Professional Documents
Culture Documents
Construction Technology of Open Caisson For Oversize Surge Shaft in Drift Gravel Stratum
Construction Technology of Open Caisson For Oversize Surge Shaft in Drift Gravel Stratum
Xing-guo Yang
State Key Laboratory of Hydraulics and Mountain River Engineering,
Sichuan University, Chengdu, Sichuan, 610065, China
College of Water Resource and Hydropower, Sichuan University,
Chengdu, Sichuan 610065, China
e-mail: 89022251@163.com
Hong-tao Li*
State Key Laboratory of Hydraulics and Mountain River Engineering,
Sichuan University, Chengdu, Sichuan, 610065, China
College of Water Resource and Hydropower, Sichuan University,
Chengdu, Sichuan 610065, China
*Corresponding author: e-mail: htl@scu.edu.cn
ABSTRACT
Economically affordable, open caissons are a popular choice for various geotechnical engineering
applications. Theyre also frequently used because of their reinforcement and demolition capacities, as
well as for providing a large opening construction that provides safety for neighboring buildings in a
complex construction field. The large cylindrical surge shaft of Xiergou Hydropower Station is located
in drift gravel stratum. The upper 65 m of this surge shaft adopts an open caisson form with an internal
diameter of 22 m and external diameter of 25 m. The open caisson construction can face challenges
such as deviation, tilt, cracking, sink-suspension, and sudden sinking. This study analyzes the sinking
stability of an open caisson by using theoretical calculations to determine sudden sinking,
sink-suspension, and other risks. These calculations make use of open caisson structure optimization
and auxiliary sinking methods, such as shock blasting. Moreover, using finite element numerical
simulation, this study calculated the stress variations during the sinking of the open caisson. The
calculations were used to optimize the construction program of an open caisson to avoid cracking and
the failure of the open caisson concrete. Using a field sinking test and deformation monitoring, this
study determined a set of systematic methods for the construction of a large open caisson on drift
gravel stratum, which yielded a new method for open caisson construction under complicated
geological conditions.
KEYWORDS:
surge shaft; open caisson structure; construction; excavation; drift gravel stratum
INTRODUCTION
The principle of the open caisson suggests that the earth surfaces open caisson structure
occurs gradually, in advance of the sinking to the designed elevation under the containment of the
- 5725 -
5726
open caisson wall. Since the first application in the France Saloney Coal Field in 1893, the open
caisson construction method has been widely applied, to more than 1,500 underground
constructions in Europe. The open caisson construction method is predominantly self-sinking.
However, this method is only applicable for soft strata and shallow sinking depths and lacks of
related control measures. In the 1990s, construction methods based on the loaded -sinking, space
system caisson (SS), and super open caisson system (SOCS) were gradually adopted. During the
construction of an open caisson, the sudden sink, sink-suspension, derivation, tilt, and wall failure
should be controlled. Furthermore, more dangerous construction conditions may be encountered
in the sinking process compared to the completion stage of the open caisson. Therefore, its vital
to pay close attention to the safety requirements for the open caisson structure [1-3]. Today,
research on the open caisson construction period has primarily been concentrated on sinking
stability [4-5], subgrade reaction [6-10], side friction resistance [11-13], strength, and deformation
[14-15]. Certain researchers [16] have calculated stipulations for the construction process of small
and medium-sized open caissons while ignoring the particularity of the large open caisson.
Although researchers around the world have accumulated information regarding open caisson
construction [17], few have investigated the construction of a large open caisson on a complicated
drift gravel stratum.
Xiergou Hydropower Station is a diversion hydropower station located in Zhouqu County in
Gansu Province, China. Its open-top impedance surge shaft is located on the hill slope on the back
of the plant, with the upper end connected to the diversion tunnel and the lower end connected to
the pressure pipeline (Figure 1). The surge shaft is 102 m deep and lies in the 97m overlying
stratum. The upper part of this stratum is filled with silty soil or gravelly soil and is 33.4 m thick.
The low part is a 63.6 m thick pluvial drift gravel stratum with boulders that are a general
diameter of 0.4~0.6 m with a maximum diameter of 1.5 m, which accounts for about 5%~8%. The
stratum in the elevation range of 1537.5~1524 m is a compact conglomerate layer. The upper 65
m of the surge shaft adopts an open caisson form with an internal diameter of 22 m and external
diameter of 25 m (Figure 2). The open caisson construction method can effectively prevent well
wall collapse and thus reduce safety risks caused by the combination of temporary support
measures with a permanent wellbore structure. However, the traditional loading-sinking, SS and
SOCS based methods fail to solve the problems that arise during the construction process of drift
gravel stratum. These problems include deviation, tilt, the cracking and failure of the open caisson
wall, sinking-suspension, and sudden sinking. Through theoretical calculation analysis, numerical
simulation, field testing, and monitoring this study analyzed the construction plans to demonstrate
the sinking methods, reliability, and structure safety of the open caissons in different strata.
Moreover, it investigated the sinking coefficient, construction method, sinking-blocking
processing method, and sinking-slagging method of an open caisson, which provided references
for the open caisson design and construction under complicated geological conditions.
Surge shaft
Hydropower house
5727
QB
T R
where K is the sinking coefficient; Q is the weight and additional load of the open caisson; B is
the water discharge. In the instance of the drainage sinking method, B=0; T is the frictional
resistance between an open caisson wall with soil and can be obtained by Eq. (2); R is the
counter-force of the foot blade and can be got by Eq. (3).
The frictional resistance T between an open caisson wall with the soil layer can be obtained
by:
T D( H 2.5) f
where D is the external diameter of the open caisson ; H is the total height of the open caisson ; f
is the coefficient of frictional resistance between the open caisson wall with the soil layer
The counter force of the foot blade R is calculated by:
R D0 (c n / 2)Rd
where D0 is the average perimeter of the open caisson; c is the tread width of the foot blade; n is
the horizontal projection width of the foot blade slope with the internal contact surface between
5728
the terrain and open caisson; Rd is the limit carrying ability of subsoil. In the instance of the soil
excavation in the tread and slope of foot blade, R=0.
The reinforced concrete of the open caisson had a volume-weight of 25 KN/m3. The
excavation section was located above the underground water line. In the calculation, we set B=0.
The drift gravel stratum foundation has a higher bearing capacity. The Rd is valued as 0.6 MPa.
The open caisson in the drift gravel stratum sinks intermittently and significantly by extremely
short small time intervals instead of being synchronously attributed to the fluctuations of the
frictional resistance coefficient around the open caisson. Analysis on the sensitivity of the sinking
coefficient of the open caisson suggested that the sinking coefficient was sensitive to the frictional
resistance coefficient (Figure 4). When there was no excavating conducted on the soil in the tread
and slope of the foot blade and open caisson wall thickness of 1.5 m (Figure 4 (a)), the sinking
coefficient under the depth of 35 m is higher than 1.0. The high sinking coefficient of the open
caisson suggests the possibility of sudden sinking. To stabilize the sinking, the friction resistance
increase should be equivalent to the weight increase of open caisson. Thus the wall thickness of
the open caisson should be reduced to 1.14 m under a depth of 35 m. For construction
convenience, the wall thickness of the open caisson was set at 1.2 m. After the weight of the open
caisson was reduced, the open caisson satisfied the stable sinking condition after the soils on the
slope were excavated according to the calculation results of the subsequent excavating soil area.
In the case of excavating the soils in the tread and slope of the foot blade and wall thickness
of 1.5 m (Figure 4 (b)), the sinking coefficient rapidly reduces as the frictional resistance
coefficient increasing from 10 kPa to 35 kPa. As the open caisson sinks below a depth of 10 m,
the sinking coefficient shows little variations with the depth increase. The fluctuations of the
frictional resistance coefficient in the construction caused the sinking coefficient to drop below
1.0. In these conditions, theres a tendency of sinking. In the case of the sinking being blocked,
the surrounding rocks can be lubricated by means of flushing water along the open caisson wall to
reduce the frictional resistance coefficient. Also, the sinking process can be furthered by shock
blasting the open caisson via a small amount of explosives (generally a bundle of 4 32 cartridges,
800 g) that are hung along the middle part of the open caisson with cranes. This method can
induce a brief vibration of the wall of the open caisson and thus promote the successful sinking of
the open caisson.
During the sinking process of the open caisson, the soils around the open caisson are hard to
stabilize due to in the lack of a capacity to press the backfill on the external side of the open
caisson. Therefore, during the first 35 m of sinking, the open caisson thickness is set to 1.5 m to
reduce the backfill. After 35 m, the open caisson wall thickness is reduced to 1.2 m to avoid the
high open caisson weight. To ensure the safety of the open caisson during the sinking process, the
external wall of the steel foot blade adopts a vertical structure and the tread is increased from 20
cm to 30 cm. According to the conditions of the field construction, this study increased the height
of the steel plate on the inner side of the foot blade from 100 cm to 150 cm, and the installation
height of the stiffening rib from 30 cm to 50 cm, all of which helped prevent the foot blade
concrete failure induced by the excavation and blasting of open caisson, as well as the frictional
failure of the foundation in the sinking process (Figure 5).
f=15kPa
f=25kPa
f=35kPa
Sinking coefficient
Sinking coefficient
2.5
5729
1.5
1
0.5
0
0
20
40
60
Sinking depth/m
f=10kPa
f=20kPa
f=30kPa
7
6
5
4
3
2
1
0
0
20
40
f=15kPa
f=25kPa
f=35kPa
60
Sinking depth/m
a: Without excavating the soils in the tread and b: Excavating the soils in the tread and slope of
slope of foot blade
foot blade
Figure 4: Sinking coefficient sensitivity curve
5730
large diameter and complex geological conditions. During the construction, a large amount of
boulders emerged in the open caisson as the open caisson sunk more than 10 m. In addition,
stresses were concentrated on the open caisson wall and thus resulted in the cracking and failure
of the concrete. Therefore, it is important to select the optimal construction method and plan by
simulating various cases, studying the stress on the open caisson wall and foot blade, and
analyzing the potential locations and forms of the failure on the open caisson wall and foot blade.
The finite element software ANSYS was used to calculate 6 materials, including C2 reinforced
concrete, Q235 steel, soil, drift gravel, weakly weathered bedrock, and slightly weathered bedrock.
The open caisson wall, bedrock, and foot blade were simulated using a linear elastic model, while
overburden was simulated using ideal elastic perfectly elastic and plastic Drucker-Prager model.
Table 1 shows the physical and mechanical parameters of the two models. The compressive
strength and tensile strength of concrete were set as 12.5 MPa and 1.3 Mpa, respectively.
The contacts of the open caisson wall and overburdened foot blade were simulated using
surface-surface contact elements. The surfaces in the contacting state were impenetrable to each
other and capable of transmitting normal pressure and tangential friction force instead of normal
tension. Therefore, the contact problem is freely decomposable. This effectively simulates the
interactions between the open caisson wall and the surrounding soils. In the calculation, the
element Targe170 was used to simulate the 3-D target surface; and Conta174 was used to
simulate the contact surface. Figure 7 shows the finite element calculation model of the surge
shaft.
To determine a reasonable construction method while avoiding the disadvantageous
mechanical deformation brought on by unreasonable constructions, this study selected the
following cases:
Case 1: symmetrical geological condition.
Case 2: asymmetrical case. First, excavating the weak overburden on the tread side of the foot
blade and supporting the other foot blade side through rocks.
Case 3: asymmetrical case. First, excavating the rocks on the tread side of the foot blade and
supporting the other foot blade side through weak overburdens.
5731
Elastic
modulus
GPa
Deformation
modulus
GPa
2.78
6.5
4.00
0.30
2.80
9.0
7.00
0.40
0.40
0.167
0.25
1.55
2.24
2.50
7.55
Poisson
ratio
Density
0.34
g/cm
0.05
0.06
kPa
0.48 25.4 25
0.53 27.6 0
28.0
206
According to the results of the numerical simulation, the maximum tensile and compressive
stresses on the open caisson wall in the sinking process are achievable (Figure 8). In case 1, with
an increase of the sinking depth of the open caisson, the maximum tensile and compressive
stresses grow gradually and reach to 1.14 MPa and 3.03 Mpa, respectively. In case 2, the
maximum stress on the open caisson wall is seen on the foot blade supported by the hard base.
Stresses are concentrated and increase gradually with the sinking of the open caisson. The
maximum tensile and compressive stresses calculated reach to 2.48 MPa and 4.50 Mpa,
respectively. Both exceed the concretes designated tensile strength. In case 3, the open caisson
wall does not present an obvious stress concentration. The maximum tensile and compressive
stresses are 1.16 MPa and 3.11 Mpa, respectively. The maximum tensile stresses on each part of
the open caisson are all lower than the designed tensile strength of the concrete. During the
construction process under a symmetrical geological condition, the open caisson sinks layer by
layer and the stress satisfies the requirements; under the asymmetrical case, the hard rock sections
should be executed first followed by the weak rock sections. In this way, the open caisson absorbs
a lower stress and thus will not be damaged.
Case 1
Case 2
Case 3
5732
5733
Figure 10: Excavation of the compact conglomerate layer under open caisson cutting
edge
5734
Causes
Countermeasures
As
the
bowl-shaped
excavation goes too deep, the
open caisson is temporally
held in a reasonably stable
condition by the external wall
frictional resistance and foot
blade. By continuing the
excavation, the frictional
resistance reaches to the limit
and the open caisson wall
resistance suddenly reduces
due to the thixotropy of soil.
Sudden sinking is thereby
induced.
Appropriately
increasing
the
sinking
coefficient; pouring water along the open
caisson wall to reduce the friction between the
open caisson wall and soil.
Controlling the excavation (the bowl bottom
should not be too deep); do not hollow the
foot blade; determine the foundation condition
in advance.
5735
found in time.
5) The bias pressure on the
open caisson wall is induced
because of the removal of
soils or objects from the open
caisson;
the
uneven
distribution of the load on the
open caisson.
6) Sand boils on one side of
the open caisson.
5736
Sinking
height
(m)
off-centering
(cm)
Angle of
inclination
()
Serial
number
Sinking
height
(m)
off-centering
(cm)
Angle of
inclination
()
2.3
3.0
0.7473
13
41.3
37.0
0.5133
5.3
5.5
0.5946
14
43.7
38.0
0.4982
8.3
9.6
0.6627
15
46.8
38.5
0.4713
10.3
13.5
0.7509
16
48.9
39.1
0.4581
12.7
17.0
0.7669
17
50.8
39.8
0.4489
16.5
16.2
0.5625
18
52.8
40.2
0.4362
20.5
18.0
0.5030
19
56.8
41.5
0.4186
23.0
19.5
0.4858
20
58.69
42.5
0.4149
27.0
24.0
0.5093
21
64.32
45.8
0.4080
10
33.0
28.5
0.4948
22
63.42
46.2
0.4174
11
36.0
31.5
0.5013
23
62.92
46.3
0.4216
12
38.0
34.7
0.5232
CONCLUSIONS
(1) The results of this study show that the open caisson construction method is applicable for
drift gravel stratum and other complicated geologies. This method was conducive to environment
protection since it greatly reduced the excavation amount on the overburden and saved the
stacking area of the waste slag. The well wall stabilizing using open caisson increased the safety
of the excavation in the well and made it possible of transferring the temporary support and
permanent lining to the ground. The working environment was improved and the construction
risks were reduced as a result. This creative open caisson construction method yielded significant
social and economic benefits.
(2) According to the sinking frictional resistance analysis and structure calculation, a
reasonable open caisson structure reduces open caisson failure risk during construction.
(3) Based on the numerical analysis results and sinking test, this study proposes the following
5737
suggestions: implementing a uniform bowl-shaped excavation on the drift gravel strata; for the
hard and soft alternated strata, following the principle of hard rock priority and then soft rocks;
for the gravel strata, breaking the rocks into sections using a hydraulic hammer; in regard to the
strata with a sinking difficulty, assisting the sinking by shock blasts using a small amount of
explosives, or, by extending the excavation to realize the stable and successful sinking of the open
caisson.
(4) This study (1) analyzed the causes for the sinking-termination, sudden-sinking, tilt, and
derivation of the open caisson and (2) put forward corresponding countermeasures. Moreover, it
investigated the tower crane transporting above the surge shaft and the pilot shaft sliding method
on the lower part of the open caisson, which reduced the slagging difficulty and improved the
slagging efficiency.
ACKNOWLEDGMENTS
This study was supported by the National Natural Science Foundation of China
(No.51009104).
REFERENCES
1
Mu Baogang, Xiao Qiang, Zhang Licong, Effect of supporting soil stiffness on internal force of
caisson during sinking[J], Journal of Southeast University ( Natural Science Edition),
2012,42(5):981-987. (in Chinese)
Tao Jianshan. Construction technology for draining sinkage for south caisson anchorage to
Taizhou YangtzeRiver Highway Bridge with large-size sunk well [J]. Journal of Railway
Engineering Society, 2009(1):63-66. ( in Chinese)
CHEN Xiao-ping, QIAN Pingyi, ZHANG Zhiyong. Study on penetration resistance distribution
characteristic of sunk shaft foundation [J], Chinese Journal of Geotechnical Engineering,
2005,27(2):148-152. (in Chinese)
Vesic A S. Tests on instrumented piles, ogeechee river site[J].Journal of SMFD,1970, 96: 561
584.
Yan Fuyou, Guo Yuancheng, Liu Shangqian. The Bearing Capacity Analyses of Soil beneath
the Blade of Circular Cassion. Advanced Building Materials, 2011, 250-253: 1794-1797.
5738
3689-3696.
10 Mu Baogang, Zhu Jianmin, Niu Yazhou. Monitoring and analysis of north anchorage caisson of
Fourth Nan-jing Yangtze River Bridge[J]. Journal of Geotechnical Engineering, 2011,
33(2):269-274. ( in Chinese)
11 Dyvik R, Anderson K H, Hansen S B. Field tests on anchors in clay [J]. Journal of Geotechnical
Engineering, 1993, 119(10):1515-1531.
12 Liu F Q, Wang J H, Zhang L L. Axi-symmetric active earth pressure obtained by the slip line
method with a general tangential stress coefficient[J]. Computers and Geotechnics, 2009,
36:352-358.
13 Sreenivas Alampalli, Venkatanarayana Peddibotla. Laboratory investigation on caisson
deformations and vertical load distributions. Soils and Foundations, 1997,Vol. 37, No.2, pp.
61-69.
14 Allenby D, Waley G, Kilburn D. Examples of open caisson sinking in Scotland [J].
Geotechnical Engineering, 2009, 162(1):59-70.
15 Yang Canwen, Huang Minshui. Stress analysis of a large open caisson key construction process
[J]. Journal of Huazhong University of Science and Technology: City Science Edition, 2010,
27(1):17-21. (in Chinese)
16
17 Fathi Abdrabbo, Khaled Gaaver. Challenges and Uncertainties Relating to Open Caissons [J].
The Journal of the Deep Foundations Institute, 2012, 6 (1):21-32.
2014 ejge