1. t=18 minutes
OT = 450 minutes/day
tasks = 17
longest task time = 2.4 minutes
a. minimum cycle time = 2. 4 minutes
maximum cycle time = 18 minutes
b. what range of output is possible?
Output Capacitymin cycle time = OT
cycle time
= 450 minutes
2.4 minutes
= 187.5 units

Output Capacitymax. cycle time = 450 = 25


units
18
c. minimum # of workstations for
maximum output?
Nmin = sum of all times
CT
= 18 minutes
2.4 minutes
= 7.5 stations (8 stations)
d. what cycle time will provide output of
125 units/day?
Output Capacity = OT
cycle time
125 = 450 minutes
CT
125 CT = 450
125 CT = 450

125
125
CT = 450 = 3.6 minutes
125
e. What output potential will result if
cycle time is (1) 9 minutes (2) 15
minutes?
Output Capacity = OT
cycle time
= 450 minutes = 50 units
9 minutes
Output Capacity = OT
cycle time
= 450 minutes
15 minutes

= 30 units

Problem 4
a(1) draw the precedence diagram
.2

.4

.3

1.3

.1

.3

1.2

.8

a(2) Assign tasks according to > # of


following tasks. Assume the cycle time
is to be the minimum.
Min. Cycle time = 1.3 minutes
Nmin = sum of task times
CT
= 4.6 minutes
1.3 minutes
= 3.538 stations (4 stations)

Work Station #1
CT = 1.3 minutes
a -.2
1.1 minutes
b -.4
.7 minutes
c -.3
.4 minutes
e -.1
.3 minutes Idle Time
Work Station #2
CT = 1.3 minutes
d -1.3
0 minutes Idle Time
Work Station #3
CT = 1.3 minutes
f -.8
.5 minutes
g -.3

.2 minutes Idle Time


Work Station #4
CT = 1.3 minutes
h -1.2
.1 minutes Idle Time
a(3) determine % of Idle Time
Total Idle Time ____________________
.6 minutes
% Idle time = Idle time per cycle * 100
Nactual * Cycle time
= .6 minutes
*
100
4 WS * 1.3 minutes
= .6 * 100
5.2
= .1153856 * 100 =
11.54%

a(4) output for 420 minute work day?


Output Capacity = OT
cycle time
= 420 minutes = 323.07 units
1.3 minutes

Problem 5
(ignore desired output of 240 units per
day, balance on min. CT)
a. draw the precedence diagram
a

c
f

b. max. cycle time = t


= 4.6 minutes
c. min. # of stations needed.
Min. cycle time = 1.2 minutes
Nmin = t
CT
= 4.6 minutes
1.2 minutes

= 3.83 stations (4 stations)


d. Assign tasks on ># of following tasks.
Use > time as tiebreaker.
Work Station #1
CT = 1.2 minutes
a -.2
1.0 minutes
b -.4
.6 minutes
d
-.4
.2 minutes
c
-.2
0 minutes Idle Time
Work Station #2
CT = 1.2 minutes
f -1.2
0 minutes Idle Time
Work Station #3
CT = 1.2 minutes

-1.2
0 minutes Idle Time

Work Station #4
CT = 1.2 minutes
g -1.0
.2 minutes Idle Time
e. compute % Idle time
Total Idle time = .2 minutes
% Idle time = Idle time per cycle * 100
Nactual * Cycle time
= .2 minutes
*
100
4 WS * 1.2 minutes
= .2 * 100
4.8
= .041666 * 100 = 4.16%