SULE SQUARE

LOWER ROOF WORKS SCHEDULE


LEVEL

Preparation & Structural


Ponding Test (5days)

Waterproof Membrane & Installation of Raw Water


Screeding ( 8days)
Tank (15days)

Area 1 ( XA-XB/Y1-Y5)

10/Feb/16

Done 15/2/16

16/Feb/16

24/Feb/16

Area 2 ( XC-XD/Y1-Y4)

12/Feb/16

Done 17/2/16

18/Feb/16

26/Feb/16

Area 3 ( XC-XD/Y4-Y8)

14/Feb/16

Done 19/2/16

20/Feb/16

28/Feb/16

Area 4 ( XA-XB/Y5-Y8)

20/Feb/16

25/Feb/16

27/Feb/16

6/Mar/16

Area 5 ( XA-XD/Y8-Y10)

22/Feb/16

27/Feb/16

1/Mar/16

9/Mar/16

Prepared by : Zayar Linn

Page 1 of 2

20/Feb/16

6/Mar/16

Installaton of Domestic
Water Tank (15days)

17/Feb/16

PAHU Rooms (3

3/Mar/16

20/Feb/16

Updated as : 18 Feb 2016


PAHU Rooms (30days)

21/Mar/16

Booster / Filtration Room


(30days)

22/Feb/16

23/Mar/16

Fire Pump (Room)


(30days)

24/Feb/16

25/Mar/16

MEP Fans, Pipes & Duct


Installation
(30 days)

29/Feb/16

Page 2 of 2

30/Mar/16

Testing & Commisioning


(60 days)

31/Mar/16

30/May/16

Remark