8833 CS One At Colombo, Sri Lanka

Date:

Reclamation and Marine Facilities


Description
A

Construction of Breakwater

1
2
3
4

Breakwater
Supply and place rocks of various sizes (5 - 200 kg)
Supply and place rocks of various sizes (1000 - 3000 kg)
Supply and lay Geotextile membrane
Supply and place X Bloc Concrete Blocks - 8m3/per unit
Total cost for Breakwater

Unit

Qty

Unit Rate (US$)

m3
m3
m2
Units

167,050.00
112,450.00
50,050.00
5,355.00

3.06
2,365.06

Amount (US$)
Amount

0.00
0.00
153,351.85
12,664,917.58
12,818,269.43

0.00

11/06/2016 02:47:17

Page 1

Breakwater

10/20/2016
Amount (US$)
Total Cost

12,818,269.43

0.00

11/06/2016 02:47:17

Page 2

Breakwater