Professional Documents
Culture Documents
Failures in Soft Ground PDF
Failures in Soft Ground PDF
ABSTRACT
The success of geotechnical works on soft ground relies on important factors such as proper planning,
analysis, design, construction control and supervision. However, this is usually easier said than done and
therefore there are still repeated failures of geotechnical works such as embankment, foundation and
excavation. Most of the failures are quite similar in nature that they are caused by failing to comply with
one or a combination of the above factors. This paper presents case histories of geotechnical failures
investigated by the Authors. The causes of failures, remedial works proposed and lessons learned are
discussed. Finally, some simple guidelines to prevent failures related to geotechnical works on soft
ground are presented.
Keywords: Failure; Soft Ground; Embankment; Excavation; Foundation; Bridge
1. INTRODUCTION
The success of geotechnical works on soft ground relies on important factors of proper planning, analysis,
design, construction control and supervision. However, most of the geotechnical failures investigated by
the Authors are usually quite similar in nature that they are caused by failing to comply with one or a
combination of the factors stated above. This paper presents the statistic of the geotechnical failures
investigated by the Authors over the recent four years. Case histories of geotechnical failures of
embankments, foundations and excavations are also presented together with the causes of failures,
remedial works proposed and lessons learned. Finally, some simple guidelines to prevent failures are also
discussed.
Managing Director, Gue & Partners Sdn Bhd, Kuala Lumpur, Malaysia
Director, Gue & Partners Sdn Bhd, Kuala Lumpur, Malaysia
of supervision account for only 15%. The remaining 40% of the failures are attributed to combination of
both design and construction.
Table 1 : Cases of Failures due to Design and Construction
Category
Number of Cases
Percentage (%)
Design only
25
45%
Construction only
8
15%
From the 55 cases of failures investigated, two third of them are due to differential settlements causing
distortion to completed and/or adjacent structures as presented in Table 2. The results also reveal that all
these failures are avoidable if extra care and input from engineers having the relevant experience in
geotechnical engineering were consulted.
Table 2 : Mode of Failures
Mode of Failures
Number of Cases
Percentage (%)
2. EMBANKMENT FAILURES
Two case histories of embankment failures investigated by the Authors are presented with causes of
failures and lessons learned. The failures of two embankments (namely Embankment A and Embankment
B) occurred during the construction and are situated at the same expressway but at different locations.
2.1 Failures of Embankment A
Embankment A was initially constructed using vacuum preloading method with prefabricated vertical
drains. Figure 1 shows the cross-section of the proposed embankment. After the 1st failure, the remedial
works of stone columns were proposed and constructed. The embankment with stone columns failed
when the embankment reached 3.2m of the planned 5.5m fill height. Figure 2 shows the embankment
after 2nd failure. .
Embankment Fill (Failed Area)
(Vacuum Preloading with Vertical Drains)
Embankment Fill
(Without Vacuum Preloading)
Vertical Drains
Scale (m)
10
Heave Up
600
Sensitivity, St
10
20
0
Su = 10 kPa
2
Su = 8 kPa
F ill H e ig h t (m )
6
Stage E
Su = 17 kPa
Su = 19 kPa
12
14
16
0
0
50
100
10
Stage B
Su = 13 kPa
P ie z o m e te r H e a d (m )
D e p th (m )
Stage D
Stage C
12
Stage F
300
350
250
Piezometers at Location A
at 3.0m depth
at 6.0m depth
at 8.0m depth
-2
In view of this, instruments like piezometers, settlement gauges and vacuum meters have been installed at
site with the intention to monitor the performance of the embankment treated with vertical drains and
vacuum preloading. The construction sequence of Embankment A and changes of pore water pressure of
the piezometers in the subsoil at depths 3m, 6m and 8m throughout the construction are shown in Figure 4.
Embankment A failed not long after reaching the final fill height of 5.5m. As shown in Figure 4, from
Stage C filling onwards, the pore water pressure measured from piezometers PZ-A2 and PZ-A3 at depths
of 6m and 8m respectively increased beyond the design pore pressure until failure at Day162 after
reaching the final fill height. Piezometer PZ-A1 at 3m deep did not show increase in pore water pressure
until it was out of order after Day 130. In brief, the measurement from piezometers PZ-A2 and PZ-A3 at
Embankment A had indicated that the vacuum suction at these depths were not functioning properly and
was unable to prevent the increase of pore water pressures in the cohesive subsoil with respect to the
embankment loads.
The trend of increase in pore water pressures have been observed for more than one month but no
contingency action was taken by the Contractor and the Consultant, who was also responsible for the
design, to investigate the causes and to stop the filling until the pore water pressure in the subsoil drops
below the allowable design values. Details of back-analyses and methodology of monitoring using
observational method are presented by Gue et al. (2001) and Tan & Liew (2000) respectively.
From the monitoring results, it is clear that 1st failure of Embankment A could have been avoided if
observational method (Peck, 1969) was employed properly.
After the 1st Failure, stone columns were proposed and constructed by the Contractor using vibroreplacement process as remedial measures to support the re-construction of the new embankment. The
stone columns are of 1m diameter with grid spacing of 2.5m centre-to-centre up to a depth of 20m.
Crushed stones of size 15mm to 100mm were used as backfill medium for the stone columns. During reconstruction of the embankment on top of the stone columns, the embankment failed with large cracks (as
shown in Figure 2) when the fill height reached 3.2m which is 2.3m lower than the required fill height of
5.5m.
Table 3 : Methods for Estimation of Ultimate Bearing Capacity of Stone Columns
Mode of Failures
Bulging
General Shear
References
Greenwood (1970); Vesic (1972); Datye & Nagaraju (1975); Hughes and
Withers (1974); Madhav et al. (1979).
Madhav & Vitkar (1978); Wong (1975); Barksdale and Bachus (1983).
Figure 5 (a) Stresses on Stone Column . (b) Comparison of Different Methods (after Madhav &
Miura, 1994)
Our review indicates, the design by the Specialist Contractor only used Priebes methods (1995) to check
on the stability and settlement of the subsoils treated with stone columns. There was no evidence of
separate calculations using other methods to check on the bulging and general shear failures of the stone
columns when determining the ultimate bearing capacity; these failure modes are not sufficiently covered
in Priebes method. Table 3 lists some of the methodologies available for bulging and general shear
failure check.
From the investigation by the Authors using disturbed strength of the subsoil on the methods listed in
Table 3, the results show that generally bulging failure is not a concern but general shear failure is grossly
inadequate.
Most of the methods listed in Table 3 are reproduced in a graph by Madhav & Miura (1994) together with
their proposed method as shown in Figure 5. It is observed that there is a large range of possible ultimate
bearing capacity when using different methods and this tends to cause confusion to design engineers.
Therefore, it is recommended that when using stone columns in very soft ground (e.g. su < 15kPa) or as
remedial measures for reconstruction of failed embankments, attention shall be given to probable failure
due to general shear. In addition, load tests and close monitoring of the instrumentation should be carried
out to verify the design.
2.1 Failures of Embankment B
Embankment B is located about 2km away from Embankment A. It was initially treated with
prefabricated vertical drains. Cracks were observed at the embankment after reaching the surcharge level
with fill height of 3.9m and immediate action was taken to lower down the embankment height to Finish
Road Level (FRL) which is 1.5m lower. The embankment was observed for 2 months and since no further
cracks developed, the Consultant agreed to refill the embankment to surcharge level. Slip failure occurred
during the filling of the surcharge. After the 1st Failure, the Contractor decided to use stone columns as
remedial measures to strengthen the subsoil so that the embankment can be reconstructed. However, the
embankment supported by stone columns failed again after reaching the fill height of 3.9m.
The subsoil at Embankment B area generally consists of organic soil with a thickness of about 4m.
Underlying the organic soil is a layer of very soft to soft silty Clay with thickness of about 10m follow by
stiff to very stiff clayey Silt. Similar to 2nd failure of Embankment A, the stone columns for Embankment
B were also being design using Priebes method (1995) only without other separate checks on the bulging
and general shear failures as listed in Table 3. The investigation carried out by the Authors indicate that
the stone columns bearing capacity against general shear failure is grossly inadequate; resulting to the
failure of the embankment.
2.3 Lessons Learned from the Embankment Failures
The 1st failure of the Embankment A treated with vacuum preloading method and prefabricated vertical
drains was monitored but no action was taken to review the monitoring results and prompt for preventive
action. The failure could have been prevented if the Contractor or Consultant had reviewed the
monitoring results regularly and taken the necessary preventive action.
The failures of Embankment A and Embankment B treated with stone columns were mainly due to
inadequate design. The Authors are of the opinion that when designing stone columns to treat very soft
ground (e.g. su <15kPa) or as remedial measures for an embankment, attention should be given to probable
general shear failure instead of over relying on single method. For remedial measure, it is also important
to determine the representative disturbed (remoulded and regaining of strength through thixotropy
effects) strength of the subsoil to be used in the analyses. In addition, load test shall be carried out on
stone columns to verify the design assumptions as there are large differences among methods of analysis.
In brief, further works are necessary before a reliable unified and comprehensive design method is
available for stone columns supporting embankment on very soft ground.
When stone columns are used to treat very soft ground, it is recommended that observational method
(Peck, 1969) be used with proper instrumentation and closer monitoring to prevent failure if there is a
slight doubt on the design methodology. Many embankments on very soft ground treated with stone
columns have been successfully constructed with the help of observational method.
Failures of embankment due to design are commonly caused by the following inadequacies :(A)
Settlement Analysis
(B)
Stability of Embankment
(A)
Settlement Analysis
It is very important to evaluate both the magnitude and rate of settlements of the subsoil
supporting an embankment. This is to ensure the settlement in the long term will not affect the
serviceability and safety of the embankment.
(B)
geotechnical considerations in
the analysis, design and
construction.
Abutment
I
Abutment
II
Pier I
Pier II
II
Pilecaps
Sheer Drop
Tilt
from
Vertical
Opening
Opening between
bridge
decks at
between
bridge
Pier
II decks
at Pier II
observation infers that the upper subsoil had an undrained shear strength of about 10kPa. As a quick
preliminary check using simplified bearing capacity equation stated in Section 3.1, the ultimate bearing
capacity was about 50 to 60kPa. The estimated maximum height of fill that could be supported at failure
is about 3m which is consistent with the observed failure when the embankment reached 3m high.
Therefore, if the designer and contractor had carried out simple bearing capacity checks, failure could
have been prevented.
The results of the additional subsurface investigation after the failure show that the undrained shear
strength from the vane shear tests range from 18kPa to 51kPa with remoulded strength of 7kPa to 12kPa.
The higher su obtained from the S.I. carried out after failure is due to the gain in strength from the imposed
embankment fill over time.
A quick preliminary check on the stability of the embankment is possible using simplified bearing
capacity equation below :
qallow = (su. Nc / FOS)
where :
qallow =
allowable bearing pressure
= (fill.H + 10) (kN/m2)
fill
=
bulk unit weight of the compacted fill (kN/m3)
H
=
allowable height of embankment (m)
su
=
undrained shear strength of the subsoil (kPa)
Nc
=
5 (suggested by Authors for ease of hand calculation)
FOS =
Factor of Safety (e.g. minimum of 1.2 for short term using moderately
conservative su)
Note : The 10kPa allowance in the qallow is to cater for the minimum vehicle load.
It is also important to check for the loading on the abutment piles from lateral soil pressure imposed by the
embankment fill behind an abutment. This is to prevent failure of the pile group supporting the abutment.
Methods that can be used are Tschebotarioff (1973), Stewart, et al. (1994), Springman (1989), DeBeer
and Wallays (1972). For more complicated structures, Finite Element Method (FEM) should also be used.
When constructing bridges on very soft ground, design consultant, consultants site engineer(s) and
contractor should have some fundamental geotechnical knowledge which include understanding of the
subsoil condition and awareness on the possible problems or failures that could happen during
construction. A good example is shown in Section 3.0 where the contractor were aware that their workers
could not walk on the very soft riverbank and could have used the simple bearing capacity equation to
check on the allowable height of the fill that the subsoil can support. Quite often, failures were due to bad
temporary works that were never considered in the design.
One serious problem that usually occurs for bridge project is the temporary fill placed by the contractor to
form a temporary platform to facilitate their piling or other construction works. If not careful, slip failure
in subsoil could occur by the load imposed by the temporary fill. Therefore, it is recommended that the
design consultant should consider the possible construction method to be used by the contractor and
designed for it or check the stability when the method statement is submitted for approval or record. The
design consultant shall also ensure that during construction, the contractor must carry out works according
to the approved method statement to prevent failure. Finally, proper full-time site supervision by the
consultants representatives who have adequate site experience and knowledge are also very important to
prevent failure due to temporary works and ensure permanent works are constructed according to the
drawings and specifications.
Another common problem caused by temporary fill over soft ground is the failure to remove the
temporary fill after construction. The temporary fill would cause the compressible subsoil to settle with
time (consolidation settlement). If temporary fill area has piles, then the piles will be subjected to down
drag (negative skin friction) due to the settling subsoil and reduce the capacity of the piles. If the down
drag is not catered for in the design, the piles will have lower allowable capacity and larger settlement
causing distortion to the structures. Therefore, the design consultant shall ensure the removal of
temporary fill after construction by the contractor or to design the piles to accommodate negative skin
friction.
4. EXCAVATION FAILURE
Excavation in soft ground can be carried out either through open cut or using retaining wall system
depending on the site constraint, depth of excavation, groundwater conditions and type of subsoil. Usually
failures of retaining wall system for excavation in soft ground can be divided into four major modes of
failures :-
Inadequacy
of
Penetration Depth of
wall
or
Support
(Resisting Force)
Base Heave
Hydraulic Failure
Slip Failure
Case 1 : No Prop
Where
q = Surcharge Load
~ 10kPa (minimum)
Q =
=
q x D (no prop)
q x r (with prop)
=D+s
Case 1 : No Prop
Case 2 : With Prop
FOS =
su L D
(W + Q) D
su L r
(W + Q ) r
Note :
The required FOS is 1.2 where the vertical
shear resistance along the retained ground
shallower than the excavations is ignored.
(Kohsaka & Ishizuka, 1995).
The results of the boreholes drilled at site for design indicate that the thickness of the soft marine clay
varies from 18m to 20m follows by 25m to 32m of soft to stiff clay with an intermittent layer of dense to
very dense sand of less than 3m thick. The top layer of marine clay has an undrained shear strength (su) of
about 10kPa near the surface and slowly increases with depth.
The project involved the construction of a high rise building with a level of basement carpark. Reinforced
concrete (RC) piles were driven from the original ground level. After the installation of the reinforced
concrete piles, excavation was carried out for the construction of the basement and pilecaps. A 12m sheet
pile (FSC III) acting as temporary cofferdam was installed to facilitate the basement and pilecaps
excavation.
The sheet pile wall was stable when the excavation reached the proposed basement level of 2.5 m.
However, when the excavation for pilecaps in front of the sheet pile, reached 3.5m to 4m, the sheet pile
moved excessively towards the excavation site and the base of the excavation also heaved up. The
excessive movement of the soil pushed and moved the installed RC piles. Some of the piles moved
laterally for more than a meter thus damaging the integrity of the piles. Figure 13 shows the condition of
the site after the movement of the sheet pile wall.
2.00
Unpropped (10kPa Surcharge)
Unpropped (No Surcharge)
Propped (10kPa Surcharge)
Propped (No Surcharge)
1.75
1.50
1.25
1.00
0.75
0.50
0.25
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
The Authors also carried out back-analyses for the adequacy of the sheet pile penetration depth using the
simplified gross pressure method. The results are presented in Figure 15 which indicate that the critical
depth of excavation using 12m deep sheet pile in the above site ranges from 2.75m to 3.5m depending
whether it is propped and with 10kPa surcharge. The results confirm that the 12m penetration depth of the
sheet pile is not adequate to support an excavation depth exceeding 3.5m with props at this site.
5. CONCLUSIONS
The case histories of failures related to geotechnical works on soft ground have clearly indicated that these
failures are generally quite similar in nature and are avoidable. These failures are usually man-made and
caused by failing to comply with one or a combination of factors which include planning, analysis, design,
construction control and supervision. Observational method should be used to compare design prediction
with field performance to ensure safety.
From the 55 cases of failures investigated by the Authors over the recent four years, 50% of them are due
to inadequacy in design. In order to prevent similar failures, it is important for design consultant,
consultants site representatives and contractor to have some fundamental geotechnical knowledge so that
any inconsistencies at site can be spotted and precautionary actions taken before failure occurs. Proper
full-time site supervision by the consultants representatives with adequate experiences, knowledge is a
must. It is also the obligation of the consultant to properly brief the supervising team on the design and
construction requirements.
REFERENCES
Aboshi, H., Ichimoto, E., Enoki, M. and Haraka, K. (1979). The Compozer A Method to Improve
Characteristics of Soft Clays by Inclusion of Large Diameter Sand Columns. Proc. Intl. Conf. On
Soil Reinforcement : Reinforced Earth and other Techniques, Paris, Vol. 1, p.211-216.
Barksdale, R.D. and Bachus, R.C. (1983). Design and Construction of Stone Columns. Report No.
FHWA/RD-83/026, National Technical Information Service, Springfield, Virginia, USA.
Bergado, D.T. and Lam, F.L. (1987). Full Scale Load Test of Granular Piles with Different Densitites and
Different Proportions of Gravel and Sand in Soft Bangkok Clay. Soils and Foundations, Vol. 27,
No. 1, p. 86-93.
Bergado, D.T., Alfaro, M.C. and Chai, J.C. (1991). The Granular Pile : Its Present State and Future
Prospects for Improvement of Soft Bangkok Clay. Geotechnical Engineering, 22 , p. 143-175.
Datye, K.R. and Nagaraju, S.S. (1981). Design Approach and Field Control for Stone Columns. Proc.
10th Intl. Conf. On Soil Mech. Found. Engg., Stockholm.
DeBeer, E.E. and Wallays, M (1972). Forces Induced in Piles by Unsymmetrical Surcharges on the Soil
Around the Piles. Proc. 5th ECSMFE. Madrid, Vol. 1, p. 325-332
Gue, S. S. & Tan, Y. C. (2003), Prevention of Failure of Bridge Foundation and Approach Embankment
on Soft Ground. Lead Speaker, 2nd International Conference on Soft Soil Engineering and
Technology, Putrajaya, Selangor, July, 2003.
Gue, S. S. & Tan, Y. C. (2001), Geotechnical Solutions for High Speed Track Embankment A Brief
Overview, Technical Seminar Talk, PWI Annual Convention, Permanent Way Institution, Beserah,
Kuantan, Pahang, 28th 29th September, 2001.
Gue, S. S., Tan, Y. C. & Liew, S. S. & Ng, H. B. (2001), Failure of an Embankment Treated with
Vacuum Preloading Method, Proceedings of the XVth International Conference on Soil Mechanics
and Geotechnical Engineering, Istanbul, Turkey, Vol. 3, p. 1749 1751.
Gue, S.S. and Tan, Y.C (2000). Subsurface Investigation and Interpretation of Test Results for
Foundation Design in Soft Clay. Seminar on Ground Improvement Soft Clay (SOGISC-2000),
23-24 Aug. 2000, UTM, Kuala Lumpur.
Gue, S.S. (1999). Selection of Geotechnical Parameters for Design. Short Course on Soil Investigation
and Design for Slope (SCOFG99), 11 & 12th May, 1999, Kuala Lumpur.
Gue,S.S. and Tan, Y.C. (1998) Design and Construction Considerations for Deep Excavation. Lecture.
IEM Northern Branch, 26 September, 1998. Penang.
Gue, S.S. (1988). An Investigation into Geotechnical Failures of a Bridge Project. IEM/RRIM Joint
Engineering Symposium, 20th Aug 1988, Johor Bahru, Malaysia.
Greenwood, D.A. (1970). Mechanical Improvement of Soils Below Ground Surface. Proc. Ground
Engg. Conference, Institute of Civil Engg., p. 9-20.
Hughes, J.M.O. and Withers, N.J. (1974). Reinforcing soft cohesive soil with stone columns. Ground
Engineering. Vol. 7, No. 3, p. 42-49.
Hughes, J.M.O., Withers, N.J. and Greenwood, D.A. (1975). A Field Trial of Reinforcing Effects of
Stone Columns in Soil. Geotechnique, Vol. 25, No. 1, p. 31-44.
Kohsaka, N. & Ishizuka, K. (1995). Stability of Bottom during Deep Excavations A Survey on
Japanese Codes. Proc. of the Intl. Symposium on Underground Construction in Soft Ground,
(additional paper),New Delhi, India, p. 323-328.
Madhav, M.R. and Miura, N. (1994). Stone Columns, Proc. 13th Intl. Conf. Soil Mech. Found. Engg.,
New Delhi. India. 4 , pp. 163-164.
Madhav, M.R., Iyengar, N.G.R., Vitkar, R.P. and Nandia, A. (1979). Increased Bearing Capacity and
Reduced Settlements due to Inclusions in Soil:. Proc. Intl. Conf. On Soil Reinforcement : Reinforced
Earth and Other Techniques, Vol. 2, p.239-333.
Madhav, M.R. and Vitkar, R.P. (1978). Strip Footing on Weak Clay Stabilized with Granular Trench or
Pile. Canadian Geotechnical Journal, Vol. 15, No. 4, p.605-609.
Peck, R.B. (1969). Advantages and limitations of the observational method in applied soil mechanics.
Geotechnique. Vol. 19, No.2, pp.171-187.
Potts, D.M. (2003). Numerical Analysis : A Virtual Dream or Practical Reality ?. Geotechnique. Vol
53, No 6, p.535-573.
Priebe, H.J. (1995). The Design of Vibro Replacement. Ground Engineering, December , pp. 31-37.
Springman, S.M. (1989). Lateral Loading on Piles due to Simulated Embankment Construction. PhD
thesis. Cambridge University.
Stewart, D.P., Jewell, R.J. and Randolph, M.F. (1994). Design of Piled Bridge Abutments on Soft Clay
for Loading from Lateral Soil Movements. Geotechnique, Vol. 44, No. 2, p. 277-296.
Tan, Y. C. and Liew, S. S. (2000). Observational Method to Prevent Failure of Embankment Treated
with Vaccum Preloading. Seminar on Failures Related to Geotechnical Works, IEM, Kuala Lumpur
Tan, Y.C. and Gue, S.S. (2000). Embankment over Soft Clay Design and Construction Control.
Seminar on Geotechnical Engineering, 22 & 23 September 2000, Penang.
Tschebotarioff, G.P. (1973). Foundations, Retaining and Earth Structures. McGraw-Hill. New York.
Wong, H.Y. (1975). Vibroflotation Its Effect on Weak Cohesive Soils. Civil Engineering (London),
No. 82, p. 44-67.
Vesic, A.S. (1972). Expansion of Cavities in Infinite Soil Mass. Journal of Soil Mech. And Found.
Engg Div., ASCE, Vol. 98, No. SM3, p. 265-290.