You are on page 1of 1

Homework #4

PE5563

Due: Oct. 10, 2016

1. Use the following figure with the following additional data;


= 1000, = 750 , = 50 , = 50, = 0.25, = 5 106 1 ,

= 1.0
, = 5 2 , = 5000 .

Make additional assumptions if necessary, and do the following tasks:
a) Using explicit method, solve the pressures in each grid block using an interval of 30 days
from day 0 to 360 days.
b) Using implicit method, solve a). You need write out the equation system for the time 30
days, and then solve it and other following steps using your program that you wrote for
HW#3. The functioning whole program should be turned in.