Professional Documents
Culture Documents
Design of The Mechanical Ventilation System of A Building Using Computer Aided Design Software and Building Information Modeling Software
Design of The Mechanical Ventilation System of A Building Using Computer Aided Design Software and Building Information Modeling Software
REGISTRATION NO.
1. Francis Lesindamu
2. Elizabeth Koske
3. Godfrey Muhinda
F18/36636/2010
F18/36478/2010
F18/35663/2010
DECLARATION
We declare that this work submitted as our Final year project is our original efforts and to the
best of our knowledge, has never been presented anywhere before for academic purposes.
ABSTRUCT
Mechanical ventilation systems are designed with the sole purpose of providing proper room
comfort conditions for people within a particular room or space. The approach or methods used
to design these systems have several stages within them, each leading to the next.
This is a building services design project which was intended to design the Mechanical
Ventilation system for a commercial building, using two alternative methods, namely traditional
manual system, and a computer based Building information modeling software.
The traditional approach involved several manual calculations, use of charts and catalogues
developed by manufacturers. In this process, the space to be ventilated was first identified from
the architectural drawings. This was followed by cooling loads analysis using the Cooling Load
Temperature Difference (CLTD) method which aided in obtaining the amount of supply air
needed for each space for comfort conditions. The elements of the mechanical ventilation system
are then listed. The elements are then selected and sized based on the cooling loads analysis.
These were the ductwork, duct accessories (dampers and filters), diffusers, and the ventilation
system equipment (fan coil system). Finally, a final list of design specifications and detailed
drawings were produced. All this steps were followed to the letter in chapter 3, using ground
floor dimensions and characteristics of the materials used for the sample calculations. The
method was then repeated for the subsequent floors and the results were put down from chapter 4
to chapter 7 with each chapter representing a specific floor.
Once the traditional approach was complete, the process moves to the Building Information
Modeling approach. In this stage, which was well captured in chapter 8, a model was created
from the architectural plans provided and thereafter prepared for the heating and cooling loads
analysis. The loads are calculated and are tabulated in a heating and cooling loads report.
Equipment selection and sizing was based on the loads report. The elements of the system were
modeled and detailed. Estimation of the quantities of the elements was done by extracting
information from the completed model through the preparation of schedules. A list of design
specifications was developed from these schedules.
Upon completion, the two approaches were compared based on the following; analysis in the two
processes, scheduling and quantity take offs, change propagation, detailing of the final designs,
conflict detection and visualization of the final design.
ii
ACKNOWLEDGEMENTS
This project is made possible through the help and support from everyone, including: lecturers,
parents, family and friends, and in essence all sentient beings. Especially, please allow us to
dedicate our acknowledgement of gratitude towards the following significant advisors and
contributors.
First and foremost, we would like to give special thanks to our project supervisor, Eng. G.O.
Nyangasi for his guidance and continued support throughout this project. His invaluable insight
was of great importance towards achieving our goals.
Second, we would also like to appreciate Prof. F.M. Luti for the advice he provided us on
Mechanical ventilation system design and also teaching us the core units of the project which
were Thermodynamics, Heat transfer, Air-conditioning and Refrigeration.
Finally, we sincerely thank our parents who provided us with the financial support. The product
of this project would not be possible without all of them.
iii
Table of Contents
SUMMARY .................................................................................................................................... ii
ACKNOWLEDGEMENTS ........................................................................................................... iii
CHAPTER ONE ........................................................................................................................... 1
INTRODUCTION .......................................................................................................................... 1
1.1 BACKGROUND OF THE PROJECT .................................................................................. 1
1.2 STATEMENT OF THE PROBLEM .................................................................................... 1
1.3 OBJECTIVES OF THE PROJECT ...................................................................................... 2
1.4 JUSTIFICATION OF THE PROJECT ................................................................................. 2
1.5 SCOPE OF THE PROJECT.................................................................................................. 2
1.6 LIMITATIONS OF THE PROJECT .................................................................................... 3
CHAPTER TWO .......................................................................................................................... 4
LITERATURE REVIEW ............................................................................................................... 4
2.1 TRADITIONAL APPROACH ............................................................................................. 4
2.2 BUILDING INFORMATION MODELING ........................................................................ 5
CHAPTER THREE ...................................................................................................................... 6
MECHANICAL VENTILATION SYSTEM DESIGN: TRADITIONAL APPROACH .............. 6
3.1 SELECTION OF A DETAILED AND COMPLETE ARCHITECTURAL DRAWING 6
3.2 MECHANICAL VENTILATION CODES AND STANDARDS OF PRACTICE ......... 6
3.3 COOLING LOADS ANALYSIS ...................................................................................... 6
3.4 SYSTEMS SELECTION ................................................................................................ 24
3.5 EQUIPMENT SELECTION AND SIZING.................................................................... 25
3.6 FINAL LIST OF DESIGN SPECIFICATIONS ............................................................. 33
CHAPTER FOUR ....................................................................................................................... 34
MEZZANINE FLOOR ................................................................................................................. 34
4.1 EXTERNAL LOAD CALCULATIONS ............................................................................ 34
4.2 INTERNAL LOAD CALCULATIONS ............................................................................. 35
4.3 EQUIPMENT SELECTION AND DUCT SIZING ........................................................... 36
4.3.0 SUPPLY AIR CALCULATION .................................................................................. 36
4.3.1 DIFFUSER LOCATION SELECTION AND SIZING ............................................... 37
4.3.2 DUCT LAYOUT DESIGN AND DETAILED DRAWING ....................................... 37
iv
CHAPTER ONE
INTRODUCTION
1.1BACKGROUND OF THE PROJECT
Ventilating is the process of changing or replacing air in any space to provide high indoor air
quality, i.e. temperature is controlled, oxygen is replenished, moisture, smoke, heat, carbon
dioxide, air bone bacteria and odors are removed, and basically what happens is that the interior
air is in constant circulatory motion preventing the air from stagnating. Ventilation is one of the
most important factors for maintaining acceptable indoor air quality in buildings.
This project, which is based on Mechanical Ventilation, describes the design process involved to
come up with this system. Two approaches were adopted for this process, the traditional
approach that pertains to the use of Computer Aided Design (CAD) software for drawing and
detailing purposes and the Building Information Modeling (BIM) approach which is a semiautomated approach for the design.
Building Information Modeling is an intelligent model-based process that provides insight to
help one plan, design, construct, and manage buildings. It has been in use for several years and
the other nations have put the traditional approach aside and are now adopting this new
revolutionary technology in their designs. This is one of the reasons that inspired the project. The
BIM methodology offers dramatic new benefits to students that learning institutions have begun
to discover, but it also will likely trigger trade-off considerations for traditional skills that might
be lost.
Giving the right information to the right people at the right time therefore helping firms
to innovate and compete.
In building and design it helps in articulating ones design vision and delivers an
optimized engineering system.
It helps in giving better alignment in construction planning with performance.
In infrastructures it helps to streamline the planning and design and delivers high quality
projects.
It also improves efficiency and meets expectations for service quality.
In the design process we first started with the traditional approach followed by the BIM.
The first step in the traditional approach was the performance of a heating and cooling loads
analysis based on the architectural plans provided using the cooling load temperature difference
method. The loads were manually calculated for the all floors i.e.
The CLTD method was chosen over other methods due to its simplicity and after an accurate
estimate of the cooling loads was complete, an appropriate system, the fan-coil system was then
selected.
CHAPTER TWO
LITERATURE REVIEW
2.1 TRADITIONAL APPROACH
The traditional bit of the design is composed mainly of 2D AutoCAD drawings, manual
calculations, heating and cooling loads calculations, the sizing of the equipment, which was
generally done manually. Design Engineers using the traditional approach in designing a
mechanical ventilation system , use several manuals to guide them in their design to ensure they
come up with systems that are : environmental friendly, economical ,up to the set standards,
efficient et cetera. Most manuals and publications used in the design stage are generated from
one source and that source is The American Society of Heating, Refrigerating and AirConditioning Engineers.
The American Society of Heating, Refrigerating and Air- Conditioning Engineers is the worlds
foremost technical society in the fields of heating, ventilation, air conditioning, and refrigeration.
Its members worldwide are individuals who share ideas, identify needs, support research, and
write the industrys standards for testing and practice. The result is that engineers are better able
to keep indoor environments safe and productive while protecting and preserving the outdoors
for generations to come.
The first step during the design process is the Calculations of the heating and cooling loads,
which is done with the help of The 2009 ASHRAE HandbookFundamentals and ASHRAE
1997 Fundamentals, Chapter 28. This chapter comprises of calculating air-conditioning cooling
load for sizing cooling equipment and a general procedure for calculating heating load, for
nonresidential applications. In addition, the fundamental principles for calculating heating loads
are presented as a counterpart to cooling load calculation. The heat balance approach is a
fundamental concept in calculating cooling loads. While generally cumbersome for widespread
or routine use, this underlying concept is the basis for each of the three simplified procedures
outlined for varying purposes. The cooling calculation procedure most closely approximating the
heat balance concept is the transfer function method (TFM), first introduced in the 1972
ASHRAE Handbook of Fundamentals. This computer-based procedure takes place in two steps,
first establishingthe heat gain from all sources and then determining the conversion of such heat
gain into cooling load.
The second step in the design process is the system selection which is selected by the use of
ASHRAE 2008-Systems and Equipment Chapters 1 through 5.Chapter 1 addresses procedures
for selecting the appropriate system for a given application while taking into account pertinent
issues associated with designing, building, commissioning, operating, and maintaining the
system. It also describes and defines the design concepts and characteristics of basic HVAC
systems. Chapters 2 to 5 describe specific systems and their attributes, based on their heating and
cooling medium and commonly used variations, constructability, commissioning, operation, and
maintenance.
4
CHAPTER THREE
MECHANICAL VENTILATION SYSTEM DESIGN: TRADITIONAL
APPROACH
Mechanical ventilation system design that is carried out in industry mainly constitutes of a
number of commonly used steps that were adopted in this project in order to fulfill the process.
For this stage, the steps listed were as follows:
I. Selection of a detailed and complete architectural drawing.
II. Mechanical ventilation codes and standards of practice.
III. Cooling loads analysis.
IV. Systems analysis and selection.
V. Equipment selection and duct sizing.
VI. Final list of design specifications.
The most commonly used method to perform the analysis is the heat balance method and radiant
time series method. Due to the complexity of the aforementioned methods, it is thus mandatory to
employ the use of computer software to perform the analysis. Such considerations hope to
eliminate the errors that might be brought about by manual approaches. The use of software
serves as a way in which to save time from performing tediously long calculations that may be of
an hour by hour basis. In order to have an exact feel of what exactly is involved in the heating and
cooling loads analysis, the use of software to perform the analysis was done in the later stages and
shall be revealed in the chapters to come. A manual calculation method, which is the Cooling
Load Temperature difference, was selected due to its simplicity and ease of application to perform
the analysis. This method is strictly employed for manual calculations.
PEAK LOAD COMPUTATION
The heating and cooling loads for any building vary over a 24-hr basis and all year round. The
governing factor behind this is the climate of the area where the building is located. The climate
influences the time within which the loads will be at their highest. The accurate determination of
the equipment required to meet these loads is dependent on the period of the highest loads/peak
loads. HVAC design therefore requires that a proper analysis is done over several different times
of day and several different months in order to estimate the period of peak load time in a specific
geographical location. The particular day and month are often dictated by peak solar conditions.
3.3.1INITIAL DESIGN CONSIDERATIONS
Performance of a cooling loads analysis requires that all data pertaining to the buildings
information and characteristics, the outdoor weather data, and indoor weather data be available
prior to the actual analysis. This data must first be assembled before the calculations commence.
DETERMINATION OF THE BUILDING CHARACTERISTICS
Construction Materials
As was mentioned earlier, the architectural drawings provided lacked the information regarding
the building construction materials. The selection of the appropriate material was based on
industry standard practices. The materials listed in the table below were selected from these
standards.
Table 3.1: Construction Materials for the Building
COMPONENT
DESCRIPTION
FACTORS
ROOF
EXTERIOR AND
INTERIOR WALLS
DOORS
FLOOR
CEILING
OFFICE WINDOWS
TOILET WINDOWS
U-Value = 1.8737W/(m2K)
U-Value = 3.8561W/(m2K)
U-Value = 0.54W/(m2K)
U-Value = 3.63W/(m2K)
U-Value = 5.22W/(m2K)
GROUND FLOOR
ORIENTATION
NORTH
SOUTH
EAST
WEST
WALL
22.535m2
39.725m2
62.7 m2
62.7 m2
7.59 m2
WINDOW
DOOR
11.4 m
FENESTRATION
45.73%
CEILING
FLOOR
4.33%
1.8 m
258.967m2
258.967m2
ITEM
DESCRIPTION
LOCATION
University of Nairobi premises, off Harry Thuku road
LATITUDE
1.32S
LONGITUDE
36.92E
ELEVATION
1795m
OUTDOOR WEATHER DESIGN CONDITIONS
The weather data was collected and used as the outdoor design conditions. This data included
values of the dry-bulb, wet-bulb, dew-point temperature and wind speed at various
frequencies of occurrence. The source of the data is the ASHRAE handbook of fundamentals
which makes reference to the Nairobi Meteorological station.
99.6%
9.83
2%
27.27
10
temperature conditions, the relative humidity, and ventilation rate were selected and tabulated.
The optimal thermal conditions were also based on common HVAC industry design practices.
Table 3.8: House Design Conditions.
ITEM
COOLING
LATITUDE &
LONGITUDE
ELEVATION
NOTES
1.32S, 36.92E
1795m
INDOOR DESIGN
TEMPERATURE
23.89C
INDOOR DESIGN
RELATIVE
HUMIDITY
OUTDOOR
DESIGN
TEMPERATURE
50%
DAILY RANGE
13C
OUTDOOR
DESIGN WETBULB
TEMPERATURE
WIND SPEED
15.78C
DESIGN t
4.22C
MOISTURE
DIFFERENCE
0.0083 kgv/kga
VENTILATION
RATE
10L/s
28.11C
3.35 m/s
OPERATING SCHEDULES
This is related to the schedule of lighting, occupants, internal equipment, appliances, and
processes that contribute to the internal thermal load. Based on data relating to Non-residential
buildings, the operating time is assumed to be from 8:00am-6:00pm (still occupied as early as
5:30am to as late as 7:00pm, night work schedule not beyond 10:00 pm).
DATE AND TIME
The time of day and month to do the analysis was selected. The peak load time is determined
from the careful analysis of several different times of day and several different months. The
month selected to perform the analysis was January and the peak time selected between 1200hrs
and 1800hrs.
11
CLTD is the Cooling Load Temperature difference for roof, wall or glass
(dimensionless).
2) Solar load through glass
The equation used for radiant sensible loads from the transparent/translucent elements
such as window glass, skylights and plastic sheets is:
=
Where, A is the area of roof, wall or glass calculated from building plans in m2.
SHGC is the Solar Heat Gain Coefficient (dimensionless).
CLF is the Solar Cooling Load Factor (dimensionless).
SC is the Shading Coefficient (dimensionless).
3) Partitions, ceilings and floors
The equation used for sensible loads from the partitions, ceilings and floors:
=
Where, U is the overall heat transfer coefficient for ceiling assemblies, floors and partition
walls in W/m2K.
A is the area of partition, ceiling or floor calculated from building plans in m2.
Ta is the Temperature of adjacent space in oC.
Trc is the Inside design temperature of conditioned space in oC.
4) Ventilation and infiltration air
The equations used for sensible and latent loads due to ventilation and infiltration air are:
= .
=
= .
Where,Q is the ventilation/Infiltration airflow rate in L/s. Ventilation rate specified from
ASHRAE Standard 62. Infiltration rate calculated from ASHRAE Handbook of
fundamentals.
T is the difference between the inside and outside temperature in C.
W is the difference between the indoor and outdoor air humidity ratio, kg
vapour/kg dry air.
H is the difference between the inside and outside enthalpy, kJ/kg dry air.
All sample calculations highlighted in the following analysis used all the details
of the Ground floor to serve as an example.
LOADS DUE TO ROOFS, EXTERNAL WALLS AND WINDOW
Cooling load due to heat gain through External Walls (Sample Calculation)
Mass
U-Value, W/m2
(kg/m2) K
308
3.32
308
0.68-1.14
308
0.68
200-mm concrete
532
2.78
537
0.65-1.06
537
0.65
762
762
2.39
0.64
B
A
Each layer of the code number has unique thermal characteristics. The overall heat transfer coefficient is calculated from these characteristics.
The above highlighted group corresponds to the wall construction material that was specified in
the table for the building construction material. The walls are therefore GROUP B walls.
NORTH WALL TIME: 1200HRS
From the table of the building size and dimensions, the North wall Area for the ground floor was
determined as 22.535m2.
Value for the CLTD
The cooling load temperature difference, which is the difference between the indoor and outdoor
air temperature while taking into account the solar radiation effects, was determined from tables
of the ASHRAE Handbook of fundamentals.
14
The CLTD (Uncorrected) value for the North Wall orientation for solar time 1200h is: 5
Corrections are made to the CLTD value read from the tables. The following equation applies in
this situation:
=
MONTH
January
NORTH
-1.6
SOUTH
3.8
EAST
-0.5
WEST
-0.5
K, the color adjustment factor, is assumed to be 1 (light colored and in an industrial area).
CLTDCorrected = (5 1.6) 1 + (25.5 23.89) + (25.955 29.4) = 1.61C
=
1.06 * 22.535 * 1.61 = 38.458 W
The heat gain calculated for the Ground floor North facing wall is: 38.458 W
The tables below are a summary of the building heat gains calculated for all the wall orientations.
15
1200
1300
1400
1500
1600
1700
1800
NORTH
38.458
38.458
38.458
38.458
62.37
62.37
86.26
SOUTH
337.34
337.34
379.45
421.56
463.67
505.78
547.88
EAST
512.50
645.42
711.88
711.88
778.34
778.34
844.81
Cooling load due to heat gain through Fenestration Areas (Sample Calculation)
Office Window: Triple glass, 6-mm airspace, Aluminium frame no thermal break, Product type C
U Value = 3.63W/m2K
Toilet window: Double glass, 6-mm airspace, Aluminium frame no thermal break, Product type R
U Value = 5.22 W/m2K
The two kinds of modes that contribute to the cooling load from the fenestration areas are:
1. Conduction heat gain.
2. Solar heat gain.
Conduction heat gain calculations North wall, Time: 1200hrs
Office window fenestration area, A = 7.59m2
U Value = 3.63W/m2K
CLTDUncorrectd for conduction through glass is determined from tables at 1200hrs as: 5
The CLTD value is corrected by +1.61C, the difference between the indoor design air
temperature and 25.5C and by - 3.4C, which is the difference between the outdoor daily average
temperature and 29.4C.
CLTDCorrected = 5 + 1.61 3.4 = 3.21C
Conduction heat gain, Q-conduction = 3.63 * 7.59 * 3.21
143. 54 W
Solar heat gain calculations North wall, Time: 1200hrs
The shading co-efficient, SC, was taken for that of 6-mm clear glass = 0.95
The solar heat gain factor, SHGF, was taken for 0N latitude and the month of January.
SHGF = 107.
The cooling load factor, CLF, was taken at 1200hrs solar time for glass without interior shading.
CLF = 0.69.
Solar heat gain, Q-solar = 7.59 * 0.95 * 107 * 0.69
= 532.35W
The tables below are a summary of the cooling loads due to heat gain caused by the building
fenestration area.
16
SOLAR LOAD
532.35
555.497
555.497
555.497
540.07
540.07
578.643
TOTAL LOAD
620.791
699.037
699.037
726.593
711.166
683.61
722.183
17
Due to the similarity of the office space areas for the floors of the entire building , it was
assumed that the sensible, latent and total heat gain would be the same for all the floors.
The ventilation loads for the entire building was thus as follows:
Total sensible cooling loads = 1920.522 * 5
= 9602.61 W
Total latent cooling loads = 8686.86 * 5
= 43434.3 W
Total heat gain
= 9602.61 + 43434.3
= 53036.91W
LOADS DUE TO INFILTRATION
The infiltration rate was calculated from the formula:
Component
Description
Size or
number
AL per
unit
AL,
cm2
Office window
7.59 m2
3.0
22.77
7.59 m2
1.3
49.335
3.4 m2
27.2
8.24 m2
65.92
11.64 m2
58.2
Framing
Doors
Doors
Framing
18
{ .
Three
0.000435
Three
0.000494
0.000382
0.000271
0.000161
0.000049
Floor
Ground floor
Infiltration rate
(L/s)
13.484
Q-Sensible
(W)
Q-Latent
(W)
Q-Total
(W)
69.99
316.577
386.567
19
3. Appliances
4. Power equipment
The equation used to calculate the heat gain due to people is as follows:
=
Where, Total wattage Input rating from electrical plans or lighting fixture data
CLF is the cooling load factor for lights, by use schedule and hours since on
Note: CLF = 1.0, when cooling system is operated only when lights are on or when lights are on
more than 16hrs per day.
Cooling load due to heat gain from appliances
The equation used to calculate the heat gain due to appliances is as follows:
=
Where, Heat Gain Sensible and latent heat gain from appliances.
CLF is the cooling load factor for appliances.
Note: CLF = 1.0 with 24hr operation or if cooling off at night.
Note: Set latent heat to 0 if appliance under exhaust hood.
Where, CLF is the cooling load factor for power by use schedule and hours since on.
Heat Gain Sensible heat gain from the power equipment.
LOADS DUE TO PEOPLE
From the equations listed above, the cooling loads due to people were calculated. The sensible
and latent heat gains for people were determined from tables obtained from the ASHRAE
20
handbook of fundamentals (2009). The table below shows the rates of heat gain from occupants
from conditioned spaces.(Reference no.3)
The occupied office space was assumed to have moderately active work. The total heat gain
corresponding to this was 140 W for an adult male. The adjusted total heat gain served as the
most suitable value for the calculations and was thus selected. This corresponds to 130 W. The
sensible and latent heats were 75 W and 55 W respectively.
CLF = 1.0, the equipment is assumed to be turned off at night.
Sensible heat gain due to people = N (Sensible heat gain) (CLF)
= 37 * 75
= 2775 W
Latent heat gain due to people = N (Latent heat gain)
= 37 * 55
= 2035 W
Total heat gain due to people
For Ground floor
= 2775 + 2035 = 4810 W
LOADS DUE TO LIGHTING
A prerequisite for the calculation of loads due to lighting is the input rating or the total wattage.
These data is readily available from electrical plans and completed architectural drawings.
However, these data was missing from the drawings provided. The following were assumptions
made during the determination of the total wattage.
Assumption 1: There were 13 light fixtures per 80 m2 with each light fixture holding 2
fluorescent
lamps.
Area per fixture = 80/13 = 6.154 m2/fixture
Area of office space = 258.967 m2 259 m2
Total no. of fixtures in office space = 259/6.154 42 light fixtures.
Total no. of fluorescent lamps = 42 * 2 = 84 fluorescent lamps.
Assumption 2: Wattage for one fluorescent lamp = 36 W
Total wattage for ground floor = 36 * 84 = 3024 W
Assumption 3: Special allowance factor = 1.5
Total wattage * special allowance factor = 3024 * 1.5 = 4536 W
Cooling load factor, CLF = 1.0, cooling off at night.
Loads due to lighting, Q, for each hour of load calculation = 4536 * 1 = 4536 W
LOADS DUE TO APPLIANCES
The equations to be used for appliance loads were
=
1. Desktop computers
2. Monitors
3. Printers
4. Scanners
5. Copy machines
6. Facsimile machines
Offices having computer display terminals at most desks have heat gains ranging up to 47 W/m 2.
This served as the guiding principle on the exact heat gain from the office appliances.
Ground floor area = 259 m2
Total Heat gain due to appliances = 259 * 47 = 12,173 W(Guiding principle)
The details about the appliances were unknown. The following equations for the sensible and
latent heat gains applied.
Sensible heat gain,
Latent heat gain,
=
=
MAXIMUM INPUT
RATING, W
Computer device
1800-4600
1640-2810
Communication/
transmission
1000-10000
1000-6570
Disk drives/Mass
storage
100-600
90-530
Micro-computer
Printers
450
225
Line, low speed
Copiers/Duplicators
460-1700
300-900
Copiers small
3810-17350
3255-11035
Total
Sensible heat gain range, 3566 11986 W
Qs = (3566+11986)/2 = 7776 W
Latent heat gain range, 3255-11035 W
Qs = (3255+11035)/2 = 7145 W
LOADS DUE TO POWER
Type of equipment in the building Elevator Motors.
1640-2810
1000-6570
90-530
376
460-1700
3566-11986
Assumptions.
Nominal
rpm
Full load
motor
efficiency
22.4
1750
89
3-phase
In our calculation motor is in the conditioned space while the driven equipment (elevator) is
outside the conditioned space therefore option C applies.
The sensible cooling load for the motor as presented in the load calculation manual from the
equation,
=
CLF
0.77
0.81
0.83
0.85
0.87
0.89
0.9
Q(W)
2129.05
2239.65
2294.95
2350.25
2405.55
2460.85
2488.50
23
Ground floor
1200hrs
1300hrs
1400hrs
1500hrs
1600hrs
1700hrs
1800hrs
Sensible
Sensible
Sensible
Sensible
Sensible
Sensible
Sensible
Load
(Qs)
Load
(Qs)
Load
(Qs)
Load
(Qs)
Load
(Qs)
Load
(Qs)
Load
(Qs)
Q
Latent
(For all
hours)
Load
(Qs)
People
2775
2775
2775
2775
2775
2775
2775
2035
Lights
4536
4536
4536
4536
4536
4536
4536
N/A
Walls
1267.89
1400.81
1509.39
1551.49
1683.95
1792.52
2057.9
N/A
7776
7776
7776
7776
7776
7776
7776
7145
2129.05
2239.65
2294.95
2350.25
2405.55
2460.85
2488.5
N/A
Infiltration
69.99
69.99
69.99
69.99
69.99
69.99
69.99
316.577
Ventilation
1920.522
1920.522
1920.522
1920.522
1920.522
1920.522
1920.522
9243.71
Windows
620.791
699.037
699.037
726.593
711.166
683.61
722.183
N/A
Total
21095.24 21417.002
21580.9
21705.8
21878.2
22014.5
22346.1
18740.29
Total Load
39835.53
40321.18
40446.14
40618.47
40754.78
41086.39
Equipment/Appliances
Power
40157.3
24
The recommended Tv/L ratio was selected based on the Air Diffusion Performance Index,
which is a number that quantifies the overall comfort of a space when in cooling.
The value for Tv/L for Perforated and louvered ceiling diffusers is 2.0. This value
corresponds to a maximum ADPI of 96.
5. Calculation of the throw distance Tv.
Throw distance,
3.7
4.3
VOLUME
NECK
(L/s)
VELOCITY
(m/s)
354
1.75
351
TOTAL
PRESSURE
(Pa)
10
2.5
21
Sizing of the rest of the elements, which includes the ducts, accessories and mechanical
equipment, used the values of the flow rate tabulated in the above table.
3.5.2DUCT LAYOUT, DESIGN AND DETAILED DRAWING
The duct layout was created from the diffuser layout. Below is a visual representation of the duct
layout for the Ground Floor plan.
There are three commonly used methods for the design of ducts. They are the following:
1. Static regain method.
3. Equal velocity method.
2. Equal friction method.
The most sufficient method of the above was the Equal Friction method. This was used to size
the duct-work. The steps describing this method are as follows:
1. A 1.0Pa per meter rate of frictional drop per meter length was selected and made constant
throughout the system. This value fell within the region of low velocity ducts in the duct
sizing frictional chart.
2. The duct sizing frictional chart was employed to determine the equivalent duct diameter
by using the frictional drop per meter length and a known volumetric flow rate.
3. The equivalent size of rectangular duct was determined as required in the calculations.
The aspect ratio was assumed as 1:1.
4. The corresponding duct velocity was also selected from the duct sizing frictional chart.
The table below is a detailed description of the Ground floor duct sections and their
respective details. The sections are labeled in the detailed AutoCAD drawings attached to
this report.
27
AIR FLOW
RATE (L/s)
1758
EQUIVALENT
DIAMETER (mm)
500 Sq.
VELOCITY
(m/s)
7.5
C
D
354
1404
351
275 x 250
500 x 400
275 x 250
5.1
6.8
5.1
E
F
1053
351
450 x 400
275 x 250
6.5
5.1
G
H
702
351
350 Sq.
275 x 250
5.9
5.1
351
275 x 250
5.1
A
B
For a branch duct of dimensions 275 x 250 mm, airflow rate of 354 L/s, and velocity of 5.1 m/s
the damper area was calculated as,
=
The approach velocity was used to determine the corresponding values for the velocity pressure,
overall pressure drop and the wide open flow coefficient for the damper. They were listed as
follows:
28
2. Dynamic losses.
The equations governing the calculation of the pressure losses are the Darcy, Colebrook and
Altshul Tsal equations.
Static/Frictional Losses
These losses were as a result of the measured straight duct length and were calculated using the
following equation,
Static losses = Frictional drop per meter length * Measured straight duct length.
Dynamic losses
Dynamic losses are brought about by the presence of fittings installed in the duct system. They
were calculated as follows:
1. The velocity through the fittings was determined using the equation
=
=(
.
The pressure loss is then calculated from the equation
=
Where,
Where,
and
are the main and branch loss coefficients (dimensionless).
The total pressure loss in the duct work was determined for the longest run/index run. It
comprised the summation of the:
1. Static/Frictional losses.
2. Dynamic losses.
29
3. Losses due to equipment and accessories namely the diffusers, the dampers and the
filters.
The value for the total pressure loss in the index run was used to select and size the
corresponding fan for the system. The table below is a summary of the pressure loss calculations
for each of the Ground floor duct sections and the overall pressure loss of the index run or
longest run.
Table 3.29: Ground Floor Duct Pressure Loss.
SECTION
ELEMENT
FLOW
(L/s)
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
1758
1758
1758
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
1053
1758
354
354
354
354
1404
1404
1404
1404
351
351
351
351
1053
1053
1053
351
351
351
351
702
702
702
702
351
351
351
VELOCITY
PRESSURE
(Pa)
LENGTH
(m)
LOSS
COEFFICIENT
1.732
9.927
32.898
2.4
2.203
32.898
0.13
1.316
36.186
36.186 Tee
26.356 Elbow
1.94
10.23
0.14 Tee
1.2 Elbow
1.26
26.356
1.94
4.73
26.356
0.13
1.26
23.029
1.62
TOTAL
PRESSURE
(Pa)
1.732
97.1447
9.927
78.96
10
7.47
2.203
4.277
1.316
70.2
21
7.47
10.23
36.693
31.627
1.26
51.131
21
7.47
4.73
3.426
1.26
37.31
21
SECTION
PRESSURE
(Pa)
98.8767
106.357
6.48
99.986
78.55
80.861
8.156
67.04
30
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
351
351
351
23.029 Tee
18.61
Elbow
6.137
7.47
6.137
3.224
22.332
0.14 Tee
1.2 Elbow
351
21
351
7.47
60.163
504
Inlet
Avg db.(A)
Low
Air
Flow
62
High
Air
Flow
61
Outlet
65
64
Nominal
Speed
Rev/Sec
23
PCE..
ER
KW
1 PH
AMP
PCD..
ER
KW
3PH
AMP
PCS/
D
1PH
KW
DD
3PH
KW
1.3
5.7
1.39
2.7
1.5
1.1
31
COILS
Cooling coils are of two types: Direct expansion coils and chilled water coils. A chilled water
coil was use for our design
Assumptions
Selection of the tube size was made depending on the choice of the manufacturer.
Coil sensible heat factor of 0.45.
Methodology
32
5
6
8
9
DESCRIPTION
400 x 500 Ductwork
275 x 250 Ductwork
400 x 450 Ductwork
350 x 350 Ductwork
TRANSITIONS
400 x 500mm
400 x 450mm
350 x 350mm
TEES
400 x 500mm
400 x 450mm
350 x 350mm
ELBOWS
400 x 450mm
275 x 250mm
DIFFUSERS
300 x 300mm
DAMPERS
Area of 0.0694m2
FILTERS
A pressure drop of
97.1447Pa
FANS
Nominal speed of 23rev/s
COOLING COIL
6-rows cooling coil
QUANTITY
2
6
2
1
3
2
2
2
1
1
1
1
7
7
1
1
33
CHAPTER FOUR
MEZZANINE FLOOR
All calculations performed in this chapter followed the procedures described as per Chapter
Three.
1200
1300
1400
1500
1600
1700
1800
NORTH
26.98
26.98
26.98
26.98
43.73
43.73
60.48
SOUTH
280.02
280.02
314.97
349.92
384.88
419.83
454.78
EAST
544.19
685.33
755.91
755.91
826.48
826.48
897.05
SOLAR LOAD
2404.054
2508.517
2508.517
2508.517
2438.835
2438.835
2613.041
TOTAL LOAD
2808.341
3164.699
3164.699
3290.633
3220.951
3095.017
3269.223
Component
Description
Size or
number
AL per
unit
AL,
cm2
Office window
7.59 m2
3.0
22.77
Toilet window
0.96 m2
2.2
2.112
34
cm2/m2 of window
8.55 m2
Framing
TOTAL
LEAKAGE AREA
1.3
11.115
35.997cm2
Floor
Infiltration rate
(L/s)
Mezzanine floor
2.1735
Q-Sensible
(W)
Q-Latent
(W)
Q-Total
(W)
11.282
51.029
62.311
Q-Latent (W)
Q-Total (W)
Mezzanine floor
8686.86
10607.382
Sensible
1920.522
Total loads
= 14921 W
35
CLF
0.77
0.81
0.83
0.85
0.87
0.89
0.9
Q(W)
2129.05
2239.65
2294.95
2350.25
2405.55
2460.85
2488.50
Mezzanine floor
1200hrs
1300hrs
1400hrs
1500hrs
1600hrs
1700hrs
1800hrs
Q
Latent
(For all
hours)
Sensible
Load
(Qs)
Sensible
Load
(Qs)
Sensible
Load
(Qs)
Sensible
Load
(Qs)
Sensible
Load
(Qs)
Sensible
Load
(Qs)
Sensible
Load
(Qs)
Load
(Qs)
People
2775
2775
2775
2775
2775
2775
2775
2035
Lights
4536
4536
4536
4536
4536
4536
4536
N/A
Walls
1254.23
1395.38
1500.9
1535.86
1658.13
1763.66
2027.07
N/A
7776
7776
7776
7776
7776
7776
7776
7145
Infiltration
11.282
11.282
11.282
11.282
11.282
11.282
11.282
51.03
Ventilation
1920.522
1920.522
1920.522
1920.522
1920.522
1920.522
1920.522
9243.71
Windows
2808.281
3164.699
3164.699
3290.633
3220.957
3095.002
3269.208
N/A
Total
21095.24
21592.811
21698.33
21859.23
21911.82
21891.39
22329.01
18474.74
Total Loads
39632.98
40130.551
40236.07
40396.97
40449.56
40429.13
40866.73
Equipment/Appliances
3.7
5.5
VOLUME
NECK
(L/s)
VELOCITY
(m/s)
354
1.75
360
TOTAL
PRESSURE
(Pa)
10
53
AIR FLOW
RATE (L/s)
1782
DIMENSIONS
(mm)
500 x 500
VELOCITY
(m/s)
7.4
B
C
D
1526.3
3657.2
1828.8
354
1428
354
225 x 250
450 x 500
225 x 250
4.5
7.0
4.5
E
F
6429.7
1134.96
1074
354
400 x 450
225 x 250
6.8
4.6
G
H
6458
1099.3
720
360
350 x 400
275 x 275
6.4
4.6
8920.6
360
275 x 275
4.6
Filters
Table 4.11: Details for the filters.
Air velocity for ASHRAE testing
Initial pressure drop
Recommended Final Pressure drop
492 Fpm
97.1447 Pa
348.7245Pa
37
Merv 14
Merv 13
95g
ELEMENT
FLOW
(L/s)
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
1782
1782
1782
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
1074
VELOCITY
PRESSURE
(Pa)
LENGTH
(m)
LOSS
COEFFICIENT
2.88
1782
354
354
354
354
1428
1428
1428
1428
354
354
354
354
1074
1074
1074
354
354
354
354
720
720
720
720
360
360
360
360
1.526
37.627
1.2
3.657
37.627
0.14
1.828
31.804
31.804 Tee
27.418 Elbow
2.4
6.429
0.13 Tee
1.2 Elbow
1.134
27.418
1.2
6.458
27.418
0.13
1.099
19.48
1.2
TOTAL
PRESSURE
(Pa)
2.88
97.1447
1.526
45.152
10
7.47
3.657
5.265
1.828
76.33
10
7.47
6.429
4.131 Tee
32.902
Elbow
1.134
32.902
10
7.47
6.458
3.562
1.099
23.38
53
SECTION
PRESSURE
(Pa)
100.025
64.148
8.922
95.628
43.462
51.506
10.02
84.949
7.47
38
DUCT
FITTINGS
360
360
AIR
TERMINALS
ACCESSORIES
360
2.3
2.532 Tee
21.01
Elbow
53
360
7.47
19.48 Tee
17.511
Elbow
8.921
0.13 Tee
1.2 Elbow
86.312
Model
PCD
PCE
504
Inlet
Avg db.(A)
Low
Air
Flow
62
High
Air
Flow
61
Outlet
65
64
Nominal
Speed
Rev/Sec
23
PCE..
ER
KW
1 PH
AMP
PCD..
ER
KW
3PH
AMP
PCS/
D
1PH
KW
DD
3PH
KW
1.3
5.7
1.39
2.7
1.5
1.1
Cooling coil
Selection procedure for the cooling coil was in accordance to that used for the Ground floor.
The coil performance data was:
39
8
9
DESCRIPTION
500 x 500 Ductwork
450 x 500 Ductwork
400 x 450 Ductwork
350 x 350 Ductwork
275 x 275 Ductwork
225 x 250 Ductwork
TRANSITIONS
500 x 500mm
450 x 500mm
400 x 450mm
350 x 400mm
TEES
500 x 500mm
450 x 500mm
400 x 450mm
350 x 400mm
ELBOWS
400 x 450mm
275 x 275mm
DIFFUSERS
450 x 450mm
300 x 300mm
DAMPERS
Area of 0.0694m2
FILTERS
A pressure drop of
97.1447Pa
FANS
Nominal speed of 23rev/s
COOLING COIL
6-rows cooling coil
QUANTITY
1
1
2
1
3
3
2
2
2
2
1
1
1
1
1
1
3
2
7
1
1
40
CHAPTER FIVE
FIRST FLOOR
All calculations in this chapter followed the procedures developed in Chapter Three.
1200
1300
1400
1500
1600
1700
1800
NORTH
44.99
44.99
44.99
44.99
72.92
72.92
100.85
SOUTH
271.86
271.86
305.80
339.74
373.67
407.61
441.54
EAST
512.50
645.42
711.88
711.88
778.34
778.34
844.81
379.57
1604.5
446.03
1704.9
578.96
1966.16
SOLAR LOAD
2432.676
2613.083
2586.261
2452.145
2233.524
2072.586
2015.624
TOTAL LOAD
2494.864
2698.652
2671.83
2548.68
2330.059
2158.155
2101.193
Component
Description
Size or
number
AL per AL,
unit
cm2
Office window
22.77 m2
3.0
68.31
Toilet window
1.92 m2
2.2
4.224
41
cm2/m2 of window
24.69 m2
Framing
TOTAL
LEAKAGE AREA
6.5
160.485
233.019cm2
Floor
Infiltration rate
(L/s)
First floor
14.063
Q-Sensible
(W)
Q-Latent
(W)
Q-Total
(W)
72.995
330.171
403.166
Q-Latent (W)
Q-Total (W)
First floor
8686.86
10607.382
Sensible
1920.522
Total loads
= 4680
Total loads
= 14921 W
42
CLF
0.77
0.81
0.83
0.85
0.87
0.89
0.9
Q(W)
2129.05
2239.65
2294.95
2350.25
2405.55
2460.85
2488.50
First floor
People
Lights
Walls
Equipment/Appliances
Q
Latent
(For all
hours)
1200hrs
1300hrs
1400hrs
1500hrs
1600hrs
1700hrs
1800hrs
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
4536
4536
4536
4536
4536
4536
4536
1208.707
1341.631
1442.029
1475.965
1604.288
1704.686
1965.934
7776
7776
7776
7776
7776
7776
7776
7145
Load
(Qs)
1980
N/A
Infiltration
Ventilation
72.995
72.995
72.995
72.995
72.995
72.995
72.995
330.171
1920.522
1920.522
1920.522
1920.522
1920.522
1920.522
1920.522
9243.71
Windows
2840.948
3078.628
3045.02
2887.944
2621.827
2409.21
2318.322
Total
21055.17
21425.78
21492.57
21369.43
21231.63
21119.41
21289.77
Total Loads
39754.05
40124.66
40191.45
40068.31
39930.51
39818.29
39988.65
18698.881
43
NUMBER
THROW
(m)
VOLUME
NECK
(L/s)
VELOCITY
(m/s)
281
2
TOTAL
PRESSURE
(Pa)
13
375mm Square
Diffuser
300mm Square
Diffuser
300mm Square
Diffuser
3.7
4.3
270
30
5.2
315
3.5
40
DIMENSIONS
(mm)
450 x 450
VELOCITY
(m/s)
7.2
B
C
D
2400
2300
2750
225
1350
225
275 x 275
450 x 450
275 x 275
5
6.9
5
E
F
2300
2400
1125
225
400 x 400
275 x 275
6.7
5
G
H
2300
2750
900
225
400 x 400
275 x 275
6.4
5
I
J
K
L
M
2300
2400
2300
2750
3400
675
225
450
225
225
300 x 350
275 x 275
275 x 300
275 x 275
275 x 275
5.8
5
5.2
5
5
44
Filters
Table 5.11: Details for the filters.
Air velocity for ASHRAE testing
Initial pressure drop
Recommended Final Pressure drop
Efficiency Rating per ASHRAE 52.2 2007
Efficiency Rating per ASHRAE 52.2 2007 Appendix J
Dust holding capacity at 348.72Pa
492 Fpm
97.1447 Pa
348.7245Pa
Merv 14
Merv 13
95g
ELEMENT
FLOW
(L/s)
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
1575
1575
1575
1575
225
225
225
225
1350
1350
1350
1350
225
225
225
225
1125
1125
1125
1125
225
225
225
225
900
VELOCITY
PRESSURE
(Pa)
LENGTH
(m)
LOSS
COEFFICIENT
7.8
38.665
1.2
2.4
38.665
4.1
2.3
38.665
0.13
2.75
32.104
4.1
2.3
32.104
0.14
2.4
30.084
4.1
2.3
TOTAL
PRESSURE
(Pa)
7.8
46.398
97.1447
2.4
158.52
21
7.47
2.3
5.0265
2.75
131.6264
21
7.47
2.3
4.4946
2.4
123.344
21
7.47
2.3
SECTION
PRESSURE
(Pa)
151.3427
189.39
7.3265
162.8468
6.7946
154.214
6.5118
45
30.084
0.14
4.2118
2.91
2.75
67.3665
21
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
900
900
AIR
TERMINALS
ACCESSORIES
225
21
225
7.47
900
225
225
225
225
675
675
675
675
225
225
225
225
450
450
450
450
225
225
225
225
225
225
2.75
23.15
2.3
23.15
0.15
2.4
25.024
4.1
2.3
25.024
0.13
2.75
20.053
3.36
3.4
20.053 Tee
6.427
Elbow
0.19 Tee
1.2 Elbow
7.47
2.3
3.4725
2.4
102.5984
21
7.47
2.3
3.253
2.75
67.378
21
7.47
3.4
3.81
7.7124
98.5865
5.7725
133.468
5.553
98.598
43.3924
46
Inlet
Avg db.(A)
Low
Air
Flow
59
High
Air
Flow
57
Outlet
61
59
Nominal
Speed
Rev/Sec
Model
PCD
PCE
454
23
PCE..
ER
KW
1 PH
AMP
PCD..
ER
KW
3PH
AMP
PCS/
D
1PH
KW
DD
3PH
KW
0.23
5.5
0.23
0.73
0.75
0.55
Cooling coil
Selection procedure for the cooling coil was in accordance to that used for the Ground floor.
The coil performance data was:
DESCRIPTION
450 x 450 Ductwork
400 x 400 Ductwork
275 x 275 Ductwork
300 x 350 Ductwork
275 x 300 Ductwork
TRANSITIONS
450x450mm
400x400mm
350x300mm
275x300mm
TEES
450x450mm
400x400mm
350x300mm
275x300mm
ELBOWS
QUANTITY
2
2
7
1
1
4
4
2
2
2
2
1
1
47
6
7
8
9
450x450mm
275x300mm
DIFFUSERS
375x375mm
300x300mm
DAMPERS
Area of 0.0694m2
FILTERS
A pressure drop of
97.1447Pa
FANS
Nominal speed of 23rev/s
COOLING COIL
6-rows cooling coil
1
1
1
4
7
1
1
1
48
CHAPTER SIX
SECOND FLOOR
All calculations in this chapter followed the procedures developed in Chapter Three.
1200
1300
1400
1500
1600
1700
1800
NORTH
44.99
44.99
44.99
44.99
72.92
72.92
100.85
SOUTH
271.86
271.86
305.80
339.74
373.67
407.61
441.54
EAST
512.50
645.42
711.88
711.88
778.34
778.34
844.81
379.57
1604.5
446.03
1704.9
578.96
1966.16
CONDUCTION LOAD
297.50
482.85
1400
1500
1600
1700
1800
482.85
575.53
575.53
482.85
482.85
SOLAR LOAD
2778.73
2993.06
TOTAL LOAD
3076.23
3475.91
2959.45
2791.41
2525.29
2323.64
2232.75
3442.30
3366.94
3100.82
2806.49
2715.60
Component
Description
Size or
number
AL per
unit
AL,
cm2
Office window
22.77 m2
3.0
68.31
Toilet window
1.92 m2
2.2
4.224
49
24.69 m2
Framing
TOTAL
LEAKAGE AREA
6.5
160.485
233.019cm2
Floor
Infiltration rate
(L/s)
Second floor
14.063
Q-Sensible
(W)
Q-Latent
(W)
Q-Total
(W)
72.995
330.171
403.166
Q-Latent (W)
Q-Total (W)
Second floor
8686.86
10607.382
Sensible
1920.522
Latent loads
= 1980 W
Total loads
= 14921 W
50
CLF
0.77
0.81
0.83
0.85
0.87
0.89
0.9
Q(W)
2129.05
2239.65
2294.95
2350.25
2405.55
2460.85
2488.50
Second floor
1200hrs
1300hrs
1400hrs
1500hrs
1600hrs
1700hrs
1800hrs
People
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Lights
4536
4536
4536
4536
4536
4536
4536
N/A
Walls
1208.921
1476.178
1604.503
1704.9
1966.15
N/A
Equipment/Appliances
1341.845 1442.243
Load
(Qs)
1980
7776
7776
7776
7776
7776
7776
7776
7145
Infiltration
72.995
72.995
72.995
72.995
72.995
72.995
72.995
330.171
Ventilation
1920.522
1920.522 1920.522
1920.522
1920.522
1920.522
1920.522
9243.71
Windows
3076.222
3475.911 3442.303
3366.938
3100.819
2806.491
2715.602
N/A
Total
21290.66
21823.27 21890.06
21848.63
21710.84
21516.91
21687.27
18698.881
Total Loads
39989.54
40522.15 40588.94
40547.51
40409.72
40215.79
40386.15
51
VOLUME
NECK
(L/s)
VELOCITY
(m/s)
246
1.75
TOTAL
PRESSURE
(Pa)
10
3.0
3.7
225
2.5
21
2.7
211
1.5
7.5
DIMENSIONS
(mm)
500 x 500
VELOCITY
(m/s)
7.4
B
C
D
2400
2300
2750
211
1420
211
225 x 250
450 x 450
225 x 250
4.5
7.0
4.5
E
F
2300
2400
1209
246
400 x 500
225 x 250
6.8
4.6
G
H
2300
2750
963
246
400 x 400
225 x 250
6.4
4.6
I
J
K
L
M
2300
2400
2300
2750
3400
717
225
492
246
246
350 x 350
225 x 250
300 x 300
225 x 250
225 x 250
5.9
4.5
5.4
4.5
4.5
52
Filters
Table 6.11: Details for the filters
Air velocity for ASHRAE testing
Initial pressure drop
Recommended Final Pressure drop
Efficiency Rating per ASHRAE 52.2 2007
Efficiency Rating per ASHRAE 52.2 2007 Appendix J
Dust holding capacity at 348.72Pa
492 Fpm
97.1447 Pa
348.7245Pa
Merv 14
Merv 13
95g
ELEMENT
FLOW
(L/s)
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
1631
1631
1631
1631
211
211
211
211
1420
1420
1420
1420
211
211
211
211
1209
1209
1209
1209
246
246
246
246
963
963
963
VELOCITY
PRESSURE
(Pa)
LENGTH
(m)
LOSS
COEFFICIENT
7.8
34.11
1.2
2.4
31.421
4.1
2.3
31.421
0.13
2.75
27.964
2.4
2.3
27.964
0.13
2.4
29.025
0.13
2.3
29.025
2.4
TOTAL
PRESSURE
(Pa)
7.8
40.924
97.1447
2.4
139.824
7.5
7.47
2.3
4.433
2.75
75.411
7.5
7.47
2.3
4.085
2.4
67.11
10
7.47
2.3
3.635
SECTION
PRESSURE
(Pa)
145.869
157.194
6.733
93.131
6.385
86.98
5.935
53
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
963
246
246
246
246
717
717
717
717
225
225
225
225
492
492
492
492
246
246
246
246
246
246
246
2.75
22.789
1.94
2.3
22.789
0.13
2.4
19.879
1.94
2.3
19.879
0.14
2.75
13.939
1.62
3.4
13.939
0.14
246
2.75
56.31
10
7.47
2.3
3.77
2.4
44.21
21
7.47
2.3
3.19
2.75
32.2
10
7.47
3.4
19.51
10
76.53
6.07
75.08
5.49
52.42
40.38
7.47
54
454
Inlet
Avg db.(A)
Low
Air
Flow
59
High
Air
Flow
57
Outlet
61
59
Nominal
Speed
Rev/Sec
23
PCE..
ER
KW
1 PH
AMP
PCD..
ER
KW
3PH
AMP
PCS/
D
1PH
KW
DD
3PH
KW
0.23
5.5
0.23
0.73
0.75
0.55
Cooling coil
Selection procedure for the cooling coil was in accordance to that used for the Ground floor.
The coil performance data was:
DESCRIPTION
500 x 500 Ductwork
450 x 450 Ductwork
400 x 500 Ductwork
400 x 400 Ductwork
350 x 350 Ductwork
300 x 300 Ductwork
225 x 250 Ductwork
TRANSITIONS
500 x 500mm
450 x 450mm
400 x 500mm
400 x 400mm
350 x 350mm
300 x 300mm
TEES
QUANTITY
1
1
1
1
1
1
7
2
2
2
2
2
2
55
8
9
500 x 500mm
450 x 450mm
400 x 500mm
400 x 400mm
350 x 350mm
300 x 300mm
ELBOWS
500 x 500mm
225 x 250mm
DIFFUSERS
375 x 375mm
300 x 300mm
DAMPERS
Area of 0.0694m2
FILTERS
A pressure drop of
97.1447Pa
FANS
Nominal speed of 23rev/s
COOLING COIL
6-rows cooling coil
1
1
1
1
1
1
1
1
6
1
7
1
1
56
CHAPTER SEVEN
THIRD FLOOR
All calculations in this chapter followed the procedures developed in Chapter Three.
1200
1300
1400
1500
1600
1700
1800
NORTH
44.99
44.99
44.99
44.99
72.92
72.92
100.84
SOUTH
271.86
271.86
305.80
339.74
373.67
407.61
441.54
EAST
512.50
645.42
711.88
711.88
778.34
778.34
844.81
. ]
57
CLTD
(Corrected)
C
8.003
Q Heat gain
(W)
1200
CLTD
(Uncorrected)
C
13
1300
14
8.783
1049.59
1400
15
9.533
1139.22
1500
16
10.283
1228.85
1600
17
11.033
1318.48
1700
18
11.783
1408.104
1800
18
11.783
1408.104
959.967
CONDUCTION LOAD
297.50
482.85
1400
1500
1600
1700
1800
SOLAR LOAD
2778.73
2993.06
TOTAL LOAD
3076.23
3475.91
482.85
575.53
575.53
482.85
2959.45
2791.41
2525.29
2323.64
3442.30
3366.94
3100.82
2806.49
482.85
2232.75
2715.60
Component
Description
Size or
number
AL per
unit
AL,
cm2
Office window
22.77 m2
3.0
68.31
Toilet window
1.92 m2
2.2
4.224
24.69 m2
6.5
160.485
Framing
TOTAL
LEAKAGE AREA
233.019cm2
58
Floor
Third floor
Infiltration rate
(L/s)
14.063
Q-Sensible
(W)
Q-Latent
(W)
Q-Total
(W)
72.995
330.171
403.166
Q-Latent (W)
Q-Total (W)
Third floor
8686.86
10607.382
Sensible
1920.522
Total loads
= 14921 W
LOADS DUE TO POWER
Table 7.7: Power loads
TIME
HOURS AFTER EQUIPMENT IS ON
4
1200
5
1300
6
1400
7
1500
8
1600
9
1700
10
1800
Latent loads
= 7145 W
CLF
0.77
0.81
0.83
0.85
0.87
0.89
0.9
Q(W)
2129.05
2239.65
2294.95
2350.25
2405.55
2460.85
2488.50
59
Third floor
Q
Latent
(For all
hours)
1200hrs
1300hrs
1400hrs
1500hrs
1600hrs
1700hrs
1800hrs
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
Sensible
Load
(Qs)
2700
4536
4536
4536
4536
4536
4536
4536
N/A
Walls
1208.92
1341.845
1442.243
1476.178
1604.503
1704.9
1966.15
N/A
Roof
959.97
1049.59
1139.22
1228.85
1318.48
1408.104
1408.104
N/A
Equipment/Appliances
7776
7776
7776
7776
7776
7776
7776
7145
Infiltration
72.99
72.99
72.995
72.995
72.995
72.995
72.995
330.171
Ventilation
1920.52
1920.52
1920.52
1920.52
1920.52
1920.52
1920.52
9243.71
Windows
3076.22
3475.911
3442.303
3366.938
3100.819
2806.491
2715.602
N/A
Total
22250.6
22872.8
23029.3
23077.5
23029.32
22925.01
23095.37
18698.88
Total Loads
40949.51
41571.7
41728.16
41776.36
41728.2
41623.9
41794.25
People
Lights
Load
(Qs)
1980
3.7
VOLUME
NECK
(L/s)
VELOCITY
(m/s)
225
2.5
TOTAL
PRESSURE
(Pa)
21
60
DIMENSIONS
(mm)
500Sq.
VELOCITY
(m/s)
7.5
C
D
2400
2300
2750
225
1483.3
225
275Sq.
450Sq.
275Sq.
5
6.9
5
E
F
2300
2400
1258.3
225
450Sq.
275Sq.
6.8
5
G
H
2300
2750
1033.3
225
400Sq.
275Sq.
6.6
5
I
J
K
L
M
2300
2400
2300
2750
3400
808.3
225
583.3
225
225
350x400
275Sq.
300x350
275Sq.
275Sq.
6.2
5
5.8
5
5
Filters
Table 7.12: Details for the filters
Air velocity for ASHRAE testing
Initial pressure drop
Recommended Final Pressure drop
Efficiency Rating per ASHRAE 52.2 2007
Efficiency Rating per ASHRAE 52.2 2007 Appendix J
Dust holding capacity at 348.72Pa
492 Fpm
97.1447 Pa
348.7245Pa
Merv 14
Merv 13
95g
61
ELEMENT
FLOW
(L/s)
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
1708.3
1708.3
1708.3
1708.3
225
225
225
225
1483.3
1483.3
1483.3
1483.3
225
225
225
225
1258.3
1258.3
1258.3
1258.3
225
225
225
225
1033.3
1033.3
1033.3
1033.3
225
225
225
225
808.3
808.3
808.3
808.3
225
225
225
VELOCITY
PRESSURE
(Pa)
LENGTH
(m)
LOSS
COEFFICIE
NT
7.8
30.62
1.2
2.4
30.62
2.4
2.3
30.62
0.14
2.75
40.3572
4.1
2.3
40.3572
0.14
2.4
31.6
4.1
2.3
31.6
0.14
2.75
25.38
4.1
2.3
25.38
0.13
2.4
22.53
2.9
TOTAL
PRESSURE
(Pa)
7.8
36.745
97.1447
2.4
73.488
21
7.47
2.3
4.2868
2.75
165.46
21
7.47
2.3
5.65
2.4
129.59
21
7.47
2.3
4.424
2.75
104.058
21
7.47
2.3
3.2994
2.4
65.337
21
SECTION
PRESSURE
(Pa)
141.6897
104.358
6.5868
196.68
7.95
160.46
6.724
135.278
5.5994
96.207
62
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
DUCT
FITTINGS
AIR
TERMINALS
ACCESSORIES
225
583.3
583.3
583.3
583.3
225
225
225
7.47
2.3
3.1542
2.3
22.53
0.14
4.1
2.75
83.845
21
0.14 Tee
1.2 Elbow
225
7.47
3.4
2.863
18.525
21
225
7.47
225
225
225
2.75
13.939
13.939 Tee
15.44 - Elbow
3.4
5.4542
115.065
53.258
454
Inlet
Avg db.(A)
Low
Air
Flow
59
High
Air
Flow
57
Outlet
61
59
Nominal
Speed
Rev/Sec
23
PCE..
ER
KW
1 PH
AMP
PCD..
ER
KW
3PH
AMP
PCS/
D
1PH
KW
DD
3PH
KW
0.23
5.5
0.23
0.73
0.75
0.55
Cooling coil
Selection procedure for the cooling coil was in accordance to that used for the Ground floor.
The coil performance data was:
63
5
6
8
9
DESCRIPTION
500 x 500 Ductwork
450 x 450 Ductwork
400 x 400 Ductwork
350 x 400 Ductwork
300 x 350 Ductwork
275 x 275 Ductwork
TRANSITIONS
500 x 500mm
450 x 450mm
400 x 400mm
350 x 400mm
300 x 350mm
TEES
500 x 500mm
450 x 450mm
400 x 400mm
350 x 400mm
300 x 350mm
ELBOWS
500 x 500mm
275 x 275mm
DIFFUSERS
300 x 300mm
DAMPERS
Area of 0.0694m2
FILTERS
A pressure drop of
97.1447Pa
FANS
Nominal speed of 23rev/s
COOLING COIL
6-rows cooling coil
QUANTITY
1
2
1
1
1
7
2
4
2
2
2
1
2
1
1
1
1
1
7
7
1
1
64
CHAPTER EIGHT
BUILDING INFORMATION MODELING
The completion of the traditional approach leads to the next phase of the design project which
was design using building information modeling software. In this stage of the design, various
methods that were used earlier in the traditional approach were borrowed as they proved useful
in enhancing the BIM process. Building information modeling software was revealed as a semi
automated software that brings together both the human mind and the computer software to
achieve the design goals. The design procedure followed in the approach was:
1. Selection of a completed detailed Architectural drawing.
2. Acquisition of the necessary mechanical ventilation codes and standards of practice.
3. Project initiation using Autodesk Revit software.
4. Preparation of the modeling plans.
5. Design of the mechanical ventilation system.
6. Scheduling and quantity take offs.
7. Final list of design specifications.
65
67
68
ZONE CREATION
Creating HVAC zones within a building allows one to control the airflow to given spaces, shut
off airflow to areas that are not occupied, or increase airflow to spaces when the space load
increases via a signal form a temperature sensor or other sensing device within the zone to a
central control panel.
8.5.0.4 GENERATION OF A SPACE PROPERTIES SCHEDULE
A schedule of the space properties was generated with the sole purpose of keeping track of all
the information concerning each of the spaces. The fields selected for this schedule were:
1. Name Designates the space name e.g. OFFICE, RESTROOM, e.t.c.
2. Number Assigns the space a number.
3. Space Type Describes how the space will be used e.g. office, restroom, e.t.c.
4. Number of people Specifies the space occupancy.
5. Construction Type Displays the construction data of the building.
6. Area The area of the occupied space.
7. Volume The volume of the occupied space.
8. Occupiable A check box used to show whether a room can be occupied or not.
9. Condition Type Displays whether the space is cooled, heated and cooled, unconditioned,
vented and naturally vented only.
The schedule was generated upon finalizing on the selected fields. The schedule created was
named Space Schedule 1 shown in Fig. 8.7.
70
Service type There are four main groups of systems in the software to choose from:
Constant Volume, Variable Air Volume, Hydronic and Other. These four groups have
several system variations. Knowledge on these system variations was retrieved from the
71
systems analysis and selection that was performed earlier on. The service type selected for
each zone was the Fan-Coil system.
2.
Coil Bypass Information concerning the manufacturers coil by pass factor for the unit
serving the zone is also modified. The default value, zero, was used.
3.
Cooling Information All information regarding the desired interior thermal conditions
for cooling is modified. The parameters that were set are as follows:
4.
5.
Report type Refers to the detail level of the report. Three levels are available for
selection:
o Simple, which contains summary data for systems, zones, and spaces.
o Standard, which expands the simple report to include psychrometric data as well
as building level summaries and load summary data for each space.
o Detailed, which further expands the data displayed to include the individual
components contributions to zone and space loads.
The report type chosen was Standard.
Load credits These are negative load values that come from heat entering or leaving a
space through a partition into another zone. It can be included in the calculation by
checking the box next to it or ignored. For the cooling loads analysis, the checkbox was
left unchecked i.e. it was ignored.
74
Once this is done, the diffusers are then placed in their required positions. This is achieved by
first linking the finished cad drawing the same way as it was done during the building modeling
process and the diffusers placed according to the linked drawing. This can be seen in the
drawings appended to this report.
particular floor. These two values need to be accurate to ensure the schedule sheets produce the
accurate information concerning the equipment selection and sizing.
The steps followed in the creation of the schedule was somewhat similar to that used to create
the space properties schedule. The schedules created were for the Mechanical elements in the
model which include the following.
Ducts.
Duct fittings and Accessories.
Duct systems.
Mechanical Equipment.
The above list was used to create five separate schedules that each describe the Mechanical
ventilation system. A number of different fields were selected to be displayed on these schedules.
A section of the schedule on the ducts is as shown below.
78
CHAPTER NINE
EVALUATION AND COMPARISON
9.1 ANALYSIS OF THE TWO PROCESSES
This analysis is based on the outcome of the final heating and cooling loads analysis. In the
case of the traditional approach, all the factors that affect the load analysis were determined
and calculated manually. The sensible heat gains which comprises of the solar gain through
the building envelope, solar heat gain by direct or indirect solar radiation through windows or
other fenestration materials et cetera. Aforementioned loads are also grouped in terms of
external and internal loads, external loads being; conduction through glass, solar load through
glass et cetera and the internal loads being comprised of people, lighting, appliances and
power equipment. All these loads were calculated, and tabulated for each floor. The
calculations were done as per the month of January which according to the climatic data used
is the hottest month of the year. The calculations were also done for different times of day to
determine the hour with the highest load. These hours were from 1200hrs to 1800hrs. Once
completed, the peak cooling load for all floors was at 1800hrs and was found to be
204.122kW.
In the BIM approach, analysis was done by linking the 2D AutoCAD drawings with the
Revit software, creating a 3D virtual model from these plans then putting in place the
windows and doors that matched the ones selected during the traditional approach. Once all
this was done and the spaces to be conditioned were identified, the software did the
calculations using the Radiant time series method (RTS) which is a simplification of the heat
balance method. The results were presented as a report for each zone having its own peak
load, all this peak loads were therefore summed up and the result was found to be 98.451kW.
The difference in the peak cooling loads of the two processes is 105.671kW. This difference
is very huge, indicating the presence of errors in the traditional approach. This could later on
lead to oversizing of the equipment. The traditional approach was very cumbersome
compared to the BIM approach, and yet the results are not very accurate.
80
have a slight effect on their original designs. Further information on the linking process was
made available in this report.
81
82
Using the rendering capability of Revit, designers, architects and engineers can generate
images to communicate their design intent more clearly to clients and other members of their
design team.
On the other hand, AutoCAD often relies on envisioning the building based on orthogonal
drawings or a small scale physical model. Visualization such as these can be hampered by the
viewers ability to mentally interpret 2D drawings.
83
measure thus saving on costs that would have been spent on dealing with these
problems.
5. Easy scheduling, quantity take-offs and preparation of the design specifications. The
aforementioned tasks that were conducted involved the automatic preparation of
simple schedules which had all the data for the system. These schedules enabled
preparation of the design specifications.
APPENDIX
Information to be included in the appendix can only be found in the hard copy format of the
report due to the difficulty to attach it in this word document.
84
Bibliography
1.
2.
3.
American Society of Heating Refrigeration and Air-conditioning Engineers. (1997). Nonresidential cooling and heating load calculations. In A. S.-c. Engineers, 1997 ASHRAE
Handbook of Fundamentals (pp. 28-28.64). American Society of Heating Refrigeration
and Air-conditioning Engineers.
4.
5.
6.
7.
8.
9.
ASHRAEwebsite:
https://www.ashrae.org/file%20library/doclib/public/200418145036_347.pdf.
10. Anonymous. (2013). Designing buildings: Constant Air Volume. Retrieved February 2015,
from Designing buildings:
www.designingbuildings.co.uk/wiki/Constant_air_volume_CAV
11. Anonymous. (2013). Engineering guidelines. Retrieved February 2015, from Buildiste Web
site:
http://www.buildsite.com/pdf/titus/Titus-Engineering-Guidelines-Grilles-andDiffusers-Engineering-Data-B13269.pdf
12. Anonymous. (2013). Grilles and Diffusers. Retrieved January 2015, from AirTag website:
http://airtag.com.au/wp-content/themes/airtag/pdf/Grilles-Diffusers-ManufacturedRange.pdf
13. Anonymous. (2013). Heating and Cooling Load calculation methods in Revit MEP.
Retrieved
December
2014,
from
Inside
the
system:
http://inside-thesystem.typepad.com/files/rme_calc_heating_cooling-1.pdf
14. Anonymous. (2013). Square and Rectangular louvre face ceiling diffuser catalogue.
Retrieved
January
2015,
from
Air
diffusion
website:
http://www.airdiffusion.co.uk/PDF/modelsa.pdf
15. Anonymous. (2013). Understanding and using the HVAC design review form. Retrieved
December
2014,
from
ACCA
Web
site:
http://www.acca.org/wpcontent/uploads/2014/01/HVAC-Design-Review-Form-Instructions-4-10.pdf
16. Anonymous. (2014). R-Values of insulation and other building materials. Retrieved
September
2014,
from
ArchToolbox:
http://www.archtoolbox.com/materialssystems/thermal-moisture-protection/rvalues.html
17. Autodesk. (2014). BIM Deployment Plan. Retrieved July 30, 2014, from Akcb:
http://www.akcb.com/attachments/bim_deployment_plan_final.pdf
18. Bhatia, A. (2012). A Guide to Heating and Cooling load Estimation. Retrieved July 30, 2014,
from PDH Online: http://www.pdhonline.org/courses/m196/m196content.pdf
19. Brooks, P. J. (2013). ASHRAE BOOKSTORE. Retrieved February 2015, from ASHRAE
BOOKSTORE: http://ashrae.org/ASHRAE-D-AJ10Jan05-20091230.pdf
20. C, D. S. (2013). Air side systems: Air Duct Design. Retrieved August 2014, from Mech.
Hong Kong University: http://www.mech.hku.hk/bse/bbse3006/bbse3006_1011_03airside03.pdf
86
21. Faye, C. M., Jerald, D. P., & Jeffrey, D. S. (2005). Heating, Ventilating and Air-conditioning
analysis and design. In C. M. Faye, D. P. Jerald, & D. S. Jeffrey, Heating, Ventilating and
Air-conditioning analysis and design. John Wiley & Sons.
22. Fred Hall, R. G. (2011). Ventilation systems. In F. Hall, & R. Greeno, Building services
handbook (pp. 229-264). Elsevier limited.
23. Graphisoft. (2014). About BIM. Retrieved September
http://www.graphisoft.com/archicad/open_bim/about_bim/
2014,
from
Graphisoft:
24. Han Yan, P. D. (2013). Benefits and Barriers of BIM. Retrieved 2014, from homepages:
http://homepages.lboro.ac.uk/~cvpd2/PDFs/294_Benefits%20and%20Barriers%20of%20
Building%20Information%20Modelling.pdf
25. Hergunsel, M. (2013). Thesis on the Benefits of Building Information Modelling. Retrieved
August 2014, from Scribd: http://www.scribd.com/doc/83205152/MHergunsel-ThesisBIM
26. Kenya Vision 2030. (2013). Kenya Vision 2030. Retrieved August 2014, from CBC Global:
http://www.cbcglobal.org/images/uploads/library/KIS2012_Vision_2030_Minister_of_Sta
te_Planning,_National_Development_and_Vision_2030.pdf
27. Lizardos, E., & Elovitz, K. (2000). Damper Sizing Using Damper Authority. ASHRAE
JOURNAL Practical Guide.
28. McDonald, M. (2014). Building Information Modeling. Retrieved August 17, 2014, from
Mott McDonald: https://www.mottmac.com/article/2385/building-information-modellingbim
29. National Concrete Masonry Association foundation. (2014). Thermal Catalogue of Concrete.
Masonry Assemblies. Retrieved September 2014, from Concrete Masonry association of
California: http://cmacn.org/PDF/Thermal_Catalog.pdf
30. Project and construction services. (2014). Building Information Modeling. Retrieved
september 2014, from PCSCMservices: http://www.pcscmservices.com/serBIM.asp
31. Simon, W., Bokmiller, D., & Hristov, P. (2013). Mastering Autodesk Revit. In D. Bokmiller,
S. Whitbread, & P. Hristov, Mastering Autodesk Revit (pp. 237-343). John Wiley and
Sons Inc.
32. Wikipedia. (2014). Project delivery method. Retrieved December 21, 2014, from Wikipedia:
https://www.google.com/webhp?source=search_app&gws_rd=ssl#q=What+is+a+project+
delivery+method
87