Professional Documents
Culture Documents
2012 - Kurihara - Analysis of 2007 and 2008 Ga
2012 - Kurihara - Analysis of 2007 and 2008 Ga
Author Index
Abstract: The JOGMEC/NRCan/Aurora Mallik gas hydrate production tests were conducted using
the depressurization method in April of 2007 and March of 2008. These tests represent the first and so
far only successful sustained production in the world of methane gas to surface from a gas hydrate reservoir by depressurization. A variety of data, such as wellhead/bottom-hole pressure and temperature, gas/
water flow rates, and temperature along the casing measured by distributed temperature sensing, were
acquired during the tests. The flow rates of gas and water from the reservoir sand face during the tests
were estimated by comprehensive analysis of these data. Diverse history-matching simulation was then
conducted to reproduce these estimated flow rates, using the numerical simulator MH21-HYDRES coded
especially for gas hydrate reservoirs. This series of history-matching simulation studies quantitatively
clarified the mechanisms of methane hydrate dissociation and production, as well as what had happened
in the reservoir during the production tests. This paper describes the procedures and results of a series of
these studies, including the analyses of production-test data, numerical modelling and history-matching
simulation, which will provide beneficial insights into the mechanisms of methane hydrate dissociation
and production for future exploration and development planning for gas hydrate resources.
217
Contents
Author Index
raliss au site JOGMEC/NRCan/Aurora Mallilk ont eu lieu en avril 2007 et en mars 2008. Il sagit date
des premiers essais de production prolonge au monde ayant russi recueillir par dpressurisation le
mthane gazeux provenant dun rservoir dhydrates de gaz. Toute une gamme de donnes a t recueillie
au cours de ces essais, portant notamment sur la pression dcoulement et la temprature, aussi bien la
tte de puits quen fond de puits, et sur les taux dcoulement et la temprature du gaz et de leau mesurs
par dtection thermique simultane sur la longueur du tubage. On a procd une analyse dtaille de
ces donnes en vue dvaluer les taux dcoulement du gaz et de leau mesurs dans linterface sableux
du rservoir. Pour reproduire ces taux dcoulement estims, on a ensuite eu recours une simulation
base sur une mise en correspondance de valeurs historiques ralise laide dun simulateur numrique
MH21-HYDRES codifi spcifiquement en fonction de rservoirs dhydrates de gaz. Cette srie dtudes
de simulation base sur la mise en correspondance de valeurs historiques a permis dtablir clairement de
faon quantitative les mcanismes luvre lors de la dissociation et de la production de mthane hydrat,
ainsi que tout ce qui sest produit au sein du rservoir au cours des essais de production. Le prsent article
fait tat des procdures et des rsultats lis une srie de ces tudes, y compris les analyses des donnes
provenant des essais de production, la simulation laide dun modle numrique et bas sur la mise en
correspondance de valeurs historiques; les aperus rvlateurs ainsi tablis quant aux mcanismes grant
la dissociation et la production du mthane hydrat devraient servir aux travaux futurs dexploration et de
planification de la mise en valeur des ressources en hydrates de gaz.
218
Contents
Author Index
M.Kurihara et al.
INTRODUCTION
Background
The 20072008 JOGMEC/NRCan/Aurora Mallik Gas
Hydrate Production Research Well Program was conducted at the Mallik site, located in the Mackenzie Delta,
Northwest Territories, Canada. The main goal of the program was to measure and monitor the production response
of a terrestrial gas hydrate deposit to pressure drawdown (depressurization). The Japan Oil, Gas and Metals
National Corporation (JOGMEC) and Natural Resources
Canada (NRCan) funded the program and led the research
and development studies, with Aurora College/Aurora
Research Institute acting as the operator for the field program. This paper reviews observations (e.g. gas and water
flows, pressure-temperature regimes) made during the 2007
and 2008 production tests, and analyzes the gas and water
production from the reservoir sand face. It then provides
details on a series of history-matching simulation studies,
conducted to reproduce the test results, and discusses probable mechanisms of methane hydrate (MH) dissociation
and production during these tests. Complementary papers
have described the programs operations (Numasawaetal.,
2008; Ashfordetal., 2012a,b), well-log characteristics (Fujiietal., 2008b, 2012b), geophysical monitoring
techniques (Fujiietal., 2008a, 2012a), and production
behaviour (Kuriharaetal., 2010; Uddin et al, 2012).
In 1998, the Mallik 2L-38 gas hydrate research well was
drilled through multiple methane hydrate (MH) layers (or
zones) constituting the Mallik reservoir, and a variety of
engineering data was collected, including well-log data and
the first sub-permafrost MH core samples (Dallimoreetal.,
1999).
In March 2002, the team involved in the Mallik 2002 Gas
Hydrate Production Research Well Program conducted a
124-hour, full-scale thermal-stimulation test on the JAPEX/
JNOC/GSC et al. 5L-38 well, which yielded an estimated
468m3 of gas from one of the MH layers (Hancocketal.,
2005a). In addition, six pressure-drawdown tests were conducted using Schlumbergers wireline Modular Formation
Dynamics Tester (MDT; Hancocketal., 2005b). The gas
production observed in these tests was very small due to
the low efficiency of the thermal stimulation and the small
magnitude of pressure drawdown. However, the results of
MDT testing suggested higher initial effective permeability
to water in the presence of MH and therefore more effective fluid movement by depressurization than previously
considered (Dallimore and Collett, 2005; Kuriharaetal.,
2005a,c). This indicated the potential for substantially
higher production rates from the Mallik reservoir using the
depressurization method.
Based on the results of these tests, a decision was made to
examine the producibility of gas from one of the concentrated
MH layers at this site (identified as Mallik zoneA) using the
219
Contents
Author Index
sand with low silt content. In contrast, the upper unit (about
10701080m) consists of interbedded silty sand and sandy silt,
within which MH saturations range from 30 to80%. ZoneA
is underlain by an extensive water-bearing sand interval. Three
MDT tests conducted within this zone in 2002 indicated
sufficiently high hydraulic conductivity for the successful
application of a simple depressurization technique for driving
MH production. Judging from the pressure (about 11.7MPa)
and temperature (about 12.1C) estimated from the MDT tests
and the distributed temperature sensing (DTS) system, the contact between the bottommost MH layer and the free-water zone
beneath should be close to the theoretical base of MH stability.
Since the lower unit of this reservoir exhibits high MH saturation, and given that the initial reservoir pressure-temperature
condition is very close to the three-phase (hydrate-methanewater) MH stability threshold, zoneA was selected as a primary
target of the 20072008 production test. The basic physical
properties of zoneA are summarized in Table1.
2L-38
850
900
Zone C
Zone E
950
Depth (m)
Zone D
1000
Zone B
1050
Zone A
1100
Baseof
ofMH
methane
Base
hydrate zone
stability
stability
zone
1150
0
50
100
150
Distance (m)
220
200
250
Contents
Author Index
M.Kurihara et al.
Mallik L-38
10631101
38
Shaly sandstone
1040
Mallik 5L-38
10671102
35
Shaly sandstone
2030
5095
10631101
38
Shaly sandstone
2035
5585
505
1001000
4515
101000
0.0011
0.0011
11.48
284.7
11.50
284.8
6090
4010
1001000
0.00110
11.48
284.7
5 MPa (~581 m)
Permafrost depth (~640 m)
Perforated joint (649 m)
4 MPa (~682 m)
13.375", 61 lbs./ft., J55 (677 m)
3 MPa (~783 m)
ESP cable with chemical injection #4
CTS cable back-up ESP sensor
FC : float collar
FC (1275 m)
Shoe 9.625", 40 lbs./ft., J55 (1288 m)
Figure 2. Down-hole assemblies for the winter 2007 production test on the Aurora/
JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
221
Contents
Author Index
and production tubing) was installed (Figure2). An initial production test, designed to evaluate equipment performance and
the short-term production response of the reservoir to depressurization, was subsequently conducted over a period of about
30hours, after which the well was formally suspended pending resumption of field activities in the winter of 2008.
NOMENCLATURE
A
depth (L)
k*
=
effective permeability to single flowing
phase in the presence of methane hydrate
(L2)
222
ke
kr
relative permeability
permeability-reduction exponent
pressure (M/Lt2)
radius (L)
phase saturation
time (t)
temperature (T)
volume content
gas-compressibility factor
f = porosity
w
void ratio
~ = average
Subscript
an = annulus
B
ch
casing head
e = effective
f = fluid
fv
=
for calculation of fluid (gas and water)
volumes
g
gas phase
hp
high-permeability conduit
liquid phase
memory gauge
NMR
NMR log
o = original
ph
Phoenix gauge
standard condition
sh = shale
surface =
measured at surface
t = total
w
water phase
wp
pumped water
Contents
Author Index
M.Kurihara et al.
3 MPa (~789 m)
Chemical injection splice (injection point at 811 m)
A zone (10931105 m)
FC : float collar
Figure 3. Down-hole assemblies for the winter 2008 production test, Aurora/
JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
223
Contents
Author Index
Sh =
WHUPA
WHUTA
Relief line to
Flare stack N1
WHDPA
WHDTA
B
TRAIN A
Surface
X-mas tree Safety valve
(1)
Petrophysical properties
CINJP
f t f t NMR
ft
DPU
CR
NRV
1
Dual-pot
sand trap
Choke
manifold
C
PCV
Relief line to
Flare stack N1
P-TANK
DPU
CR
LCV
SP
D
Surface
Safety valve
(B)
WTA
WQA
GASPA
GASTA
GASDPA
GASQA
GASPC
GASTC
GASDPC
GASQC
Chemical
pump
DPU
CR
Low gas
measurement skid
Relief line to
Flare stack N2
DPU
CR
NRV
1
Phase tester
Choke Tester
PCV
SP
PCV
P-TANK
Relief line to
Flare stack N2
C
B
A
PIN
POUT
DPV
TL
CSGUP
CSGUT
LEGEND
D
Liquid line
CSGDP
CSGDT
DPU
CR
LCV
SP
D
Emergency
down stations
WTB
WQB
To 400bbl tank
GASPB
GASTB
GASDPB
QASQB
Figure 4. Surface facilities for the winter 2008 production test on the Aurora/JOGMEC/NRCan Mallik
2L-38 gas hydrate production research well.
224
Contents
Author Index
M.Kurihara et al.
Zone A
Effective porosity ( e)
Volume of shale (Vsh)
Average effective porosity
1.0
MH saturation
Average Vsh
Average MH saturation
0.9
0.8
0.7
MH saturation
0.6
Shale contente
0.5
Porosity
0.4
0.3
0.2
0.1
11 48
11 50
11 44
11 46
11 40
11 42
11 36
11 38
11 32
11 34
11 28
11 30
11 24
11 26
11 20
11 22
1116
1118
1112
1114
11 08
Zone A
Depth (m)
1110
11 04
11 06
11 00
11 02
1 0 96
1 0 98
1 0 92
1 0 94
1 0 88
1 0 90
1 0 84
1 0 86
1 0 80
1 0 82
1 0 76
1 0 78
1 0 72
1 0 74
1 0 68
1 0 70
1 0 64
1 0 66
1 0 60
1 0 62
0.0
Zone A
10000
1000
100
10
Absolute permeability
Initial permeability
0.1
0.01
1150
1144
1146
1140
1142
1136
1138
1132
1134
1128
1130
1124
1126
1120
MH: 42 layers
Depth (m)
1122
1116
1118
1112
1114
1108
1110
1104
1106
1100
1102
1096
1098
1092
1094
1088
1090
1084
1086
1080
1082
1076
1078
1072
1074
1068
1070
Water: 13 layers
Figure 5. Petrophysical properties of zone A, Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production
research well. Abbreviations: ECS, Elemental Capture Spectroscopy Sonde; SDR, Schlumberger-Doll
Research.
a)
b)
10000.0
10000.0
Av. square
error = 0.32
1000.0
Av. square
error = 0.28
1000.0
1064
1066
1060
1062
0.001
100.0
10.0
1.0
0.1
0.0
100.0
10.0
1.0
0.1
0.0
0.0
0.1
1.0
10.0
100.0
1000.0 10000.0
0.0
0.1
1.0
10.0
100.0
1000.0 10000.0
225
Contents
Author Index
(2)
(3)
(4)
OBSERVED PRODUCTION
TEST RESULTS
Winter 2007 test
After recompletion of the Mallik 2L-38 well (12m perforation interval from 1093 to 1105m KB), the pumping test
began at about 16:00 (local time) on April2, 2007. This test,
1060
Temperature
1070
1080
Depth (m)
1090
Zone A
Figure 7. Initial reservoir pressure and
temperature traverses,
and three-phase equilibrium pressure in
the Aurora/JOGMEC/
NRcan Mallik 2L-38
gas hydrate production research well.
Test interval
1100
1110
1120
Three-phase
equilibrium pressure
1130
1140
Pressure
1150
1160
9
9.5
10
10.5
11
11.5
226
12
12.5
13
Contents
Author Index
M.Kurihara et al.
Data acquired
During the production (pumping) operation, bottomhole pressure and temperature were measured (with surface
readout) at the Phoenix gauge adjacent to the pump intake
at 1124m, and at four memory gauges at about 1091m, as
shown in Figure2. The pressure at the outlet of the pump
(discharge pressure) was also monitored. In addition, a
thermometer on the pump measured the temperature of the
motor windings. At the surface, the casing-head pressure
(i.e. pressure of the annulus between casing and tubing) was
measured commencing at 04:05 on April3. Although the
temperature along the casing was measured by the DTS system, it was available only for the interval from the surface to
about 1050m (i.e. above the top of zoneA). Figure8 shows
the bottom-hole pressure and temperature measured at the
Phoenix gauge and at one of the memory gauges, along with
the casing-head pressure and pump-motor temperature.
The rate of water discharge through the pump was calculated based on the number of revolutions and the pressure
differential between the inlet and outlet of the pump. The
results are shown in Figure9 with a label of first estimate.
General observations
As shown in Figures8 and9, pumping proceeded
smoothly for the first hour after the start of testing operations, as indicated by the steady decrease in bottom-hole
pressure. After the first hour, however, the discharge pressure
decreased and the motor temperature increased abruptly,
resulting in a levelling-off in the reduction of bottom-hole
pressure (plug-off period). When the bottom-hole pressure
measured at the memory gauges (which was very close
to the pressure at the perforation interval) reached about
9.5MPa after about 4.5hours of pumping, the pump was
shut down due to the extremely low pumping efficiency. The
simple calculation shown in Figure9 (with a label of first
estimate) suggests that the pumping rate during the plug-off
period was very low except for some very short periods.
After a shut-down of about an hour, the pump was
restarted and the bottom-hole pressure decreased smoothly
for about 5hours, down to about 7.5MPa. Another plugoff was encountered at this point, which led to the second
shut-down of the pump for a period of about 1.5hours.
During this shut-down period, the casing-head pressure was
Data acquired
During the production operation, the gas-production rate
was measured by flow meters at the P-Tanks, following the
down-hole separation of water and gas into TrainsA andB,
respectively (Fig.4). In addition, the volume of produced
water accumulated in the tank prior to injection into the
Mallik 3L-38 disposal well was periodically measured. Since
227
Contents
Author Index
Start
Pump
Plug
off
Start
Pump
Shut
down
Plug
off
Shut
down
Start
Pump
Plug
off
Shut
down
500
#1
#2
#3
400
Plug-off
period
300
Plug-off
period
Plug-off
period
200
100
0
-100
-200
-300
-400
0
10
15
20
25
Time (h)
Pump rate (first estimate)
228
30
Contents
Author Index
M.Kurihara et al.
the water-production rate was too small for accurate measurement by the flow meter, it was calculated based on changes in
the volume of the water stored in this tank. The gas-production rate, measured by the flow meters, and water-production
rate, calculated from the water volume in the tank, are shown
in Figure10.
parameters are shown in Figure11. Although the temperature along the casing was measured by the DTS system,
it was available only for the interval from surface to about
1050m.
General observations
Stage 1
Stage 3
Stage 2
90
2nd rapid
depressurization
st
1 rapid
depressurization
80
3 rapid
depressurization
70
8000
7000
Pumping rate
Surface gas rate
60
6000
50
5000
40
4000
30
3000
20
2000
10
1000
0
0
10
20
30
40
50
60
70
80
9000
rd
0
90 100 110 120 130 140 150
Time (h)
Stage 3
Stage 2
1st rapid
depressurization
60
2nd rapid
depressurization
Pressure (MPa)
10
3rd rapid
depressurization
50
40
30
20
10
0
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
Temperature (C)
Stage 1
12
0
150
Time (h)
Time
(hr)
Casing-head pressure
CTS-intake pressure
Phoenix-intake temperature
Memory-gauge temperature
Phoenix-intake pressure
Memory-gauge pressure
CTS-intake temperature
229
Contents
Author Index
Contents
Author Index
M.Kurihara et al.
Simple estimation
The gas-production rate and cumulative gas production
were estimated for every 5-minute time interval using the
method described in AppendixA (Fig.12). When the bottomhole pressure was reduced from 11MPa to between 7.2and
7.5MPa, 1000to 2000m3/d of sustainable gas production
was achieved. Furthermore, an instantaneous gas-production
rate of about 8000m3/d was observed when the bottom-hole
pressure was decreased to 6.9MPa. Total gas production
throughout the winter 2007 test period was estimated at
830m3. Note that these calculations were possible only after
Start
Pump
Plug
off
Shut
down
10000
1000
8000
800
6000
600
4000
400
2000
200
0
0
Start
Pump
500
Plug
off
Shut
down
#1
10
Start
Pump
Plug
off
15
Time (h)
Shut
down
20
Start
Pump
#2
25
Plug
off
30
Shut
down
50
#3
400
40
300
30
200
20
100
10
p
Gas-production rate
( (m3/d)
)
#3
0
0
10
15
Time (h)
20
25
30
231
Contents
Author Index
Estimation of water-production
volume by matching simulation
In the above calculation, the water-production volume
must be overestimated because the pumping efficiency was
assumed to be 100%, even during the period of suspected
plugging of the pump. Therefore, the water-production
volume and pumping rate were corrected through historymatching simulation to obtain more accurate figures. In order
to estimate the water-production volume accurately, the actual
pumping rate should also be evaluated precisely. Fortunately,
down-hole temperatures were measured at the Phoenix and
memory gauges (Fig.2), providing reasonable indications of
bottom-hole temperature. Thus, we were able to estimate the
actual rate of water production from the reservoir, as well as
the actual pumping rate, by history matching both bottom-hole
pressure and temperature through simultaneous adjustment of
these rates (Kuriharaetal., 2008).
The wellbore was simulated using a radial numerical
model measuring 3by 129 grid blocks. As illustrated in
Figure14, the three columns of grid blocks allocated in the
radial direction represent the tubing, the annulus between
the tubing and the protective pump shroud, and the annulus between the tubing/shroud and the well casing. The
initial temperature profile of the liquid in the wellbore and
that of the surrounding formation were inferred from available DTS data. In addition, we assumed that, after a certain
period following the start of the test, the temperature of the
water produced from the reservoir would be very close to the
three-phase (MH-methane-water) equilibrium temperature
corresponding to the bottom-hole pressure. The heat-transfer coefficient between the fluid inside the wellbore and the
surrounding formation was estimated based on the thermal
conductivity of fluid, casing, cement, and formation. The
temperature of the outer boundary in the radial direction
was considered to be variable, reflecting the heat transfer
with the fluid in the wellbore, which was simulated using
the method proposed by Vinsome and Westerveld (1980).
Furthermore, the temperature of water injected into the disposal zone beneath the production interval was assumed
to become the same as the initial temperature of that zone.
Similarly, the water in the grid block at the location of the
pump was assumed to become the same as the pump (motor)
temperature shown in Figure8.
The results of the first trial, in which the water-production and pumping rates estimated in the previous section
were simply applied as calculation constraints, are shown
in Figure15a. In this case, calculated bottom-hole temperatures agree poorly with observed values, the error being
greater than 4C at some points. After several trial-anderror simulation runs, a successful match between simulated
and observed bottom-hole temperatures and pressures was
attained, with the errors being less than 0.5C and 0.2MPa,
respectively (Figure15b). This yielded the adjusted estimates of water-production and pumping rates labelled as
history matched in Figures13 and9, respectively.
This history-matched model suggests that water production from the reservoir ranged from 0to 80m3/d and
that the total water production throughout the test period
was approximately 20m3, instead of the 40m3 estimated in
r direction
open
Gas
Water
Heat
Gas
Movement
m
Memory
Memory
Gauge
gauge
Phoenix
Phoenix
Gauge
gauge
Pump
Pump
Modeling
Modelling
Gas-water
production
Heat
Water
Movement
m
g
Heat Generation
p
by Pump
Water
injection
z direction
232
Figure 14. Radial numerical model of the wellbore for estimating pumping and water-production
rates during the winter 2007 production test on the
Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate
production research well.
Contents
Author Index
M.Kurihara et al.
a)
12000
300
9000
295
6000
290
3000
Temperature (K)
Pressure (kPa)
285
280
0
10
15
20
25
30
Time (hr)
(h)
Time
b)
12000
300
9000
295
6000
290
3000
Temperature (K)
Pressure (kPa)
285
280
0
10
15
20
25
30
Time (h)
Figure 15. Measured and simulated bottom-hole pressures and temperatures relative
to the Phoenix gauge (1124 m) and memory gauges (~1141 m) for the winter 2007
production test on the Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production
research well: a) before matching, and b) after matching.
233
Contents
Author Index
from the reservoir was estimated for the same time intervals
based on the rate at which liquid was produced to the surface
and the change in the liquid level in the annulus.
The liquid level, bottom-hole pressure, and gas- and
water-production rates thus estimated are depicted in
Figures16 to18. The estimated gas- and water-production
rates, which fluctuate significantly, have been somewhat
smoothed by a simple moving average in Figure19. It
was confirmed that gas and water were produced continuously from the reservoir throughout the test period. The
gas-production rate ranged from 1500to 2500m3/d and the
water-production rate was 5to 15m3/d during the period that
the bottom-hole pressure had stabilized in the latter part of
the stage2. The total gas and water production throughout
the test period are estimated at about 13000m3 and 70m3,
respectively.
NUMERICAL SIMULATION
We attempted to reproduce the gas- and water-production
volumes estimated in the previous section through historymatching simulation, in order to quantitatively examine the
reservoir responses (physical and thermodynamic) to the
2007 and 2008 production tests.
Numerical simulator
The simulator used in this study (MH21-HYDRES) was
originally developed by the University of Tokyo and has
since been modified and improved by Japan Oil Engineering
Co. Ltd., the University of Tokyo, the Japan National
Oil Corporation, and the National Institute of Advanced
Industrial Science and Technology (Masudaetal., 1997,
Figure 16. Estimated well pressures and fluid levels during the
winter 2008 production test on the
Aurora/JOGMEC/NRCan Mallik
2L-38 gas hydrate production
research well.
234
Contents
Author Index
M.Kurihara et al.
st
nd
1 rapid
depressurization
2 rapid
depressurization
Stage 3
3rd rapid
depressurization
14000
6000
12000
5000
10000
4000
8000
3000
6000
2000
4000
1000
2000
0
0
10
20
30
40
50
60
70
80
0
90 100 110 120 130 140 150
Stage 2
Stage 1
7000
Time (h)
Gas-production rate (most likely)
Cumulative (aqueous)
Cumulative (aqueous)
Stage 2
st
1 rapid
depressurization
140
Stage 3
80
nd
2 rapid
depressurization
3rd rapid
depressurization
70
120
60
100
50
80
40
60
30
40
20
20
10
Stage 1
160
0
0
10
20
30
40
50
60
70
80
Time (h)
Water-production rate (most likely)
Water-production rate (gaseous)
Cumulative (aqueous)
235
Contents
Author Index
Stage 2
Stage 1
Reservoir modelling
To reflect the petrophysical properties and the initial
pressure-temperature traverses estimated in the Properties
of zone A reservoir section, a two-dimensional radial reservoir model was constructed for zoneA that mimicked an
area extending 5km from the Mallik 2L-38 well. A total of
796 grid blocks was allocated in the radial direction, 786 of
which were allocated within 1000 m of the well. In the vertical direction, 42 and 13 grid layers were assigned for the
interval above the MH-water contact and for the free-water
interval, respectively (Fig.5). The initial reservoir properties, such as effective porosity, shale content, MH saturation,
absolute permeability, and effective permeability to water,
were defined for each grid layer, as presented in Table2 and
Figure5.
The grid size in the radial direction (Dr) increased exponentially from a minimum value of 2cm for the innermost
grid block to 7.5m for the block located at 1000m from the
well. In the vertical direction, the grid blocks were more uniformly sized (Dz= 0.61.5m for the MH interval).
History matching
Overview of history-matching simulation
Figure20 illustrates the procedure for the historymatching simulation. First, the winter 2007 test results
were simulated with the reservoir model constructed as
described above, specifying the observed bottom-hole pressure profile as a boundary condition. The simulated gas- and
Stage 3
5000
100
4500
2 rapid
depressurization
rd
3 rapid
depressurization
4000
80
3500
70
3000
60
2500
50
2000
40
1500
30
1000
20
500
10
0
0
10
20
30
40
50
60
70
80
Time (h)
Gas-production rate (most likely)
236
90
nd
st
1 rapid
depressurization
Contents
Author Index
M.Kurihara et al.
Table 2. Parameters for the two-dimensional (radial) reservoir model constructed for zone A
of the Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
Model properties
Modelling area
Thickness (m)
Grid system
Number of grid blocks
Initial pressure (MPa)
Initial temperature (K)
Values
5000 m around the well
72.4 (39.4 for methane hydrate zone; 33.0 for water zone)
r-z radial co-ordinate
796 (r-direction); 55 (z-direction)
11.311.7 (11.5 at centre of methane hydrate zone)
284.2285.2 (284.8 at centre of methane hydrate zone)
5.033.8 for methane hydrate zone
Porosity (%)
10.329.9 for water zone
0.011615.8 for methane hydrate zone;
Absolute permeability (mD)
20.51538.6 for water zone
0.00663.8 for methane hydrate zone;
Initial effective permeability to water (mD)
20.51538.6 for water zone
083.0 for methane hydrate zone;
Initial methane hydrate saturation (%)
0 for water zone
17100 for methane hydrate zone;
Initial water saturation (%)
100100 for water zone
237
Contents
Author Index
10000
Gas-production rate (measured)
800
600
6000
Total gas production
(simulated) ~_ 830 m3
400
4000
Total gas production
(simulated) ~_ 40 m3
200
2000
0
0
10
15
Time (h)
238
20
25
8000
Contents
Author Index
M.Kurihara et al.
Original run
800
600
Estimated
ka (x10)
400
ke (x10)
Original
200
0
5
10
15
20
25
Time (h)
Well
Methane hydrate
is (partly)
dissociated.
Permeability gradually
increases with decrease
in MH saturation
b)
N=2
N=2
N = 10
N=10
N = 15
N=15
0.8
0.6
0.4
0.2
0
0
0.2
0.4
0.6
0.8
e.g., 45
Well
Permeability was
assumed to
increase more
drastically.
k*/k
a)
1
0
0
Sh
239
Contents
Author Index
a)
10000
10000
Gas-production rate (estimated)
8000
8000
Simulated
6000
4000
6000
4000
2000
2000
0
0
Estimated
0
5
10
15
20
25
Time (h)
b)
240
30
25
160
20
Simulated
120
15
Estimated
80
10
40
10
15
20
25
Time (h)
Figure 24. Results of preliminary history matching after introducing a high-permeability conduit model (winter 2007 test) for the Aurora/JOGMEC/NRCan Mallik 2L-38 gas
hydrate production research well: a) gas production, and b) water production.
240
200
Contents
Author Index
M.Kurihara et al.
Generation of high-permeability conduits (e.g. wormholes) in the vicinity of the well associated with the sand
production during the winter 2007 test
Expansion of these high-permeability conduits during
the winter 2008 test
Existence of free gas near the well at the beginning of the
winter 2008 test
Low vertical permeability
Extremely low relative permeability to water
Significant heterogeneities in permeability and MH saturation in both the lateral and vertical directions
Low initial salinity of formation water
Low kinetic constant for MH dissociation
Decrease in the absolute permeability in high-permeability conduits, reflecting their partial collapse and/or
deformation, and/or possible blockages of these conduits
due to the migration/accumulation of fine sand grains
during the winter 2008 test
Increase in the skin factor, due probably to the plugging
of the sand screen by the migration of fine sand and/or the
collapse of some of perforation holes during the winter
2008 test
A good match between simulated and observed/estimated production-test results was attained by adjusting the
reservoir-model parameters described below.
10000
200
9000
180
8000
160
7000
140
6000
120
5000
100
4000
80
3000
60
2000
40
1000
20
0
0
10
20
30
40
50
60
70
80
90
The winter 2008 test was then simulated, using the previously simulated results for the end of the shut-in period as an
initial condition. As shown in Figure25, the simulated winter 2008 test results were quite different from the observed/
estimated flow data, especially in the following respects:
0
100 110 120 130 140 150
Time (h)
Gas-production rate (most likely)
Water-production rate (most likely)
241
Contents
Author Index
k * = xk hp (1 Sh ) + (1 x ) k o (1 Sh ) ,
(5)
k eg = k * k rg , and
(6)
k ew = k * k rw ,
(7)
242
Contents
Author Index
M.Kurihara et al.
12
Perforation
interval
20 m
High-permeability conduits
Compaction area
Transmissibility multiplier
1.4
3m
Bottom-hole
pressure
1.2
10
8
1
0.8
0.6
4
0.4
2
Transmissibility
multiplier
0.2
0
0
10
20
30
40
50
1.6
0
60
70
80
90
Time (h)
DISCUSSION
Winter 2007 test
Source of produced gas
Approximately 830m3/d of gas and 20m3/d of water
were produced during the winter 2007 test. Possible sources
of this gas are the methane hydrate (MH) reservoir, a free-gas
layer located in the vicinity of the tested zone, and gas dissolved in the produced water. Careful interpretation of the
well-log data did not indicate the presence of a free-gas layer
(Fujiietal., 2008b). Although dissolved gas may have been
present in the produced water, the amount should have been
very small, judging from the methane solubility (about 3m3/
m3 for pure water at 10MPa and 10C) and the total amount
of water produced (about 20m3). Therefore, most of the produced gas should have come from the dissociation of MH.
Although some undissociated gas hydrate may have been
carried into the wellbore along with the sand, we infer, based
on the estimated volume of sand (and hence MH particles)
produced, that the bulk of the gas generated was from MH
dissociated in the reservoir by depressurization. This is also
suggested by the locus of the bottom-hole pressure and temperature measured at the memory gauge, which is assumed
to be almost identical to the reservoir pressure and temperature during the period of stable production. As depicted in
Figure34, the pressure-temperature values moved along the
three-phase equilibrium curves during the stable production
period, which is consistent with the dissociation of MH in
the reservoir by depressurization.
243
Contents
Author Index
1
0.9
0.8
krw (initial
guess)
0.7
0.6
0.5
0.4
0.3
0.2
krg (initial
guess)
0.1
0
0.2
0.4
0.6
0.8
Sw (fraction)
0.8
0.7
krw (modified)
0.6
0.5
0.4
0.3
0.2
0.1
0
0
krg (modified)
0.2
0.4
0.6
0.8
Sw (fraction)
krw
(initial)
Swc
0.272
Coreys N
5.0
krg
(initial)
Sgc
0.032
3.0
0.9
0.8
0.7
krw (modified)
0.6
0.5
0.4
0.3
2
0.2
krg (no
1modification)
0.1
0
0.2
0.4
0.6
0.8
Sw (fraction)
Initial guess
Coreys N
Relative permeability
1
0.9
Relative permeability
Relative permeability
krw
(high
permeability)
Swc
0.272
Coreys N
3.0
krw2
(high
permeability)
Swc
0.300
Coreys N
3.0
krg
(high
permeablity)
Sgc
0.032
Coreys N
2.8
krw
(outside)
Swc
0.350
Coreys N
5.5
krg
(outside)
Sgc
0.032
Coreys N
3.0
Figure 28. Modification of relative-permeability curves for the winter 2008 test on
the Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
Abbreviations: krw, water relative permeability; krg, gas relative permeability; Sw, water
saturation; Swc, critical water saturation; Sgc, critical gas saturation. Coreys N is a
water-saturation normalization factor for multiphase flow systems.
244
Efficiency of depressurization
The net heating value of the produced gas was calculated based on the estimated gas-production rate. The energy
required to run the pump was calculated for every 5-minute
time interval, based on the electric power consumed and
assuming a pump efficiency of 40%. This calculation
revealed that the total energy produced was about 16 times
greater than that consumed by the pump. Even though energy
other than that consumed by the pump was expended during
the test, the produced energy is still considered to exceed
the consumed energy. This suggests that the depressurization
Contents
Author Index
M.Kurihara et al.
a)
10000
1000
Gas-production rate (estimated)
Estimated
8000
800
Simulated
(calibrated)
6000
600
4000
400
2000
200
0
0
10
15
20
25
Time (h)
b)
240
30
Water- production
production raterate
(estimated)
Water
(estimated)
Waterproduction
rate
(simulated)
Water production rate (simulated)
Cumulative water
production
(estimated)
Cumulative
water
production
(estimated)
Cumulative water
production
(simulated)
Cumulative
water
production
(simulated)
25
160
20
Simulated
120
15
Estimated
80
10
40
0
0
10
15
20
200
25
Time (h)
Figure 29. Results of final history matching for the winter 2007 test on the Aurora/
JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well: a) gas production,
and b) water production.
245
Contents
Author Index
a)
Gas- production rate (measured)
7000
14000
10000
4000
8000
3000
6000
2000
4000
1000
2000
0
0
10
20
30
40
50
60
70
80
90
6000
0
100 110 120 130 140 150
Time (h)
b)
Water - production rate (measured)
Water - production rate (simulated)
Cumulative water production (mesured)
Cumulative water production (simulated)
Cumulative water production (simulated:modified)
90
80
100
90
80
70
70
60
60
50
50
40
40
30
30
20
20
10
10
0
0
10
20
30
40
50
60
70
80
90
100
110
120
130 140
0
150
Time (h)
Figure 30. Results of final history matching for the winter 2008 test on the Aurora/
JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well: a) gas production, and b) water production.
246
100
Contents
Author Index
M.Kurihara et al.
Well
well
20 m
Perforation interval
Pressure
12.000
286.000
11.000
284.500
10.000
283.000
9.000
281.000
8.000
280.000
7.000
276.000
6.000
277.000
5.000
275.500
4.000
(MPa)
Temperature
274.000
(K)
1.000
0.240
0.875
0.210
0.750
0.180
0.625
0.150
0.500
0.120
0.375
0.090
0.250
MH saturation
0.125
0.000
0.060
0.030
Gas saturation
(fraction)
(Fraction)
0.000
(Fraction)
(fraction)
Figure 31. Distributions of reservoir properties simulated using the final history-matched
model at the end of the winter 2007 test on the Aurora/JOGMEC/NRCan Mallik 2L-38
gas hydrate production research well.
Well
well
20 m
Perforation interval
Pressure
12.000
286.000
11.000
284.500
10.000
283.000
9.000
281.000
8.000
280.000
7.000
276.000
277.000
6.000
5.000
4.000
(MPa)
Temperature
274.000
(K)
1.000
0.240
0.875
0.210
0.750
0.180
0.625
0.150
0.500
0.120
0.375
0.090
0.250
MH saturation
275.500
0.125
0.000
0.060
Gas saturation
(fraction)
(Fraction)
0.030
0.000
(Fraction)
(fraction)
Figure 32. Distributions of reservoir properties simulated using the final history matched
model at the end of the shut-in between the winter 2007 and winter 2008 tests on the
Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
247
Contents
Author Index
Well
well
20 m
Perforation interval
Pressure
12.000
286.000
11.000
284.500
10.000
283.000
9.000
281.000
8.000
280.000
7.000
276.000
6.000
277.000
5.000
275.500
Temperature
4.000
(MPa)
274.000
(K)
1.000
0.240
0.875
0.210
0.750
0.180
0.625
0.150
0.500
0.120
0.375
0.090
0.250
0.060
0.125
MH saturation
0.030
Gas saturation
0.000
0.000
(fraction)
(Fraction)
(Fraction)
Figure 33. Distributions of reservoir properties simulated using the final history-matched
model at the end of the winter 2008 test on the Aurora/JOGMEC/NRCan Mallik 2L-38
gas hydrate production research well.
12000
Time
11000
memory
gauge
Memory-gauge
WCQR-1801
WCQR-1801
P-T
diagram
P-T diagram
10000
1
5
9000
Pressure (kPa)
5%KCl
5%
KCl++3%MeOH
3% MeOH
Equilibrium curve
Curve
equilibrium
8000
10
5%
KCl++2%MeOH
2% MeOH
5%KCl
equilibrium
Equilibrium curve
Curve
7000
Time
12
NaCl
4%4%
NaCl
equilibriumCurve
curve
Equilibrium
5000
11
5% NaCl
5%
NaCl
Equilibrium curve
Curve
equilibrium
6000
13
4000
1 Flow #1 start
9 Flow #3 start
10
3 Flow #1 plug-off
11
4 Flow #1 shut-off
5 Flow #2 start
12 Flow #3 plug-off
13 Flow #3 shut-off
3000
7 Flow #2 plug-off
8 Flow #2 shut-off
2000
0
10
Temperature ()
15
Figure 34. Locus of bottom-hole pressure and temperature during winter 2007 test on
the Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
248
20
Contents
Author Index
M.Kurihara et al.
a)
the simulation results with the observed/estimated gas production unless it was assumed that there was free gas near
the well at the beginning of the winter 2008 test.
According to the final history-matching results, about
2630m3 (in the standard condition) of free gas existed at the
end of the winter 2007 test (Figure31). Potentially, all of this
free gas could have been absorbed to re-form MH during the
shut-in period (Figure32), since the reservoir pressure and
temperature were within the MH stability field during this
period. However, if we assume that about 740m3 of this free
gas remained in the gaseous state at the end of the shut-in
period (i.e. the beginning of the winter 2008 test), the high
gas production with low water production can be rather easily reproduced by simulation, as shown in Figure36. This
may be a plausible scenario, given that some portion of the
residual free gas may have been isolated from free water by
membrane-like thin films of MH.
In summary, the high gas production with low water production observed/estimated in stage1 of the winter 2008
test can be reproduced assuming either 1)a relatively large
extent for the high-permeability regions, or 2)the presence of
free gas at the beginning of the winter 2008 test. In the final
b)
Well
well
Perforation
perforation
interval
interval
20 m
0.100
0.095
0.075
0.065
0.050
0.035
0.025
0.015
0.000
0.100
0.095
0.075
0.065
0.050
0.035
0.025
0.015
0.000
20 m
(Fraction)
(Fraction)
Figure 35. Fraction of each grid block in the Aurora/JOGMEC/NRCan Mallik 2L-38 gas
hydrate production research well occupied by high-permeability conduits at a) end of stage 2
of winter 2007 test, and b) end of winter 2007 test.
a)
b) 100
7000
5000
4000
3000
2000
1000
0
90
80
70
60
50
40
30
20
10
0
10
20
30
40
50
60
70
80
Time (h)
90
10
20
30
40
50
60
70
80
90
Time (h)
Figure 36. Results of history matching for the winter 2008 test on the Aurora/JOGMEC/NRCan Mallik 2L-38 gas
hydrate production research well, assuming the presence of free gas at the beginning of the winter 2008 test, for
a) gas-production rate, and b) water-production rate.
249
Contents
Author Index
We propose that the lower-than-predicted gas- and waterproduction rates may be due to a reduction in transmissibility
in the vicinity of the well associated with the skin effect,
probably caused by the migration of fine sand grains and/
or the collapse/compaction of some high-permeability conduits. Our history-matching simulations suggest that these
skin effects may have decreased reservoir transmissibility to
about 30% of its initial value (in a stepwise fashion coincident with the reduction of bottom-hole pressure), as shown
in Figure27. This scenario is consistent with the notion that
each successive pressure drop caused additional reservoir
solids (sand/silt particles) to flow towards the perforation
interval and pack against the surface of the screen, reducing
the effective transmissibility across the screen.
12000
NaCl 5%
4%
3%
Stage-1
Stage 1
11000
2%
1%
0%
Pressure (kPa)
10000
9000
8000
7000
Equilibrium
Equilibrium Curve
curve
6000
Stage-2
Stage 2
5000
4000
Stage-3
Stage 3
3000
4
4.5
5.5
6.5
7.5
8.5
9.5
Temperature (C)
Figure 37. Locus of bottom-hole pressure and temperature during the winter 2008 test
on the Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well.
250
Contents
Author Index
M.Kurihara et al.
memory gauges due to the influence of the down-hole induction heater located in the shallower part of the wellbore
(~837m); 2)inclusion in the produced water of a component of the initial (warmer) in situ pore water in addition to the
endothermically cooled water released by local gas hydrate
dissociation; and 3) the apparent nonequilibrium reaction
of MH dissociation resulting from slow dissociation of
MH restricted by a low kinetic-rate constant (although this
is considered unlikely and we have not speculated on the
possible causes of such a phenomenon). Note also that, at
the end of stage3, the temperature of the bottom-hole fluid
increased to 12.5C, which may suggest reverse circulation
of the fluids in the wellbore.
Efficiency of depressurization
As in the case of the winter 2007 test, the net heating
value of the produced gas and the energy expended on running the pump (at 40% power efficiency) for dissociation and
production of MH were calculated for every 5-minute time
interval. These calculations revealed that the total energy produced was about 32 times greater than that consumed by the
pump, which is much better than in the winter 2007 test, due
probably to more stable and sustainable gas production. The
2008 production test demonstrated that high energy efficiency
can be expected for the MH dissociation and production by
depressurization once stable gas production is established.
4500
Gas
Gas
0.09
4000
Water
Water
0.08
3500
0.07
3000
0.06
2500
0.05
2000
0.04
1500
0.03
1000
0.02
500
0.01
0
0
24
48
72
96
120
144
0.1
5000
0
168
Time (h)
Figure 38. Typical production behaviour in conventional gas reservoirs.
251
Contents
Author Index
a)
b)
Depressurization
Growth of wormhole
MH zone
MH zone
Dissociation area
Produced sand
Water-injection zone
Water-injection zone
c)
d)
Depressurization
Depressurization
Growth of wormhole
Growth of wormhole
MH zone
MH zone
Plug off!
Produced sand
Dissociation area
Dissociation area
Produced sand
Water-injection zone
Water-injection zone
f)
e)
Depressurization!
Deformation of wormhole
Gas
Re-formation
of MH
Skin?
Dissociation area
g)
Depressurization
Deformation of wormhole
Skin?
Dissociation area
h)
Depressurization
Deformation of wormhole
Skin?
Dissociation area
Figure 39. Schematic diagrams of the physical behaviour of the Mallik reservoir during the
winter 2007 and 2008 tests on the Aurora/JOGMEC/NRCan Mallik 2L-38 gas hydrate production research well, inferred from history-matching simulation: a) before winter 2007 test,
b) end of stage 1 of winter 2007 test, c) end of stage 2 of winter 2007 test, d) end of stage 3
of winter 2007 test, e) end of 20072008 shut-in, f) end of stage 1 of winter 2008 test, g) end
of stage 2 of winter 2008 test, and h) end of stage 3 of winter 2008 test.
252
Contents
Author Index
M.Kurihara et al.
CONCLUSIONS
Methane hydrate production tests
The methane hydrate production tests of the JOGMEC/
NRCan/Aurora 20072008 Gas Hydrate Production Research
Well Program were conducted using the depressurization
method during April 2007 (pre-test) and March 2008 (extended
production test). By analyzing various data acquired during
the tests, such as wellhead and bottom-hole pressures and temperatures, and gas/water flow rates, several conclusions can be
drawn and speculations made.
In the winter 2007 test, a certain amount of gas and water
were produced from a 12m perforated interval of Mallik
zone A by reducing the bottom-hole pressure to about
7MPa. The produced gas, however, was not directly delivered to the surface via the tubing but accumulated at the top
of the casing because of the irregular (on-off) pumping operations caused by excessive sand production. Hence, the test
results, including the gas- and water-production rates, were
assessed as follows based on the monitored data:
Gas- and water-production rates during the first few
hours of testing were negligible.
When the bottom-hole pressure was reduced from
11MPa to between 7.2and 7.5MPa, short-term gas-production rates of 1000to 2000m3/d were achieved, and
corresponding water-production rates of 10to 70m3/d
were inferred.
Instantaneous gas production of about 8000m3/d was
observed when the bottom-hole pressure was decreased
to 6.9MPa.
Total gas and water production throughout the test period
were estimated at about 830m3 and 20m3, respectively.
During periods of pump shut-down, some of the water
injected into the disposal zone beneath the production
interval reverse-flowed upwards towards the test interval,
thus increasing the wellbore temperature.
Sand production during testing may have created relatively
high permeability conduits (e.g. wormholes), resulting in
significantly enhanced formation permeability near the
wellbore and promoting higher-than-expected rates of
gas production for the tested bottom-hole pressure.
Energy efficiency during the production test was calculated at about16 (i.e. the energy recovered was 16 times
the energy expended).
In the winter 2008 test, which targeted the same reservoir interval, substantially higher gas-production rates were
sustained over a period of 6 days in response to a stepwise
reduction of the bottom-hole pressure to about 4.5MPa. This
sustained production was facilitated by employing sand screens
253
Contents
Author Index
Numerical simulation
The results of the MH production tests conducted in April
2007 and March 2008 were successfully history matched in a series of numerical simulations, through careful iterative adjustment
of key reservoir parameters as outlined below, and by introducing
the hypotheses of the generation and growth of high-permeability
conduits and the subsequent collapse/compaction of these conduits. Each grid block within the numerical modelling space was
considered to consist of two fractions: one having the original
absolute permeability and the other assigned an enhanced permeability value representing the influence of high-permeability
conduits (wormholes). The permeability of the near-wellbore grid
blocks was increased appropriately to simulate the generation
and growth of high-permeability conduits during the winter 2007
test. The fraction of each grid block containing high-permeability
conduits was estimated from the history-matched permeability
for the winter 2007 test, and then kept at that value throughout
the simulation of the winter 2008 test (i.e. there was no additional
formation or growth of high-permeability conduits due to sand
production). The following additional parameter adjustments
were implemented in the numerical simulations of the 2008 test:
To reproduce the lower-than-predicted gas-production rates
observed during the 2008 test, the transmissibility of the
grid blocks located in the vicinity of the well was decreased
coincidentally with the reduction of bottom-hole pressure,
in an effort to simulate the effects of the collapse/deformation of high-permeability conduits and/or accumulation of
fine sand grains in the vicinity of the well.
To suppress the simulated water production caused by
crossflow from the water-bearing layers overlying the
perforation interval, the absolute permeability in the vertical direction was reduced by a factor of 5.
254
In accordance with the results of the above history-matching simulation, the test results were examined qualitatively
as follows:
The area with high-permeability conduits created by sand
production during the winter 2007 test was simulated to
extend about 10m radially from the well. The major area
of MH dissociation was simulated to be about 7to 10m
from the well in the radial direction and about 1to 2m
above and below the perforation interval.
Numerical simulations suggest that all of the free gas
remaining within the production zone following the 2007
test could have been absorbed to re-form MH during the
shut-in period between April 2007 and February 2008,
thus increasing the MH saturation in the vicinity of the
well by 1to 5%.
Following from the previous points, we infer that the rapid
increase and decrease in gas production early in stage1
of the 2008 test was the result of rapid MH dissociation
in the near-wellbore regions containing high-permeability conduits. The subsequent gradually decreasing gas
flows observed in the later part of stage1 likely reflect a
transition in production from the highly disturbed nearwellbore region towards a more stable production regime
characteristic of the comparatively undisturbed reservoir
at greater distances from the well.
Our analysis considers that, during the winter 2008 test,
near-well reservoir transmissibility may have decreased
incrementally to about 30% of the original value,
possibly due to the collapse/deformation of high-permeability conduits and/or to the accumulation of fine solids
(sand/silt) on the surface of the screens during successive
pressure draw-down stages.
The gas production late in each stage is assumed to
reflect the dissociation of MH located outside the highpermeability regions, which suggests the intrinsic (i.e.
undisturbed by high-permeability conduits) potential of
the Mallik reservoir.
ACKNOWLEDGMENTS
This study was financially supported by the Research
Consortium for Methane Hydrate Resources in Japan (MH21
Research Consortium) to carry out Japans Methane Hydrate
Research and Development Program by the Ministry of
Economy, Trade and Industry (METI). The authors gratefully
acknowledge this financial support and permission to present
this paper. The authors also thank Waseda University, Japan
Oil Engineering Co. Ltd., Japan Oil, Gas and Metals National
Corporation, Natural Resources Canada (Geological Survey
of Canada), Aurora College/Aurora Research Institute,
the National Institute of Advanced Industrial Science and
Technology, Schlumberger K.K., and the University of Tokyo
for their technical support.
Contents
Author Index
M.Kurihara et al.
REFERENCES
Ashford, D.I., Dallimore, S.R., Hernandez-Johnson, L., Mizuta,
T., Nixon, F.M., Applejon, A, and Taylor, A.E., 2012a. Overview
of engineering and operations activities conducted as part of
the JOGMEC/NRCan/Aurora Mallik 20072008 Gas Hydrate
Production Research Well Program, Part B: 2008 field program; in Scientific results from the JOGMEC/NRCan/Aurora
20072008 Gas Hydrate Production Research Well Program,
Mackenzie Delta, Northwest Territories, Canada, (ed.) S.R.
Dallimore, K. Yamamoto, J.F. Wright, and G. Bellefleur;
Geological Survey of Canada, Bulletin 601
Ashford, D.I., Mizuta, T., Dallimore, S.R., Yamamoto, K.,
Nixon, F.M., Imasato, Y., Wright, J.F., Taylor, A.E., and
Applejohn, A., 2012b. Overview of engineering and operations activities conducted as part of the JOGMEC/NRCan/
Aurora Mallik 20072008 Gas Hydrate Production Research
Well Program, Part A: 2007 field program; in Scientific
results from the JOGMEC/NRCan/Aurora 20072008 Gas
Hydrate Production Research Well Program, Mackenzie Delta,
Northwest Territories, Canada, (ed.) S.R. Dallimore,
K. Yamamoto, J.F. Wright, and G. Bellefleur; Geological
Survey of Canada, Bulletin 601.
Dallimore, S.R. and Collett, T.S., 2005. Summary and implications of the Mallik 2002 Gas Hydrate Production Research
Well Program; in Scientific results from the Mallik 2002
Gas Hydrate Production Well Program, Mackenzie Delta,
Northwest Territories, Canada, (ed.) S.R. Dallimore and
T.S. Collett; Geological Survey of Canada, Bulletin
585, 28p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=220702> [accessed October 10, 2012].
Dallimore, S.R., Uchida, T., and Collett, T.S. (ed.), 1999.
Scientific results from JAPEX/JNOC/GSC Mallik 2L-38
gas hydrate research well, Mackenzie Delta, Northwest
Territories, Canada; Geological Survey of Canada, Bulletin
544, 403p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=213992> [accessed October 10, 2012].
Dallimore, S.R., Wright, J.F., Nixon, F.M., Kurihara, M.,
Yamamoto, K., Fujii, T., Fujii, K., Numasawa, M., Yasuda, M.,
and Imasato, Y., 2008. Geologic and porous media factors
affecting the 2007 production response characteristics of the
JOGMEC/NRCan/Aurora Mallik Gas Hydrate Production
Research Well; in Proceedings of the 6th International
Conference on Gas Hydrates (ICGH 2008), Vancouver, British
Columbia, July 610, 2008, Paper 5829, 10p.
Fujii, K., Sakiyama, N., Morikami, Y., Ikegami, T., Pimenov,
V., Shako, V., Parshin, A., Inada, N., Nakatsuka, Y., Wright,
J.F., and Dallimore, S.R., 2012a. Down-holemonitoring data
analysis and interpretation for the JOGMEC/NRCan/Aurora
Mallik Gas Hydrate Production Research Well Program;
in Scientific results from the JOGMEC/NRCan/Aurora
20072008 Gas Hydrate Production Research Well Program,
Mackenzie Delta, Northwest Territories, Canada, (ed.)
S.R. Dallimore, K. Yamamoto, J.F. Wright, and G. Bellefleur;
Geological Survey of Canada, Bulletin 601.
Fujii, K., Yasuda, M., Cho, B., Ikegami, T., Sugiyama, H.,
Imasato, Y., Dallimore, S.R., and Wright, J.F., 2008a.
Development of a monitoring system for the JOGMEC/
NRCan/Aurora Mallik Gas Hydrate Production Test Program;
in Proceedings of the 6th International Conference on Gas
Hydrates, Vancouver, British Columbia, July 610, 2008,
Paper 5830, 6p.
Fujii, T., Noguchi, S., Murray, D.R., Takayama, T., Fujii, K.,
Yamamoto, K., Dallimore, S.R., and Al-Jubori, A., 2012b.
Overview of wireline-logging analysis in the Aurora/
JOGMEC/NRCan Mallik 2L-38 gas hydrate production
research well; in Scientific results from the JOGMEC/NRCan/
Aurora 20072008 Gas Hydrate Production Research Well
Program, Mackenzie Delta, Northwest Territories, Canada,
(ed.) S.R. Dallimore, K. Yamamoto, J.F. Wright, and
G. Bellefleur; Geological Survey of Canada, Bulletin 601.
Fujii, T, Takayama, T., Dallimore, S.R., Nakamizu, M.,
Mwenifumbo, J., Kurihara, M., Yamamoto, K., Wright J.F.,
Al-Jubori, A. Tribus, M., and Evans R.B., 2008b. Wire-line
logging analysis of the JOGMEC/NRCan/Aurora Mallik gas
hydrate production test; Proceedings of the 6th International
Conference on Gas Hydrates, Vancouver, British Columbia,
July 610, 2008, Paper 5684, 12 p.
Hancock, S.H., Collett, T.S., Dallimore, S.R., Satoh, T., Inoue,
T., Huenges, E., Henninges, J., and Weatherill, B., 2005a.
Overview of thermal-stimulation production-test results
for the JAPEX/JNOC/GSCetal. Mallik 5L-38 gas hydrate
production research well; in Scientific results from the Mallik
2002 Gas Hydrate Production Research Well Program,
Mackenzie Delta, Northwest Territories, Canada, (ed.) S.R.
Dallimore and T.S. Collett; Geological Survey of Canada,
Bulletin 585, 15p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=220702> [accessed October 10, 2012].
Hancock, S.H., Dallimore, S.R., Collett, T.S., Carle, D.,
Weatherill, B., Satoh, T., and Inoue, T., 2005b. Overview of
pressure-drawdown production-test results for the JAPEX/
JNOC/GSCetal. Mallik 5L-38 gas hydrate production
research well; in Scientific results from the Mallik 2002 Gas
Hydrate Production Research Well Program, Mackenzie Delta,
Northwest Territories, Canada, (ed.) S.R. Dallimore and
T.S. Collett; Geological Survey of Canada, Bulletin
585, 16p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=220702> [accessed October 10, 2012].
Henninges, J., Schrtter, J., Erbas, K., and Huenges, E.,
2005. Temperature field of the Mallik gas hydrate occurrenceimplications on phase changes and thermal properties; in Scientific results from the Mallik 2002 Gas Hydrate
Production Research Well Program, Mackenzie Delta,
Northwest Territories, Canada, (ed.) S.R. Dallimore and
T.S. Collett; Geological Survey of Canada, Bulletin
585, 14p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=220702> [accessed October 10, 2012].
Kim, H.C., Bishnoi, P.R., Heidemann, R.A., and Rizvi, S.S.H.,
1987. Kinetics of methane hydrate decomposition; Chemical
Engineering Science, v.42, no.7, p.16451653.
255
Contents
Author Index
Kurihara, M., Funatsu, K., Kusaka, K., Yasuda, M., Dallimore, S.R.,
Collett, T.S., and Hancock, S.H., 2005a. Well-test analysis for
gas hydrate reservoirs: examination of parameters suggested by
conventional analysis for the JAPEX/JNOC/GSCetal. Mallik
5L-38 gas hydrate production research well; in Scientific
results from the Mallik 2002 Gas Hydrate Production Well
Program, Mackenzie Delta, Northwest Territories, Canada,
(ed.) S.R. Dallimore and T.S. Collett; Geological Survey of
Canada, Bulletin 585, 31p., <http://geoscan.ess.nrcan.gc.ca/
cgi-bin/starfinder/0?path=geoscan.fl&id=fastlink&pass=&form
at=FLSHORTORG&search=R=220702>
[accessed October 10, 2012].
Masuda, Y., Konno, Y., Iwama, H., Kawamura, T., Kurihara, M.,
and Ouchi, H., 2008. Improvement of near wellbore permeability by methanol stimulation in a methane hydrate production well; in Proceedings of the 2008 Offshore Technology
Conference, Houston, Texas, Paper OTC 19433, 12p.
Kurihara, M., Funatsu, K., Ouchi, H., Masuda, Y., and Narita,
H., 2005b. Investigation on applicability of methane hydrate
production methods to reservoirs with diverse characteristics; Proceedings of the 5th International Conference on Gas
Hydrates, Trondheim, Norway, June 1316, 2005, p.714725.
Kurihara, M., Funatsu, K., Ouchi, H., Masuda, Y., Yasuda, M.,
Yamamoto, K., Numasawa, M., Fujii, T., Naria, H.,
Dallimore, S.R., and Wright, J.F., 2008. Analysis of the
JOGMEC/NRCan/Aurora Mallik gas hydrate test through
numerical simulation; Proceedings of the 6th International
Conference on Gas Hydrates, Vancouver, British Columbia,
July 610, 2008.
Kurihara, M., Ouchi, H., Inoue, T., Yonezawa, T., Masuda, Y.,
Dallimore S.R., and Collett, T.S., 2005c. Analysis of the
JAPEX/JNOC/GSCetal. Mallik 5L-38 gas hydrate thermal
production test through numerical simulation; in Scientific
results from the Mallik 2002 Gas Hydrate Production Well
Program, Mackenzie Delta, Northwest Territories, Canada,
Mackenzie Delta, Northwest Territories, Canada, (ed.)
S.R. Dallimore and T.S. Collett; Geological Survey of Canada,
Bulletin 585, 20p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=220702> [accessed October 10, 2012].
Kurihara, M., Sato, A., Funatsu, K., Ouchi, H., Yamamoto, K.,
Numasawa, M., Ebinuma, T., Naria, H., Masuda, Y.,
Dallimore, S.R., Wright, J.F., and Ashford, D., 2010. Analysis
of production data for 2007/2008 Mallik gas hydrate production tests in Canada; in Proceedings of the CPS/SPE
International Oil and Gas Conference and Exhibition, Beijing,
China; Society of Petroleum Engineers, 24p.
Masuda, Y., Fujinaga, Y., Naganawa, S., Fujita, K., Sato, K., and
Hayashi, Y., 1999. Modelling and experimental studies on
dissociation of methane gas hydrates in Berea sandstone cores;
University of Tokyo, Department of Geosystem Engineering,
unpublished paper presented at 3rd International Conference
on Gas Hydrates, Salt Lake City, Utah, July 1822, 1999.
256
Masuda, Y., Naganawa, S., Ando, S., and Sato, K., 1997.
Numerical calculation of gas-production performance from
reservoirs containing natural gas hydrates; in Proceedings,
Western Regional Meeting, Long Beach, California. June
2527, 1997; Society of Petroleum Engineers Inc., Richardson,
Texas, Paper SPE 38291.
Uddin, M., Wright, J. F., Dallimore, S.R, and Coombe, D., 2012.
Gas hydrate production from the Mallik reservoir: numerical
history matching and long-term production forecasting; in
Scientific results from the JOGMEC/NRCan/Aurora Mallik
20072008 Gas Hydrate Production Research Well Program,
Mackenzie Delta, Northwest Territories, Canada, (ed.)
S.R. Dallimore, K. Yamamoto, J.F. Wright, and G. Bellefleur;
Geological Survey of Canada, Bulletin 601.
Vinsome, P.K.W. and Westerveld, J., 1980. A simple method for
predicting cap and base rock heat losses in thermal reservoir
simulators; Journal of Canadian Petroleum Technology,
v.19, no.3, p.8790.
Wright, J.F., Dallimore, S.R., Nixon, F.M., and Duchesne, C.,
2005. In situ stability of gas hydrate in sediments of the
JAPEX/JNOC/GSCetal. Mallik 5L-38 gas hydrate production research well; in Scientific results from the Mallik 2002
Gas Hydrate Production Well Program, Mackenzie Delta,
Northwest Territories, Canada, (ed.) S.R. Dallimore and
T.S. Collett; Geological Survey of Canada, Bulletin
585, 11p., <http://geoscan.ess.nrcan.gc.ca/cgi-bin/
starfinder/0?path=geoscan.fl&id=fastlink&pass=&format=FLS
HORTORG&search=R=220702> [accessed October 10, 2012].
Yamamoto, K. and Saeki, T., 2009. Resource assessment and
onshore production tests of methane hydrate; Journal of the
Japanese Association of Petroleum Technology, v.74,
p. 270279.
Contents
Author Index
M.Kurihara et al.
Appendix A:
Methods for calculating gas and water production from Mallik zone A
(winter 2007 test )
p ph pch
rl g
(A-1)
Q g ( i ) = A an D l
pch Ts
,
zps T
(A-2)
where ps and Ts are the pressure (0.1013MPa) and temperature (288.8K) at standard conditions, respectively. Then
the gas-production rate for each time interval (qg(i)) can be
estimated by differentiating Qg(i) as:
q g( i) =
dQ g ( i )
dt
Q g ( i ) Q g ( i 1)
t ( i ) t ( i 1)
(A-3)
(A-4)
W( i ) = A an D ph D l .
q w ( i ) q wp ( i ) +
W( i ) W( i 1)
(A-5)
t ( i ) t ( i 1)
Q w ( i ) Q w ( i 1) + q w ( i ) t ( i ) t ( i 1) .
(A-6)
257
Contents
Author Index
Appendix B:
Methods for calculating gas and water production from Mallik zone A
(winter 2008 test )
D l = D ph
p ph pch
rl g
(B-1)
p B = pm + g f ( D B Dm )
(B-7)
For each of the above cases, the fluid levels for calculating
the amount of gas and water present above the middle of the
perforated zone in the wellbore were estimated as:
D l fv = D B
p B pch
rl g
(B-8)
(B-3)
p
D
p
q g ( i ) = q gsurface ( i ) + A an l fv ( i ) ch ( i ) lfv ( i1) ch ( i 1)
z ( i 1) T( i 1)
z ( i ) T( i )
(B-4)
(B-5)
Q g ( i ) = Q g ( i 1) + q g ( i ) t ( i ) t ( i 1) ,
(B-9)
Ts
and
t ( i ) t ( i 1) ps
where
w=
qw
qw
=
and
q w + q g q w + q g pszT
s
pT
r pT
rg = gs s .
p zT
s
258
(B-6)
(B-10)
~
where T is the average temperature over the interval between
the liquid level and the surface, and ~z is the z-factor corres~.
ponding to pch and T
Contents
Author Index
M.Kurihara et al.
q w ( i ) = q wsurface ( i ) A an
(D
l fv ( i )
(t
(i)
D l fv ( i 1)
t ( i 1)
Q w ( i ) = Q w ( i 1) + q w ( i ) t ( i ) t ( i 1) .
) and
(B-11)
(B-12)
259