Testyourunderstanding.Printoutthefollowingsummarysheetthenfillintheblankspacestocompletethedocument.
A.ProjectManagementTools
AGANTTchartdisplaystasksalonga(1)..timescale.GANTTchartsshouldshowthebestpossiblewaytocompletethetaskinthe(2)..time.Activitiescanbedo
sequentially,andtheGANTTchartshowsthisclearly.PERTdiagramsorcriticalpathnetworks,ontheotherhand,useagraphicalformtoshowrelationshipsbetween(4)..
diagramnetwork..showtheinterdependenceofeventsandthe(6)..pathisusedtoshowthesequenceofeventsthathavethesumofthelongestduration.Toallowf
organizationsareestimatingactivitytimes,threeestimatesareprovided,the(7)..time,themost(8)..timeandthe(9)..time.
Answers
A.ProjectManagementTools
(1)horizontal
(2)shortest
(3)parallel
(4)activities
(5)timeframe
(6)critical
(7)pessimistic
(8)probable
(9)optimistic