Tentative Programme of 8 Storey Residential Building at Juffair

Activity ID

Activity Name

Tentative Programme of 8 Storey Residential Building at Juffair


KEY DATES
KEY110

Project Finish

CONSTRUCTION

SUPERSTRUCTURE

MOCK UP ROOM WORKS


MURW10
Inspection And Approval Of Mock Up Room

Original
Duration
103
0
0

Programme To
Complete Start

Programme To
Complete Finish

28-Feb-17

28-Feb-17

01-Nov-16

28-Feb-17
28-Feb-17

98

01-Nov-16

22-Feb-17

14
14

01-Nov-16
01-Nov-16

16-Nov-16
16-Nov-16

98

01-Nov-16

22-Feb-17

15
10
10
10

17-Dec-16
22-Dec-16
22-Dec-16
22-Dec-16

02-Jan-17
02-Jan-17
02-Jan-17
02-Jan-17

15
15
15

17-Dec-16
17-Dec-16
17-Dec-16

02-Jan-17
02-Jan-17
02-Jan-17

98
8
4

01-Nov-16
01-Nov-16
01-Nov-16

22-Feb-17
09-Nov-16
05-Nov-16

Paint 1St Coat Recreational Floor

06-Nov-16

09-Nov-16

PAINTING FINAL COAT


PAINTFF330
Paint Final Coat for 1st to 6th floor

15
15

06-Feb-17
06-Feb-17

22-Feb-17
22-Feb-17

24
4

06-Dec-16
06-Dec-16

02-Jan-17
10-Dec-16

MEP WORKS
ELECTRICAL WORKS
ELECTRICAL FINAL FIX
MEPELFF170 Switches & Sockets Fixing for 1st to 6th floor
PLUMBING WORKS
PLUMBING FINAL FIX
MEPPLFF170 Sanitary Ware and Vanity Units Fixing for 1st to 6th Floor
PAINTING WORKS
PAINTING 1ST COAT
PAINT1ST160
Paint 1St Coat 6Th Floor
PAINT1ST170

WOODEN DOOR / CABINETS WORKS


WDC120
Wooden Door / Cabinet Works 2Ndfloor
WDC130

Wooden Door / Cabinet Works 3Rdfloor

11-Dec-16

14-Dec-16

WDC140

Wooden Door / Cabinet Works 4Th Floor

15-Dec-16

19-Dec-16

WDC150

Wooden Door / Cabinet Works 5Th Floor

20-Dec-16

24-Dec-16

WDC160

Wooden Door / Cabinet Works 6Th Floor

25-Dec-16

28-Dec-16

WDC170

Wooden Door / Cabinet Works Recreational Floor

29-Dec-16

02-Jan-17

RECREATIONAL FLOOR FINISHES BEFORE AUTHORITY APPROVAL


A1000
Recreational Floor Finishes Before Authority Approval

30
30

29-Nov-16
29-Nov-16

02-Jan-17
02-Jan-17

AUTHORITY APPROVALS
AUTHAPP10
Approval Of Thermal Insulation

20
10

03-Jan-17
03-Jan-17

25-Jan-17
14-Jan-17

AUTHAPP20

Approval Of Water Supply

10

03-Jan-17

14-Jan-17

AUTHAPP30

Approval Of Municipality

10

03-Jan-17

14-Jan-17

AUTHAPP40

Approval Of Electrical Department

10

03-Jan-17

14-Jan-17

AUTHAPP

Approval Of CDD

10

15-Jan-17

25-Jan-17

RECREATIONAL FLOOR WORKS AFTER AUTHORITY APPROVAL


A1010
Recreational Floor Works after Authority Approval

24
24

26-Jan-17
26-Jan-17

22-Feb-17
22-Feb-17

TESTING & COMMISSIONING


TC100
Electrical Testing And Commissioning

20
10

15-Jan-17
15-Jan-17

06-Feb-17
25-Jan-17

1 of 2

Nov

2016

Dec

Jan

2017

Feb

Mar

Project Finish

Tentative Programme of 8 Storey Residential Building at Juffair


Activity ID

Activity Name

Original
Duration

Programme To
Complete Finish

TC110

Plumbing Testing And Commissioning

TC120

HVAC Testing And Commissioning

10

15-Jan-17

25-Jan-17

TC130

Fire Fighting Testing And Commissioning

10

26-Jan-17

06-Feb-17

TC140

Lift Testing And Commssioning

10

26-Jan-17

06-Feb-17

15

06-Feb-17

22-Feb-17

15

12-Feb-17

28-Feb-17

DEMOBILIZATION
DM100

Demobilization

SNAGGING & HAND OVER


SH100

Snagging And Hand Over

10

Programme To
Complete Start

15
15

15-Jan-17

06-Feb-17
12-Feb-17

25-Jan-17

22-Feb-17
28-Feb-17

2 of 2

Nov

2016

Dec

Jan

2017

Feb

Mar