Professional Documents
Culture Documents
New Microsoft Word Document
New Microsoft Word Document
No.
Description of
Documents
Present
status
1.
2.
3.
4.
A) LISEGA - Snubber
QAP for SG Snubber - Rev-F
QAP for PCP Motor Snubber - Rev-D
General Machining Procedure
Procedure for Visual & Dimensional
Examination
Approved
Approved
Approved
Pending for
Approval by NPCIL
5.
Approved
Approved
1.
2.
3.
4.
5.
6.
RT Procedure
Pneumatic Test Procedure
1.
2.
3.
1.
6.
7.
8.
9.
10.
11.
Approved
Approved
Approved
Pending for
Approval by NPCIL
Remarks
Reference
Documents are to
be submitted by
LISEGA.
Reference
Documents are to
be submitted by
LISEGA.
Approved
To be Revise and
resubmitted by
PLL
Approved
To be revised and
resubmitted by
PLL
To be revised and
resubmitted by
PLL
Pending on NPCIL
Approved.
Updated
procedure to be
sent by PLL
To be revised and
resubmitted by
PLL
PO for KAPP is
pending
Despite 3
reminders been
sent. Without
PO, QA
reference
Number cant
be generated.
Unpriced PO
copy to be
submitted by
PLL as soon as
possible.
Comments to be
included.
(Submitted
Procedure was old
procedure of Jugal
Udyog)