-Dec-14 21-Feb-13 A
18-Aug-16
A1080
COMMISSIONING
22-Aug-14
12-Jan-15
15-Feb-16
27-Sep-16
23-Aug-12
13-Jul-15
21-Aug-12 A
28-Mar-17
ODI - P5
A1090
ENGINEERING
23-Aug-12
11-Aug-14 21-Aug-12 A
31-Mar-15 A
A1100
CONSTRUCTION
19-Mar-13
03-Jun-15
28-Jun-13 A
21-Feb-17
A1110
COMMISSIONING
20-Feb-15
13-Jul-15
15-Aug-16
28-Mar-17
Actual Work
Primary Baseline
Remaining Work
Page 1 of 1