Site Visit Report

Date: 11.06.2015
Site ID: MR508185
Site Name: Lukaya
Co ordinates:
Vendor:
Sub-Contractor: Jarlso
Site Supervisor: Martin
Eaton Engineer:
Emmanuel

Lat:

Long:

Site Visit Inspection

Tower Strengthening Acceptance

Observations

Newly installed bolts: M12 bolts are Grade 4.6 instead of the
required Grade 8.8
Newly installed M12 bolts not painted. Secondary horizontals with
undercoat but no final paint touch up done
Two Missing M20 bolts at joint of section 2 and 3 Contractor left on
site mobilizing to install
Torque test not done on some bolts due lack of ``accessibility`` arising from the nature of installation (Last two Photos)

Photos
Page 1 of 3

Site Visit Report

Newly installed bolts: Some M12 bolts are Grade 4.6 instead of the
required Grade 8.8

Two Missing M20 bolts at joint of section 2 and 3 Contractor left on site
mobilizing to install

Page 2 of 3

Site Visit Report

No torque test done on these bolts due lack of ``accessibility``