Professional Documents
Culture Documents
Formulas PMP Resumen
Formulas PMP Resumen
PERT
Where:
O + 4(ML) + P
6
P O
= SD =
6
t e=Time estimate
te =
O=Optimistic estimate
P=Pessimistic estimate
ML=Most likely estimate
O+ML+P
Three Point Estimates=
3
Communication Channels
2
n(n 1) n n
C=
=
2
2
=Standard deviation
SD=Standard deviation
Where:
C=Communication channels
n=Number of people
Activity Duration:
AD =
Mt
PV =
(1+ r )t
CV = EV AC
schedule variance
SV = EV PV
CPI =
estimate to complete
ETC = EAC AC
TCPI =
EAC = AC + ETC
2 Where current state is anomolous to the norm
EAC = AC + BAC EV
EAC = AC +
ESI
BAC EV
BAC AC
PV=Present Value
Mt=Amount of payment t time
Benefit PVincome
=
PVcosts
Cost
EV
AC
EV
SPI =
PV
Where:
t=Time Periods
Where:
Earned Value
Work quantity
Production rate
ESI
BAC EV BAC
=
CPI
CPI