You are on page 1of 3

Microsoft Project - Tutorial

Earned value and schedule variance


In this tutorial you will learn how to obtain earned value performance information and how to examine schedule variance in real time.

Obtain earned value performance

After entering actual progress we want to look for earned value indicators on how well we are doing. We are going to change the view but
instead of choosing a table from the menu we need to select more tables and select Earned value from our list. Now we get a sheet with our
earned value information. We can compare the earned value with the planned value which measures following costs:

Cost variance (CV)the difference between a tasks estimated cost and its actual cost (the formula CV = Earned Value Actual Cost).

Schedule variance (SV)the difference between the current progress and the scheduled progress of a task, in terms of cost (the formula
SV = Planned Value Earned Value).

Microsoft Project - Tutorial

Estimate at completion (EAC) is the estimated total cost of a task or project, based on performance as of the status date.

Budget at completion (BAC) shows an estimate of the total project cost.

Variance at completion (VAC) shows the difference between the budget at completion (BAC) and the estimate at completion (EAC).

When we look at our project by January 18th we are suppose to spend roughly 20.500, we have earned for actual work a little less 19.800 but
we spend over 27.800 so we have a negative amount for both scheduled as cost variance. There is more than 700 worth of work that is
supposed to be done but that hasnt been done and on the existing work we achieved we are 8000 over budget.

Microsoft Project - Tutorial

Examine schedule variance in real time


According to our schedule variance we are behind in time calculated in money for 700. When we want to look at the schedule variance in time
we need to go to view > variance where we get a sheet with a view at our baseline start, actual start, start variation which shows us how much
time we started ahead/late on our task and the finish variation which shows by how much time we finished early or late. When we look at our
project we see the 4 workdays we started ahead of schedule but it took us a day longer than expected to finish.

You might also like