Se aa.
IN ITS
TRACKS
Dimas Satya Lesmana, Country Manager (Indonesia),
Clock Spring company, L.P., describes a successful crack arrest
repair procedure on a 12 in. H.P. gas pipeline in South Sumatera.
te Cae egies
Pet ea emi et
Re ae er
pee ee erect ko
eet eee ee eC
Ce eer
eee een eta Manatee saeco
Pee ee eee eed
fon applications such as: CO, pipelines, service and operation
Cee ae ee er
eee ee ec
Cte eee tera
he original design, development and testing of the
high strength Clock Spring composite repair system
‘An operator of a high pressure (83 bar) 12in.
ee ae ae
Ce eee td
Proresee a
See i
Ce eee Mee or)
ere eer es
Cee ee)
eeFigure 2. X:
‘The area was repaired with the installation of a high
pressure leak repair clamp, as shown in Figure 3, ard the
Pipeline returned back to service.
Following the installation ofthe repair clamp, the cient
performed further evaluation ofthe material characteristics
and determined it would be prudent to install crack arestors
10 ether side of the repair This will not prevent cracks:
{rom continuing to propagate, however testing has shown
application of a crack arrestor and transfer of hoop stress can
‘greatly reduce this process. In ackltion, should cracks continue.
to propagate, the installation of Clock Spring will prevent pipe
rupture and potential catastrophic faire
“The Clock Spring repair features a full cured laminate high
strength composite col, which Is sized for the specific pipeline
diameter,
‘The coils a unique construction of continuous strand
‘lass fibre, aligned in the hoop direction and hed within a resin
‘matrix. Each Clock Spring col is manufactured under strict
{QHVCC guidelines and is given its own unique part number
to ensure complete treceabilty and provides confidence
to the oporator that the repair provides full raceabiity and
repeatabily and is manufactured in accordance to the repait
products 2s originally uiised and reported within the test work
‘conducted by the GRI for which the 80 year peranent repair
approval applies. This ensures there are no variables in the
‘complete mechanical performance and safety af Clack Spring
products, which are now used in over 72 countries worldwide,
In conjunction withthe high strength Clock Spring col, a
high compressive strength filers placed into any defect area,
Cr void on the pipe surface to transfer the load (hoop stress)
{rom the pipe wall the composite coll. The complete system
is then applied and bonded in place using a forrulated and
propristary adhesive. A typical composite leave installation
Consists of three parts:
1. Acomposite structure of unidirectional glass fibres and a
polymer base.
2 An adhesive system,
‘Anigh comoressive strength loacktransferring compound.
Figure 4 provides a schematic of a completed Clok Spring
instalation,
Fora crack arrest application, the cols sized to provide
12 fll complete layers around the circumierence of the pipe;
the coll is then installed around new or existing stee! pipaines
at specified intervals, eliminating the need of removing the
Bipeline from service,
‘The strength of the glass fibre and memory ofthe
‘composite combine to provide the barrior needed to stop the
Pipe wall buiging and potential propagation of cracks. In most
Crack arest applications, two or tee units (pending the pipe
‘lameter and yield strength calculations) are placed side-by-
Side to ensure that the crack can be fully arested.
‘The ease of instalation makes the composite sleeve crack
arrestor system effective. Theso units can be installed on theFigure 5. Surface preparation being complete:
pipeline without the need for any hot work, oF for any heavy oF
‘specialised installation equipment or skled labour.
‘Atypical installation consists of locating and cleaning
the pine surface where the crack arrestor will be installed
(Figure 8). Filing any voids undor the composite sleeve with
the high compressive strength filer material and then applying
the col.
\With the inner edge of tho composite secured to a
startar pad, the composite can be wrapped and tightened
‘onto the pipe. Each coil installation will take in the region of
£20 - 30 minutes and wil achieve full cure within two hours.
Figure 6.
‘As shown in Figur 6, the decision was made to install a
total of three colls ether side ofthe repair clamp to provide
reinforcement for over 11m both up and downstream ofthe
clamp.
For this critical repair application. the use of the Clock.
Spring crack arrest system has alowed the operator to
‘ensure the continued operation ofthe pipeline in a safe and
conscientious manner, and at the same time eliminated the
immediate need of a pipe shutdown and cut and replace. WP
5
igs
Products
Foam Pigs
Steel Pigs
Cups and Discs
Brushes and Blades
Solid
arte aeo)
eee ee ay
eae eee LEI
(ee ene ert ia alice Reel
Making the world a cleaner place...
One pipeline at a time.”
Services
Pipeline Cleaning
Pig Tracking
Trouble-shooting
Training Seminars
pices
Werte)
www.pigsunlimited.com