07/12/2016

General overview of the job in December 6,2016 (shot blasting)

Very few area is completed with shot blasting and the reason being
that the compressor could not provide enough pressure for the job so it
is taking long time.
When the compressor starts to build up pressure, it takes about 5
minutes to build the pressure of 8.6 bar.
As the sand blasting process starts, the pressure in the compressor
drops to 3.2 bar within a minute.
The pressure of 3.2 bar holds up for about 5 minutes only and the
process is stopped for 5 minutes again to let the compressor build up
the pressure

Measurement of Temperature and Humidity.


Outside the turbine housing
Instrumen
t1

Instrumen
t2

22

21

74

82

Temp.
(Celsius)
Humidity (RH
%)

Inside the turbine housing


Instrumen
t1

Instrumen
t2

21.9

21.5

75

83

Temp.
(Celsius)
Humidity (RH
%)

Measurement for roughness


The distance between the highest peak and the lowest valley at two different
positions were measured and was found to be:

60 microns

80 microns
R