Solution
PART A
Performance criterion
Weight(W) Supplier
1.Price
0.2
2.Quality
0.2
3.Delivery
0.3
4.Production Facilities
0.1
5.Enviromental protection
0.1
6.Financial position
0.1
Total
1
PART B
The supplier A and C survived the total hurdle under the condition of younger Bennet proposed policy.
The supplier C will get the order of raw material because his score is more then the supplier A and B.The second in the list will be supp
PART C
The current policy was not very effective because they Benett company was giving orders without having a specific criteria.They were
c criteria.They were