Professional Documents
Culture Documents
pms-2015-1 Paper Objectives of Feasibility Studies PDF
pms-2015-1 Paper Objectives of Feasibility Studies PDF
Exploration
Discovery
Assessment
Development
Production
Closure
infrastructure,
1)
2)
3)
Prefeasibility Studies
There are three common reasons for carrying out prefeasibility
studies as follows:
1)
2)
3)
Terminology
A range of sometimes conflicting titles are used for studies,
including the following;
Scoping study
Class 1 Study
Preliminary Evaluation
"Order-of-Magnitude Estimate"
"Capacity Factor Estimate"
Screening study
Prefeasibility Study
Class 2 Study
Intermediate Economic Study
Preliminary Feasibility Study
"Equipment Factor Estimate"
Final Feasibility Study
Class 3 Study
Bankable Feasibility Study
"Forced Detailed Estimate"
Detailed Engineering Study
Class 4 Study
Project Control Estimate
Definitive Cost Estimate
"Fall-out Detailed Estimate"
Thompson (1993) reports that "he discovered that if 10 people
were discussing preliminary engineering or that old standby
definitive estimate, there were 10 different opinions" (as to the
meaning of these terms). Some of the above terms are not
widely used in Australia.
The terminology used in these notes is that usually used by the
authors, and we believe it to be widely used in the Australian
mining industry.
Contingency Allowance
The contingency allowance is intended to make provision for:
Items which have not been covered because of oversight.
Unpredictable external changes, such as changes in
legislation, taxation and royalties, or provision or
discontinuation of external infrastructure services.
35
(Without contingency)
% Likely Accuracy
Scoping Study
30
Prefeasibility Study
25
20
Final Feasibility
Study
15
Detailed
Mechanical
Engineering
Completion
10
5
0
Project
Completion
20
40
60
80
100
120
% Project Status
Scoping Study
Preliminary Feasibility
Study
Detailed Design
Site
Geographical location
Assumed
General
Approximate
None
If Available
Available
Specific
Detailed
None
None
Preliminary
Final
Possibly
Recommended
Essential
Essential
Indicated/Inferred Resources
Proven/Probable
Reserve
Mining Method
Assumed
Preliminary
Finalised
Mining Rate
By Analogy
Geotechnical
Assumed
Equipment Selection
Mining
Preliminary
Optimised
Optimised by Detailed
Scheduling
Finalised
Preliminary
Detailed
Finalised
Not Essential
Preliminary
Process Flowsheets
Assumed
Preliminary
Optimised
Finalised
Bench-scale Tests
If Available
Recommended
Essential
Essential
Not Needed
Recommended
Recommended
Essential
Preliminary
Optimised
Finalised
Treatment Process
Conceptual
Possible
Probable
Actual
Equipment Selection
General Arrangements,
Mechanical
General Arrangements,
Structural
Hypothetical
Preliminary
Optimised
Finalised
Sometimes
Minimum
Preliminary
Complete
None
Outline
Outline
Preliminary
None
Single-line
Some Detail
Piping Drawings
None
Single-line
Some Detail
None
Electrical Drawings
None
None
Single-line
Some Detail
Specifications
None
Performance
General/Major Equipment
Detailed
Project Staff
Specialist Engineer
Specialist Engineer
Estimators
Existing Files
Single Source
Multiple
Competitive
Civil Work
Rough Sketch
Drawing Estimate
Drawing Estimate
Take-offs
Mechanical Work
% of Machinery
% of Machinery
Manhours/Tonne
Manhours/Tonne
Structural Work
Rough Sketch
Preliminary Drawings
Take-off/Tonne
Take-off/Tonne
% of Machinery
% of Machinery
Take-off
Take-off
Electrical Work
$ per Kw
$ per Kw
Take-off
Take-off
Indirect Costs
Accuracy (Based on
Experience)
% of Total
% of Total
Calculated
Calculated
20-25%
15-20%
15%
10%
Assumed
Investigative
Investigative
Negotiate
On-costs
Assumed
Calculated
Calculated
Calculated
Power Costs
Assumed
Actual
Actual
Contract
Fuel Costs
Assumed
Verbal Quote
Letter Quote
Contract
Consumable Supplies
Assumed
Verbal Quote
Letter Quote
Contract
Reagents
Assumed
Verbal Quote
Letter Quote
Contract
Maintenance Supplies
Assumed
Verbal Quote
Letter Quote
Contract
Economic Analysis
If Meaningful
Comparison/ Rejection
Preliminary Evaluation
If Required
Commitment to Final
Feasibility Study
Required
If Requested
Commitment to Project
Project Control
Use of Estimates
disbursement schedules,
overrun financing,