Ukuran baja tulangan

No
1
2
3
4
5
6
7
8
9
10
11
12

Dimensi
D6
D8
D10
D12
D13
D14
D16
D19
D22
D25
D28
D32

Diameter
Luas
Berat
Nominal penampang
nominal
(mm)
nominal (cm2) (kg/cm2)
6
0.2827
0.222
8
0.5027
0.395
10
0.7854
0.617
12
1.131
0.888
13
1.3273
1.04
14
1.5394
1.12
16
2.0106
1.58
19
2.8353
2.23
22
3.8013
2.98
25
4.9087
3.85
28
6.1575
4.83
32
8.0425
6.31

Balok Tulangan atas


As perlu (SAP2000)=
As pasang(tabel) =
=

5.382 cm2
5 x D13
6.6365 cm2 . OK

Balok Tulangan bawah


As perlu (SAP2000)=
As pasang(tabel) =
=

3.522 cm2
3 x D13
3.9819 cm2 . OK

KOLOM K1 40x40
Longitudinal
reinforcement
(SAP2000)
=
As pasang
(tabel)

=
=

16.000 cm2
8 x D16
16.0848 cm2
OK

KOLOM K2 15x30
Longitudinal
reinforcement
(SAP2000)
=
As pasang
(tabel)

=
=

4.5 cm2
4 x D12
4.524 cm2
OK