MEP Progress 17 Mar
MEP Progress 17 Mar
DATE: 17-Mar-16
Storey
Basement-1
Level 1
ELECTRICAL SYSTEM
(% work done)
95%
81%
ELV SYSTEM
(% work done)
86%
86%
ACMV SYSTEM
(% work done)
86%
77%
BMS SYSTEM
(% work done)
86%
86%
FIRE PROTECTION
(% work done)
95%
95%
PA SYSTEM
(% work done)
89%
83%
P&S
OVERALL
(%)
79%
72%
GAS
95%
80%
95%
95%
80%
80%
89%
83%
76%
77%
86%
80%
81%
72%
Level 3
82%
86%
77%
86%
80%
81%
72%
95%
80%
Level 4
81%
86%
77%
86%
90%
81%
72%
95%
82%
Level 5
82%
86%
77%
86%
90%
81%
72%
95%
83%
Level 6
81%
86%
77%
86%
90%
81%
72%
95%
83%
Level 7
68%
76%
77%
86%
80%
81%
72%
95%
77%
Level 8
59%
62%
77%
86%
69%
81%
0%
95%
64%
Level 9
72%
76%
27%
86%
90%
81%
72%
50%
69%
Level 10
81%
86%
81%
86%
90%
81%
72%
50%
83%
Level 11
81%
86%
81%
86%
95%
81%
68%
50%
84%
Level 12
81%
86%
77%
86%
90%
81%
68%
50%
82%
Level 13
81%
86%
77%
86%
90%
81%
72%
50%
82%
Level 14
81%
86%
63%
86%
85%
81%
72%
50%
78%
Level 15
72%
76%
72%
86%
80%
81%
72%
50%
76%
Level 16
72%
76%
59%
86%
90%
81%
72%
50%
77%
Level 17
41%
76%
63%
81%
84%
81%
68%
50%
70%
Level 18
36%
76%
27%
81%
70%
81%
68%
50%
58%
Level 19
36%
76%
0%
81%
70%
81%
63%
50%
52%
Level 20
36%
76%
0%
81%
50%
81%
59%
50%
45%
Level 21
18%
10%
0%
81%
0%
81%
36%
50%
21%
Level 22
9%
10%
0%
81%
10%
81%
0%
50%
19%
Level 23
0%
0%
0%
81%
0%
72%
0%
50%
13%
62%
0%
71%
18%
56%
0%
84%
10%
73%
0%
81%
20%
60%
50%
OVERALL
(%)
72%
10%
95%
ESC
Level 2
Lower Roof
80%
LIFT
60%
85%
69%
77%
11%
70%
68%
PLANT ROOM
90%
20%
Ejector Pit
20%
90%
HT Switch Room
95%
60%
20%
20%
MDF Room
30%
80%
IT Room
Transformer Room
95%
LV Switch Room
90%
PAHU Room
70%
Chiller Room
80%
Generator Room
60%
85%
70%
FL01 LMR
40%
FL02 LMR
90%
PL05-08 LMR
50%
70%
Fire Pump Rm
50%
30%
Fire Tank
80%
75%
30%