Place- Cross Country Pipeline. Observations: 1. HYDROTEST STATUS: Location: 4 kms away from Raw Water Reservoir inside the plant. Length: Hydrotest conducted over a length of 1300 mtrs. Contractor: Shri Company. Arrangements for the Test: a. Water for the test was taken from the local villager as well as using tankers. b. Pump for pressurizing was brought on rent. Working Pressure: 12 kg/cm2. Test Pressure: 18 kg/cm2. TEST RESULTS: a. Test failed on 28.04.2012 after the pressure reached to 15 kg/cm2. b. Reason for failure was leakage of dummy pipe used.
Arrangement for
Arrangement for Hydrotest
Dummy Piece
Leaked Dummy Pipe
MORSHI PUMP HOUSE STATUS:
1. PUMP HOUSE: Reinforcement and shuttering work under progress. 2. MCC ROOM: Column Foundation Work under progress. 3. FOREBAY: a. PCC Complete. b. Excavation Complete.