GENERAL TIME SCHEDULE OF SS "RAVSHAN" 220/110/10kV

ID

No.

Name of Task

Duration

GENERAL TIME SCHEDULE FOR SS RAVSHAN

PROJECT MANAGEMENT

PROJECT TEAM MOBILIZATION

90 days

SUBMISSTION OF MOBILIZATION PLAN

20 days

MOBILIZATION

20 days

SUPPLY OF THE EQUIPMENT OF 220kV

180 days

POWER TRANSFORMER 220/110/10kV

180 days

DISCONNECTOR 220kV

90 days

CIRCUIT BREAKER 220kV

90 days

10

10

CURRENT TRANSFORMER 220kV

90 days

11

11

VOLTAGE TRANSFORMER 220kV

90 days

12

12

SURGE ARRESTER 220kV

90 days

13

13

14

14

POWER TRANSFORMER 10/35kV

160 days

15

15

REGULATING TRANSFORMER 10/10kV

160 days

16

16

DISCONNECTOR 110kV

90 days

17

17

CIRCUIT BREAKER 110kV

90 days

18

18

CURRENT TRANSFORMER 110kV

90 days

19

19

VOLTAGE TRANSFORMER 110kV

90 days

20

20

SURGE ARRESTER 110kV

90 days

21

21

MV EQUIPMENT

90 days

22

22

REACTOR 10kV

90 days

23

23

PROTECTION & CONTROL PANEL

180 days

24

24

OHL'S TOWER 110kV & GANTRY

90 days

25

25

LINE ACCESSORY

60 days

26

26

27

27

CONSTRUCTION OF THE SS FENCE

50 days

28

28

RECONSTRUCTION/REPAIR/RESTORATION OF THE CONTROL ROOM

100 days

29

29

100 days

30

30

RECONSTRUCTION/REPAIR/RESTORATION OF THE MV
SWITCHGEAR-10kV
CONSTRUCTION OF FOUNDATION FOR THE EQUIPMENTS 220&110kV

31

31

CONSTRUCTION OF THE CABLE TRAY

45 days

32

32

INSTALLATION OF THE METAL STRUCTURE & GANTRY

45 days

33

33

INSTALLATION OF EARTHING SYSTEM OF THE SS EQUIPMENT

45 days

34

34

CONSTRUCTUON OF OIL RECEIVER AND WATER TANK

60 days

35

35

CONSTRUCTION OF THE ROADS AND BACKFILLING WITH RUBBLE

45 days

36

36

37

37

INSTALLATION OF THE EQUIPMENT OF THE 220kV

90 days

38

38

INSTALLATION OF THE EQUIPMENT OF THE 110kV

90 days

39

39

INSTALLATION OF THE POWER TRANSFORMER 220/110/10kV

120 days

40

40

INSTALLATION OF REAKTOR 10kV

10 days

41

41

INSTALLATION OF MV SWITCHGEAR 10kV

15 days

42

42

INSTALLATION OF THE PROTECTION & CONTROL PANEL

30 days

43

43

INSTALLATION OF FLEXIBLE BUS 220kV OUTDOOR SWITCHGEAR

25 days

44

44

INSTALLATION OF FLEXIBLE BUS 110kV OUTDOOR SWITCHGEAR

25 days

45

45

ASSEMBLY & INSTALLATION OF FIRE FIGHTING SYSTEM

90 days

46

46

90 days

47

47

ASSEMBLY & INSTALLATION OF HEATING, AIR CONDITIONING AND


VENTILATION SYSTEM
INSTALLATION WASTEWATER AND STORM WATER

48

48

INSTALLATION OF SECONDARY CIRCUITS AND ADJUSTING

60 days

49

49

LABORATORY TESTS

20 days

50

50

INSTALLATION OF LIGHTINGS SYSTEMS OF THE SS

20 days

51

51

ACCOMPLISHMENT OF THE SS

15 days

52

52

CONSTRUCTION OF THE OHL'S-110kC (10 km)

60 days

53

53

CONSTRUCTION OF 10kV FEEDERS FROM SS "RAVSHAN"

20 days

SUPPLY OH THE EQUIPMENT 110kV, 35kV & 10kV

CIVIL WORKS ON SS "RAVSHAN"

INSTALLATION OF THE EQUIPMENTS

Deputy General Director of JSC "TGEM"


Safarov I.D. _______________________________________

732 days

180 days

467 days

190 days

557 days

90 days

Q2

Q3

Q4

2017

Q1

Q2

Q3

Q4

2018

Q1

Q2

Q3

Q4

2019

Q1