Grid leveling is used for site investigation
Cutting Area
End point
A1
A2
A3
A4
B1
B2
B3
C1
C2
C3
D1
Height
1.40
0.60
0.55
0.13
0.90
0.70
0.40
0.60
0.10
0.00
0.10
M.factor
1
3
3
3
3
6
6
3
6
6
3
Weighting
1.40
1.80
1.65
0.31
2.70
4.20
2.40
1.80
0.60
0.00
0.30
Total
17.24
Cutting Area:- =
400
6
17.24
= 1149.33M3
Filling Area
End point
A
B
B
C
C
D
Height
0.23
0.01
0.46
0.34
0.75
0.05
M.factor
1
3
3
6
3
4
Weighting
0.23
0.03
1.38
2.04
2.25
0.20
D
D
D
E
E
E
E
E
F
F
F
F
F
Total
0.23
0.56
1.02
0.12
0.24
0.31
0.67
1.16
0.46
0.51
0.62
0.75
1.24
6
6
3
3
6
6
6
3
2
3
3
3
1
1.38
3.36
3.06
0.36
1.44
1.86
4.02
3.48
0.92
1.53
1.86
2.25
1.24
32.89
Filling Area:- =
400
6
32.89
= 2192.67M3