Activity

ID

Activity
Description

-1 1 2

Months
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

MAITRE DE L'OUVRAGE
Dates Butoirs (Project Milestones)
MLA000100

Entre en vigueur

MLA000110

Accs au site pour mobilisation

MLA052135

Disponibilit du rseau lectrique

MLA064100

Disponibilit du gaz naturel

Notice to Proceed
Site Access for Construction Mobilization
Back Feed Power Available
Fuel Gas Available

SNC-LAVALIN CONSTRUCTORS INTERNATIONAL INC.


Dates Butoirs (Project Milestones)
MLA000200

Rception donnes technique du turbinier

Turbine Generator Vendor Data Received

MLA048100

Attribution commande TAG/A (Turb. gaz/Alt.)

Award PO: CT/G

MLA056100

Attribution commande chaudires

Award PO: HRSG's

MLA078100

Attribution commande TAV/A (Turb. vapeur/Alt.)

Award PO: ST/G's

MLA178100

TAV/A #1 prt pour expdition

MLA278100

TAV/A #2 prt pour expdition

MLA156100

Dbut livraison chaudire #1

HRSG #1 Start Delivery on Site

MLA256100

Dbut livraison chaudire #2

HRSG #2 Start Delivery on Site

MLA148100

TAG/A #1 prt pour expdition

CTG #1 Ready to Ship

MLA248100

TAG/A #2 prt pour expdition

CTG #2 Ready to Ship

MLA178110

TAV/A #1 reu au chantier

MLA278110

TAV/A #2 reu au chantier

MLA148110

TAG/A #1 reu au chantier

MLA248110

TAG/A #2 reu au chantier

MLA156150

Fin livraison chaudire #1

HRSG #1 Last Shipment on Site

MLA256150

Fin livraison chaudire #2

HRSG #2 Last Shipment on Site

MLA000850

Vapeur disponible/Prt tourner TAV

MLA000870

Prt pour dbut des essais

MLA000860

Acceptation provisoire usine

MLA000950

Periode de correction

STG #1 Ready to Ship


STG #2 Ready to Ship

STG #1 Complete Shipment to Site


STG #2 Complete Shipment to Site
Combustion Turbine/Gen #1 Delivered on Site
Combustion Turbine/Gen #2 Delivered on Site

Steam Available/Ready to Roll Steam Turbine


Ready to Start Testing
Provisional Acceptance
180-day Cure Period Complete

Ingnierie (Engineering & Design)


EGA000010

Agencement gnral

EGA000005

Spc. tech. quipements majeurs

Start Date
Finish Date
Data Date
Run Date

01APR03
29MAY06
01APR03
21JAN03 08:38

General Arrangement
Major Equipment Specification

Early Bar
Progress Bar
Critical Activity

553D

Sheet 1 of 4

Algerian Energy Co.


Projet Skikda 600-800 MW
Proposition - chancier

Primavera Systems, Inc.

SNC-Lavalin Constructors International Inc

Activity
ID

Activity
Description

-1 1 2

Months
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Ingnierie (Engineering & Design)


EGA000100

Slection fournisseurs & ingnierie dtaille

Vendor Selection / Detailed Engineering

EGD000100

Conception lectrique souterraine

Underground Electrical Engineering

EGE000100

Conception tuyauterie souterraine

Underground Piping Engineering

EGF000100

Conception des fondations

EGS000150

Conception mcanique

EGK000100

Conception tuyauterie en surface

Above Ground Piping Engineering

EGL000100

Conception lectricit en surface

Above Ground Electrical Engineering

EGM000100

Conception de l'instrumentation

Instrumentation Engineering

Foundation Engineering
Mechanical Engineering

Approvisionnement (Procurement)
PRS024100

Fabrication/livraison systme de refroidissement

PRS000100

Fab/livraison quipement mcanique gnrale

Fab/Dlvr Plant Cooling System

PRL052110

Fabrication/livraison appareillage avant poste

PRL052100

Fabrication/livraison transformateur surtenseur

Fab/Dlvr GSU Transformers

PRL052125

Fabrication/livraison appareillage lectrique

Fab/Dlvr Balance of Plant Electrical

PRM032200

Fabrication/livraison DCS

Fab/Dlvr Balance of Plant Mechanical


Fab/Dlvr Substation Equipment

Fab/Dlvr Distributed Control System

Construction
CNA001020

Dbut de la construction

CNA001330

Mobilisation au site

CNC000340

Amnagement du site

CND000100

Services souterrains

CNF156100

Installation des fondations - Chaudire #1

CNF256100

Installation des fondations - Chaudire #2

CNF148110

Installation des fondations - TAG/A #1

CNF248110

Installation des fondations - TAG/A #2

CNF178100

Installation des fondations - TAV/A #1

CNF000200

Installation des fondations - BOP

CNF024100

Installation des fondations - Refroidissement

Foundation Installation - Plant Cooling System

CNF278100

Installation des fondations - TAV/A #2

Foundation Installation - STG #2

CNJ010200

Btiment administratif et de commande

Administrative/Control Building

CNJ010300

Btiment appareillage lectrique

Electrical Building

Start Date
Finish Date
Data Date
Run Date

01APR03
29MAY06
01APR03
21JAN03 08:38

Construction Start
Site Mobilization
Site Improvement
U/G Utilities
Foundation Installation - HRSG #1
Foundation Installation - HRSG #2
Install CTG #1 Foundation
Install CTG #2 Foundation
Foundation Installation - STG #1
Foundation Installation - BOP

Early Bar
Progress Bar
Critical Activity

553D

Sheet 2 of 4

Algerian Energy Co.


Projet Skikda 600-800 MW
Proposition - chancier

Primavera Systems, Inc.

SNC-Lavalin Constructors International Inc

Activity
ID

Activity
Description

-1 1 2

Months
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Construction
CNR156100

Installation chaudire #1

Install HRSG #1

CNF052100

Installation des fondations-Transf. surtenseur

CNS000200

Installation des rservoirs rigs en chantier

CNR256100

Installation chaudire #2

Install HRSG #2

CNS178100

Installation TAV/A #1

Install STG #1

CNS278100

Installation TAV/A #2

CNS148100

Installation TAG/A #1

CNS248100

Installation TAG/A #2

Foundation Installation - GSU Transformers


Install Field Erected Tanks

Install STG #2
Install CTG #1
Install CTG #2

CNL052110

Installation de l'avant poste (sous-station)

Install Substation

CNS024100

Installation du systme de refroisissement

Install Plant Cooling System

CNK000100

Installation tuyauterie en surface

A/G Piping Installation

CNL000100

Installation appareillage lectrique en surface

A/G Electrical/Electrical Equipment

CNS036100

Systme de traitement d'eau

CNM000100

Installation de l'instrumentation

CNL152125

Installation transformateur(s) #1

CNL252125

Installation transformateur(s) #2

CNM032200

Installation systme de commande (DCS)

Water Treatment System


Instrumentation Installation
Install GSU Tranformer(s) #1
Install GSU Transformer(s) #2
Install Distributed Control System

Mise en service (Commissioning & Start-up)


SUZ000100

Essais et mise en service

SUZ052125

Essai et mise sous-tension transformateur #1

SUZ052150

Essai et mise sous-tension transformateur #2

SUZ148100

Mise en service TAG/A #1

SUZ248100

Mise en service TAG/A #2

SUZ148125

Vrification finale GE TAG/A #1

SUZ248125

Vrification finale GE TAG/A #2

SUZ156100

Vrification et mise en service chaudire #1

SUZ256100

Vrification et mise en service chaudire #2

SUZ178100

Mise en service TAV/A #1

SUZ278100

Mise en service TAV/A #2

SUZ148150

Premire mise feu TAG/A #1

Start Date
Finish Date
Data Date
Run Date

01APR03
29MAY06
01APR03
21JAN03 08:38

Start-up & Commissioning


Test & Energize GSU Transformer #1
Test & Energize GSU Transformer #2
Commission CTG #1
Commission CTG #2
GE Check-out CTG #1
GE Check-out CTG #2
Checkout/Commission HRSG #1
Checkout/Commission HRSG #2
Commission STG #1
Commission STG #2
Initial Fire Combustion Turbine #1

Early Bar
Progress Bar
Critical Activity

553D

Sheet 3 of 4

Algerian Energy Co.


Projet Skikda 600-800 MW
Proposition - chancier

Primavera Systems, Inc.

SNC-Lavalin Constructors International Inc

Activity
ID

Activity
Description

-1 1 2

Months
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Mise en service (Commissioning & Start-up)


SUZ148175

Prise en charge partielle TAG/A #1

SUZ248150

Premire mise feu TAG/A #2

SUZ156150

Chasses de vapeur et restauration de tuyauterie

SUZ248175

Prise en charge partielle TAG/A #2

SUZ256150

Chasses de vapeur et restauration de tuyauterie

SUZ128100

Vapeur au condenseur by-pass #1 (contournement)

SUZ228100

Vapeur au condenseur by-pass #2 (contournement)

Steam to Condenser By-pass Operation #2

SUZ178125

Premier dmarrage TAV/A #1

Initial Roll Steam Turbine Generator #1

SUZ178150

Synchronisation rseau TAV/A #1

Synchronize Steam Turbine Generator #1

SUZ178175

Monte en puissance TAV/A #1

Steam Turbine Generator #1 Loading

SUZ278125

Premire mise en service TAV/A #2

Initial Roll Steam Turbine Generator #2

SUZ278150

Synchronisation rseau TAV/A #2

Synchronize Steam Turbine Generator #2

SUZ278175

Monte en puissance TAV/A #2

Steam Turbine Generator #2 Loading

SUZ000800

Ajustements fins de la centrale

SUZ000860

Essais de performance et de consommation

SUZ000900

Essai de la centrale

SUZ000880

Essais d'mission atmosphrique

SUZ000890

Vrification des niveaux sonores

SUZ000950

Periode de correction

Start Date
Finish Date
Data Date
Run Date

01APR03
29MAY06
01APR03
21JAN03 08:38

Partial Load Run - Combustion Turbine #1


Initial Fire Combustion Turbine #2
Steam Blows & Pipe Restoration - HRSG #1
Partial Load Run - Combustion Turbine #2
Steam Blows & Pipe Restoration - HRSG #2
Steam to Condenser By-pass Operation #1

Plant Fine Tuning


Net Generation and Heat Rate Acceptance Test
Plant Testing
Emissions Testing
Noise Level Testing

Early Bar
Progress Bar
Critical Activity

553D

Sheet 4 of 4

Algerian Energy Co.


Projet Skikda 600-800 MW
Proposition - chancier

Primavera Systems, Inc.

SNC-Lavalin Constructors International Inc