Professional Documents
Culture Documents
Sedimentation Lecture No. 6 1. Purpose: A. Overall Treatment Process
Sedimentation Lecture No. 6 1. Purpose: A. Overall Treatment Process
Lecture No. 6
1. Purpose
2. Considerations
A. Overall Treatment Process.
If there are big particles in the water, >15um, as might be found in river water, a grit
chamber is in order. A conservatively designed sedimentation basin should be used to
obtain a settle water turbidity of <2NTU. The sedimentation would NOT do it alone,
but in combination with chemicals, filtration etc. In the filter unit, the quality of the
output water is proportional to the quality of the input water. See F.3.2.5-1, p.141.
Example
Given: Final filtered water quality of .5NTU
Find: Water quality of settled.
From: F.3.2.5-1, p.141.
Anywhere from 1-6 units, silica scale
Raw water contains 2 basic types of suspended matter: discrete (nonflocculable) such
as sand and silt and colloidal suspensions such as clay, microorganisms and substances
that cause color.
Discrete particles are relatively easy to remove and removal strategies include: grit
chamber, plain sedimentation, cyclone separator.
Example:
Given: An alum floc
Find: 1.)specific gravity 2.)particle size in mm 3.)If the settling rate is .04fpm, convert this value
to gpm/ft2.
From: T3.2.5-1. p.143.
1.) specific gravity
specific gravity=1.001
2.)particle size in mm
particle size = 1-4mm
3.)If the settling rate is .04fpm, convert this value to gpm/ft 2.
.04ft/min x 7.48gal/ft3 = .30gpm/ft2
V, horizontal
H, inlet
Outlet
H
Vs, settling
Sludge
vs or v0 is the settling velocity of the smallest particle size that is 100% removed.
Removed means captured in the sludge layer. A smaller particle will be lighter and
therefore will settle at a velocity slower than v0. A smaller, slower particle will have a
shallower, less steep slope and be inclined to be removed via the outlet. When such a
light particle, v<v0, starts below the top of the water line at the inlet a portion of such
light particles will be removed. If a particle is heavier than v0, v>v0, its slope will be
steeper than the v0 and 100% of these heavier particles will reach the sludge layer.
Detention time.
t = H/Vs = L/Vh
Vh = L/t
but
Vh = Q/Ax-section
Ax-section = HW
Ax-section =HW
Vh = Q/HW
Substituting
L/t = Q/HW
t = LHW/Q, LHW=V
t = V/Q
Overflow rate
t = H/Vs = LHW/Q
therefore,
Vs = Q/LW, LW=Plan area, Ap, also known as the surface area.
Vs = Q/Ap
Shows that the overflow rate is equivalent to the settling velocity of smallest particle that
is 100% removed.
Example:
Given: 2 tanks, =100, d=10, Q=14MGD
Find: t, OR
1.) t
t = V/Q = 2tanks x 1002 x 10 / 14MG/10 6gal x
t = .08388days = 2.01hours = 120.8min
2.) OR
OR = Q/Ap = 14MGD x 106gal/MG / (2tanks x 100)2
Removal rates
For v>v0, 100% removed
For v<v0, some will be removed, but how much
fraction of particles removed = v1/v0 = H1/H
mathematically,
fraction removed = (1-Xs) +
Xs
vdx
0
(1-Xs) = fraction of the particles with v>v0, all of these particles will be removed.
Xs
vdx
0
fraction of Xs
particles with
less than
X
the stated
velocity
0
V/V0
V
V0
V, settling velocity
Example:
Given: A settling basin is designed to have a surface overflow rate of 32.6 m/day = .37mm/s
(800gpd/ft2).
Find: The overall removal obtained for a suspension with the size distribution given below. The
specific gravity of the particles is 1.2 and T=20C. =1.027, =0.9997
Particle
size, mm
Weight
fraction
greater
than
size,
percent
Weight
fraction
less than
size,
percent
0.10
0.08
0.07
0.06
0.04
0.02
0.01
10
15
40
40% of
the
particles
> .07
70
93
99
100
100% of
the
particles
> .01
90
90% of
the
particles
pass the .
10 sieve
85
60
30
7
7% of the
particles
pass the .
04 sieve
Weight
fraction,
%
v, mm/s,
from
above
calc.
Nr,
Weight
fraction
remaining
%
10.0
15.0
40.0
70.0
93.0
99.0
100
1.08
0.689
0.527
0.387
0.172
0.043
0.011
.10
90.0
0.05
85.0
0.04
60.0
0.02
30.0
0.01
7.0
0.001
1.0
0.0001
0
Plot the above numbers:v vs. weight fraction remaining , e.g. 1.08, 90.0; 0.689,85 etc.
1.0
1-Xs 100% removed
fraction of Xs=.27
particles with
less than
X
the stated
velocity
0
V/V0
V
V0=.37mm/s(800gal.day,ft2)
V, settling velocity
All particles with a settling velocity greater than .37mm/s will be 100% removed. From the
graph, the fraction (1-Xs) is equal to 0.73 or 73%; a portion of the remaining 27% will be
removed, graphically this is the area above the settling curve, but below the Xs line. One way to
obtain this desire area is to assume increments of x, say 0.04, and pick off the corresponding v,
velocity, from the graph. The resulting product x(v) is the area for that increment. The
increments are then summed to obtain the total area.
x
v
x(v)
0.04
0.04
0.04
0.04
0.04
0.04
.027
0.06
0.0024
0.16
0.0064
0.22
0.0088
0.26
0.0104
0.30
0.0120
0.34
0.0136
0.37
.0099
Xs
vdx
0
The temperature difference involved density flows are 0.2-0.5C and the flow velocity
of the density flow is 2.6-6fpm with a design or intended flow velocity of 1.3fpm.
The types include: upflow clarifiers, reactor clarifiers and horizontal rectangular.
Upflow clarifiers, reactor clarifiers are susceptible to hydraulic and solids shock
loadings.
Most large water treatment plants use horizontal rectangular clarifiers primarily
because of the flexible performance, predictable settling efficiency and minimum
maintenance cost.
Design criteria include T3.2.5-2, p.150:
Flow imbalance at the inlet will lead to flow short-circuiting, jetting, turbulences and
hydraulic instability.
The most simple and effective method for distributing the water from the flocculation
tanks to the sedimentation tanks is a perforated baffle wall whose requirements are as
follows:
- The wall should cover the entire cross section of the basin
- The wall should be uniformly perforated
- A maximum of ports should be provided to minimize jets and dead zones
- The headloss through an individual port should be .12-.35
- The headloss through an individual port should be less than .4 to prevent floc
breakage.
- The size of the ports should be uniform in diameter, 3-8 to avoid clogging
- The ports should be placed no more than approximately 10-20 on center to
avoid compromising the structural strength of the wall.
- The flow should be directed at the basin outlet.
The water exiting the basin should be uniformly collected across an area that is
perpendicular to the proper flow direction. Perforated baffles are not recommended for
the outlet because they are not effective in dealing with density currents.
V-notched weir plates are used for the outlets and are generally attached to the
launders. Launders are long troughs which channel the water to an outlet. Long
launders have major advantages: the water level of the tank remains substantially
constant; wave action is minimized; weirs and modules are easily attached to the
launders.
G. Shape of the Tank
Rectangular basins that are both wide and deep tend to hydraulically unstable and
foster density flow patterns. Basins that are narrow, shallow and long have flow
stability and minimize short circuiting.
Flow characteristics of the sedimentation basin can be estimated by the Reynolds, NR,
and Froude, NF, numbers:
NR = vR/ < 20,000
NF = v2/gR > 10-5 units p.161
An ordinary basin has NR >15,000 and NF <10-6 both of which indicate an inferior
condition.
One of the least desired shapes has 180 turn at its midlength because they are
inefficient due to turbulence and dead spots at the turn.
H. Sludge Collection System
Choices include: chain and flight; traveling bridge with squeegees; traveling bridge
with suction; float supported sludge suction; underwater bogies with squeegee.
Any thing with moving parts such as the traveling bridge should not be used in very
cold, ice prone parts of the country.
The chain and flight can service a maximum length of 200ft, 60m.
The traveling bridge can service any length of tank; but it is effective if the length
exceeds 260-300ft, 80-90m. The speed is typically 1fpm.
The underflow rate associated with sludge removal of the horizontal flow and long
rectangular basins is typically .1-.2% of the plant flow. The concentration of solids in
the sludge is .2-5%.
Floc settling. The majority of the floc should settle in the first half of the tank. Visual
observation is important. If the water is clear in the middle and full of floc at the end, a
density flow is indicated.
Abnormal phenomena. sludge floating (bulking); scum; fly larvae; algae; corrosion.
Optimization of the sludge withdrawal process.
4. Example Problems
Given: Grit Chamber Design, Q=85MGD, .15mm minimum size to be removed, 10C. Consult
the grit chamber criteria on page 171. W=35ft. d=10
Find:
1.) The number and shape of the tanks
2.) Tank dimensions
3.) t
4.) surface loading
1.) The number and shape of the tanks
Two rectangular tanks. If one goes down for a problem or maintenance, the other is still
available to do the job. An alternative for a smaller plant is one tank and a by-pass channel.
2.) Tank dimensions
The settling velocity of the .15mm sand from T3.2.5-1.
v0 = 15mm/s = 3.0fpm
From page 160:
water depth = 10-16ft, say 10ft.
Q = 85MGD x 1.547cfs/MGD
Q = 131.5cfs x 60s/min = 7890 cfm
Q/tank = 7890 cfm / 2
Q/tank = 3945 cfm
A = WD = 10x 35
A = 350ft2
v = Q/A = 3945 cfm / 350ft2
v = 11.27fpm
20%
10/10=1
6E. Given: Grit Chamber Design, Q=55MGD, .03mm minimum size to be removed, 10C.
Consult the grit chamber criteria on page 160. W=30ft.
Find:
1.) The number and shape of the tanks
2.) Tank dimensions
3.) t
4.) surface loading
6E. Given: Design the sedimentation tanks for your project. Use example 3, p.163 as a
guide.
Find: Include the following items:
1.) The number of tanks
2.) Tank dimensions
3.) The configuration of the tank inlet and diffuser wall.
6F. Given: Design the sedimentation tanks for your project.