3rd Pit
Railway
Office of the
Divl. Rly Manager (Mech)
Tinsukia
No. M-246/1/Plg/Pt.II/NTSK
Date: 09/11/16
To
SrDEN/C/TSK
Sub:- Failure of wat walk of 3rd Pit/DBRG
It is to be informed that 21 Nos of pillars along with cat-walk of under
construction 3 pit collapsed as shown in photo. In this connection it is requested to please check all
other pillars and foundation of the 3rd pit so that there is no further failure of 3 rd pit after completion in
future.
rd
Sr.DME/TSK
Copy to:
1. DRM & ADRM/TSK for kind information please.