Start
Site Clearance
Site Investigation
Piling
Concrete Wall
Constructing Process
Concrete
Stairs
End
Description
1. Site Clearance
- Clear all the debris remaining on the site.
- Clear all the existing building that has on the site.
- All the waste and debris should be removed and disposed of according as
approved by official authorities.
2. Site Investigation
- Check the past record of the site.
- Check the ground water condition of the site
- Check the physical properties of soil and rock underlying the site.
- Check the mechanical properties such as strength and compressibility of different
soil and rock.
3. Analysis and Design
- Analysis of the appropriate material in the construction of retaining wall.
- Design the retaining wall to hold back the slope.
- Test the material that use to construct the retaining wall.
- Makesure all the material use to construct the retaining wall pass the test and has
all the requirement needed.
4. Constructing Process
- Start the construction of the retaining wall based on the plan.
i. Piling
Installation of anchor pile.
Anchor piles are inserted in a casing that is brought to depth by
System (IBS)
Size of panel is 3 meter x 2.5 meter.
The panel will be install between of the concrete wall.
v. Planting
The purpose of planting the climbing tree is for grip the soil on the
slope.
Type of tree that suitable is ficus pumila.
The plat can climb up the wall and has a good ability to grip the
soil.