Professional Documents
Culture Documents
Classification of Drilling Systems PDF
Classification of Drilling Systems PDF
SEPTEMBER 2012
Copyright 2012
American Bureau of Shipping
ABS Plaza
16855 Northchase Drive
Houston, TX 77060 USA
Foreword
Section 2
Section 3
Drilling Systems
Section 4
Section 5
Section 6
Section 7
Section 8
Section 9
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
This Guide is to be used in conjunction with other applicable ABS Rules and Guides, codes and standards
as referenced therein, and applicable national regulations.
ABS Classification continues to provide the offshore industry with a pathway toward agreement by Regulatory
Authorities. However, the Owner/Operators specific request for compliance with applicable requirements
of Flag or Coastal State Authorities affecting the drilling systems is to be filed as an addendum to the
Request for Classification.
The following changes to the Guide were incorporated into the September 2012 CDS Guide:
General
None
Section 1
Editorial changes.
Section 2
ii
Editorial changes.
Section 3
Revised accumulator hydraulic capacity requirements for subsea and surface BOP stack.
Revised choke and kill systems requirements, and their control system requirements.
Kill Unit
Personnel Baskets
Section 4
Allowance of PDAs.
Allowance of limited use of ABS Type Approval Program for selected equipment.
Section 5
Clarified the requirements for Flexible Lines/Hydraulic Hoses to consider different service categories.
Clarified the requirements for Thread Joints and Connections and Socket Welds.
Section 6
Section 7
Section 8
Editorial changes.
Section 9
Appendix 1
iii
Appendix 2
Updated the contents to provide additional parameters for Appendix 2 Example of Manufacturers
Affidavit of Compliance
Appendix 3
Appendix 4
None
Appendix 5
Appendix 6
iv
None
Table of Contents
1.1
Process ........................................................................................... 1
1.3
1.5
1.7
3.3
3.5
3.7
5.3
Applications ..................................................................................... 4
7.3
7.5
Scope .............................................................................................. 5
7.7
Alternatives...................................................................................... 6
7.9
9.3
11
13
15
15.3
17
Units .................................................................................................. 10
19
Fees .................................................................................................. 10
21
Disagreement .................................................................................... 10
21.1
21.3
Surveyor ........................................................................................ 10
SECTION 2
23
Limitation of Liability.......................................................................... 10
25
References ........................................................................................ 10
27
Definitions ......................................................................................... 11
29
vi
General .......................................................................................... 23
1.3
1.5
1.7
Materials ........................................................................................ 24
1.9
1.11
Design Specifications........................................................................ 24
SECTION 3
1.1
5.1
5.3
5.5
5.7
Design Conditions.......................................................................... 26
5.9
5.11
7.3
7.5
7.6
7.7
7.9
7.11
7.13
7.15
7.17
7.19
7.21
7.23
7.25
7.27
3.3
3.5
3.7
3.9
3.11
5.3
5.5
5.7
6.3
11
13
15
17
9.3
9.5
9.7
Derricks/Masts ............................................................................... 70
11.3
11.5
11.7
11.9
11.11
Miscellaneous Equipment.............................................................. 83
13.3
13.5
13.7
13.9
13.11
Operational Procedures................................................................. 86
15.3
15.5
15.7
17.3
19
21
23
21.1
21.3
21.5
23.3
Drip Pans....................................................................................... 92
vii
SECTION 4
3.3
3.5
3.7
3.9
TABLE 1
SECTION 5
SECTION 6
3.1
3.3
3.5
3.7
Materials.......................................................................................... 127
5.1
5.3
1.1
1.3
1.5
1.7
3.3
11
viii
9.3
11.3
11.5
11.7
13
15
SECTION 7
13.3
15.3
1.1
1.3
3.3
11
13
11.1
11.3
11.5
SECTION 9
13.1
SECTION 8
3.1
3.3
3.5
3.7
3.9
3.11
3.13
5.3
1.3
ix
5.1
5.3
5.5
7.3
7.5
SECTION
Classification
The requirements for conditions of Classification for entire drilling units and offshore structures are contained
in the ABS Rules for Conditions of Classification Offshore Units and Structures (Part 1). Additional
requirements specific to a drilling system, its subsystems, equipment or components are contained in this Guide.
1.1
Process
The term Classification, as used herein, indicates that drilling systems, subsystems, equipment, and/or
components have been designed, constructed, installed, and surveyed in compliance with this Guide, in
conjunction with other applicable ABS Rules and Guides, codes and standards as referenced therein, and
applicable national regulations. The continuance of Classification is dependent on the fulfillment of
requirements for surveys after construction.
The Classification process consists of:
a)
The development of Rules, Guides, standards and other criteria for the design, construction, installation
and maintenance of drilling systems, subsystems, equipment, and/or components;
b)
The review of the design and survey during and after construction to verify compliance with such
Rules, Guides, standards or other criteria;
c)
The assignment and registration of Class when such compliance has been verified, and;
d)
The issuance of a renewable Classification certificate, with annual endorsements, valid for five (5)
years.
The Rules, Guides and standards are, in general, developed by the International Association of Classification
Societies and ABS staff and passed upon by committees made up of naval architects, ocean and marine
engineers, shipbuilders, engine builders, steel makers, process engineers and by other technical, operating and
scientific personnel associated with the worldwide maritime industry. Theoretical research and development,
established engineering disciplines, as well as satisfactory service experience are utilized in their development
and promulgation. ABS and its committees can act only upon such theoretical and practical considerations
in developing Rules and standards.
ABS Surveyors apply normally accepted examination and testing standards to those items specified for each
survey by the Rules; construction/manufacturing procedures, safety procedures and construction supervision
remain the responsibility of the shipyard, the offshore unit or structures repairer, manufacturer, Owner/Operator
or other client.
For Classification, the drilling system, subsystems, equipment, and/or components are to comply with the
requirements of this Guide, in conjunction with all other applicable ABS Rules and Guides, codes and
standards as referenced therein.
1.3
Section
ABS will release certain information to the offshore unit or structures underwriters for underwriting purposes.
Such information includes text of overdue conditions of Classification, survey due dates and certificate
expiration dates. The Owner/Operator will be advised of any request and/or release of information. In the
case of overdue conditions of Classification, the Owner/Operator will be given the opportunity to verify
the accuracy of the information prior to release.
ABS may release offshore unit or structure-specific information related to the Classification and statutory
certification status. This information may be published on the ABS website or by other media and may
include the offshore unit or structure classification, any operating restrictions noted in the ABS Record, the
names, dates and locations of all surveys performed by ABS, the expiration date of all Class and statutory
certificates issued by ABS, survey due dates, the text of conditions of Classification (also known as outstanding
recommendations), transfers, suspensions, withdrawals, cancellations and reinstatements of Class, and other
related information as may be required.
1.5
1.7
Scope of Classification
Nothing contained in any certificate or report is to be deemed to relieve any designer, builder, owner,
manufacturer, seller, supplier, repairer, operator, other entity or person of any warranty, express or implied.
Any certificate or report evidences compliance only with one or more of the Rules, Guides, standards or
other criteria of the American Bureau of Shipping, and is issued solely for the use of ABS, its committees,
its clients or other authorized entities.
Nothing contained in any certificate, report, plan or document review or approval is to be deemed to be in
any way a representation or statement beyond those contained in 1/1.5. ABS is not an insurer or guarantor
of the integrity or safety of a drilling system, subsystem, equipment or component. The validity, applicability
and interpretation of any certificate, report, plan or document review or approval are governed by the
Rules, Guides and standards of the American Bureau of Shipping, who shall remain the sole judge thereof.
ABS is not responsible for the consequences arising from the use by other parties of the Rules, Guides,
standards or other criteria of the American Bureau of Shipping, without review, plan approval and survey
by ABS.
The term approved is to be interpreted to mean that the plans, reports or documents have been reviewed
for compliance with one or more of the Rules, Guides, standards or other criteria of ABS.
This Guide is published with the understanding that responsibility for shutting down drilling operations,
beyond the limit specified in the drilling system design basis, does not rest upon the Committee.
Section
3.1
3.3
Suspension of Class
Class will be suspended and the Certificate of Classification will become invalid from the date of any use,
operation or other application of any drilling system, subsystems, equipment, and/or components for which
it has not been approved and which affects or may affect Classification or the structural integrity, quality or
fitness for a particular use or service.
Class will be suspended and the Certificate of Classification will become invalid in any of the following
circumstances affecting the drilling system:
i)
If Continuous Survey items which are due or overdue at the time of Annual Survey are not
completed and no extension has been granted,
ii)
If the Periodical Surveys required for maintenance of Class, other than Annual or Special Periodical
Surveys, are not carried out by the due date and no Rule-allowed extension has been granted, or
iii)
If any damage, failure or deterioration repair has not been completed as recommended.
Class will be subject to a suspension procedure if recommendations issued by the Surveyor are not carried
out and/or completed by their due dates and no extension has been granted.
Class may be suspended, in which case the Certificate of Classification will become invalid, if proposed
repairs, as referred to in 1/15.1, have not been submitted to ABS and agreed upon prior to commencement.
Class is automatically suspended and the Certificate of Classification is invalid in any of the following
circumstances:
3.5
i)
If the Annual Survey is not completed by the date which is three (3) months after the due date,
ii)
If the Special Periodical Survey is not completed by the due date, unless the drilling system is
under attendance for completion prior to resuming operation. Under exceptional circumstances,
consideration may be given for an extension of the Special Survey, provided the drilling system is
attended and the attending Surveyor so recommends. Such an extension shall not exceed three (3)
months.
Lifting of Suspension
Class will be reinstated after suspension for overdue surveys upon satisfactory completion of the overdue
surveys. Such surveys will be credited as of the original due date. Class will be reinstated after suspension
for overdue recommendations upon satisfactory completion of the overdue recommendation. Class will be
reinstated after suspension for overdue continuous survey items upon satisfactory completion of the overdue
items.
Section
3.7
Cancellation of Class
If the circumstances leading to suspension of Class are not corrected within the time specified, Class will
be cancelled.
Class is cancelled immediately when drilling systems, subsystems, equipment, and/or components are operated
without having completed recommendations which were required to be dealt with before the drilling system
was brought back into service.
When Class has been suspended for a period of three (3) months due to overdue Annual, Special or other
periodical surveys required for maintenance of Class; overdue Continuous Survey items; or overdue outstanding
recommendations, the CDS Notation will be canceled. A longer suspension period may be granted for drilling
systems, subsystems, equipment, and/or components which are either laid up, awaiting disposition of a casualty
or under attendance for reinstatement.
Class Notation
5.1
5.3
7.1
Applications
This Guide contains provisions for the Classification of offshore drilling systems, subsystems, equipment,
and/or components that are used for hydrocarbon well drilling, completion, workover, and/or well testing
or supporting such activities on mobile offshore drilling units (MODUs), offshore installations, tendering
vessels, and other structures that are classed by ABS. This Guide is intended for use in conjunction with
the latest edition of the following or other applicable ABS Rules and Guides:
ABS Rules for Building and Classing Mobile Offshore Drilling Units (MODU Rules)
ABS Guide for Building and Classing Mobile Offshore Units (MOU Guide)
ABS Rules for Building and Classing Offshore Installations (Offshore Installations/FOI Rules)
ABS Guide for Building and Classing Floating Production Installations (FPI Guide)
ABS Rules for Building and Classing Steel Vessels (Steel Vessel Rules)
ABS Rules for Building and Classing Facilities on Offshore Installations (Facilities Rules)
If specifically requested by the Owner/Operator, this Guide can also be used as a basis for acceptance or
certification under the requirements of other Administrations. An Owner/Operator who requires a drilling
system to be evaluated for compliance with other national regulations should contact ABS.
If specifically requested by the manufacturers, Owner/Operator, or designers, ABS can provide approval of
individual equipment or component associated with drilling systems or subsystems in accordance with the
requirements of this Guide (see 4/3.7), and where the installation unit may not be classed with ABS.
Section
7.3
Effective Date
This Guide and subsequent changes to this Guide are to become effective on the date specified by
ABS. In general, the effective date is not less than six months from the date on which the Guide is
published and released for its use. However, ABS may bring into force the Guide or individual
changes before that date, if necessary or as appropriate.
7.3.2
Where design of drillings systems, subsystems, equipment or components comply with the
requirements of this Guide at the time of approval and/or construction, no retroactive application
of later requirement changes to such drilling systems, subsystems, equipment or components will
be required unless considered necessary or appropriate.
7.5
Diverter System
Riser Joints
Connectors
Burner Booms
Pressure Vessels Associated with Drilling and Well Control, Tensioning, and Fluid Storage
Section
7.7
Control Systems for Well Control, Drilling Support and Support Systems
Alternatives
7.7.1
7.7.2
National Standards
i)
The Committee will consider special arrangements or design of drilling systems and their
equipment which can be shown to comply with standards recognized in the country provided
that the proposed standards are not less effective.
ii)
7.7.3
Novel Features
Drilling systems which contain novel features of design to which the provisions of this Guide are
not directly applicable may be classed, when approved by the Committee, on the basis that this
Guide, insofar as applicable, has been complied with and that special consideration has been given
to the novel features, based on the best information available at that time. Justifications of the
novel features can be accomplished by applying 1/7.7 of this Guide.
7.7.4
ii)
ABS will consider the application of risk evaluations for alternative arrangements and
novel features in the design of the drilling system, subsystems, equipment or components,
verification surveys during construction, and surveys for maintenance of Class.
iii)
When applied, risk assessment techniques are to demonstrate that alternative arrangements
and/or novel features provide acceptable levels of safety in line with current offshore and
marine industry practice.
iv)
The ABS Guidance Notes on Review and Approval of Novel Concepts, ABS Guidance Notes
on Risk Assessment Applications for the Marine and Offshore Oil and Gas Industries, and
ABS Guide for Risk Evaluations for the Classification of Marine-Related Facilities provide
guidance to ABS clients on how to prepare a risk evaluation to demonstrate equivalency
or acceptability for a proposed drilling system design.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
7.9
v)
Portions of the drilling system or any of its subsystems, equipment or components not
explicitly included in the risk evaluation submitted to ABS are to comply with any applicable
part of the ABS Rules and Guides.
vi)
If any proposed alternative arrangement or novel feature affects any applicable requirements
of Flag and Coastal State, it is the responsibility of the Owner/Operator to discuss with
the applicable authorities the acceptance of alternatives based on risk evaluations.
Risk Assessment
Risk assessment may be used to demonstrate that alternatives and novel features provide acceptable levels of
safety in line with current offshore and marine industry practice.
i)
When this optional risk assessment is applied at the specific request of the designer or
manufacturer, all hazards that may affect the drilling system or any of its subsystems, equipment
or components are to be identified.
ii)
iii)
The objective of the hazard identification is to identify areas of the design that may require the
implementation of further risk control options in order to reduce the risk to an acceptable level.
iv)
Loss/Failure of Mooring
Blowout
Loss of Stability
Impact to Equipment
Dropped Objects
Structural Failure
Collision
Mechanical Failure
Helicopter Crash
Electrical Failure
Extreme Environment
v)
The identified risk control options (prevention and mitigation measures) deemed necessary to be
implemented are to be considered part of the design basis of the drilling system.
vi)
Appendix 4 in the ABS Guide for Risk Evaluations for the Classification of Marine-Related Facilities
contains a description of the most common hazard identification techniques. Also, Appendix 2 in
the same Guide provides an overview of how to assemble an appropriate risk assessment team.
vii)
When the risk assessment technique is considered, ABS participation in the hazard identification
meeting(s) is recommended. Tangible benefits can be derived by the participation of an ABS
representative who will later be directly involved in reviewing the designs for ABS Classification.
Other Regulations
9.1
Where authorized by the Administration of a country signatory thereto and upon request of the Owner/
Operator of a classed drilling system or one intended to be classed, ABS will survey for compliance
with the provisions of International and Governmental Conventions and Codes, as applicable.
Section
9.3
Governmental Regulations
Where authorized by a government agency and upon request of the Owner/Operator of a new or existing
drilling system, ABS will survey and certify a classed drilling system or one intended to be classed for
compliance with particular regulations of that government on their behalf.
11
IACS Audit
The International Association of Classification Societies (IACS) conducts audits of processes followed by
all of its member societies to assess the degree of compliance with the IACS Quality System Certification
Scheme requirements. For this purpose, auditors for IACS may accompany ABS personnel at any stage of
the Classification or statutory work, which may necessitate the auditors having access to the drilling
system, subsystems, equipment, and/or components or access to the premises of the builder or manufacturer.
In such instances, prior authorization for the auditors access will be sought by the local ABS office.
13
Submission of Plans
Typical documentation that is required to be submitted for drilling system, subsystems, equipment, and/or
components for the ABS Classification process is provided in Subsection 2/7 of this Guide.
i)
Section 4 provides the ABS approval process for drilling systems, subsystem, equipment, and/or
components. Subsequently, Section 4, Table 1 identifies the typical drilling system, subsystems,
equipment, and/or components that are part of the ABS Classification process.
ii)
iii)
Upon satisfactory completion of ABS review of design plans and data, ABS Engineers will issue
an ABS approval letter and an Independent Review Certificate (IRC), as specified in Section 4,
Table 1 of this Guide. This letter or certificate, in conjunction with ABS-approved documentation,
will be used and referenced during surveys. Subsequently, the ABS Surveyor will issue appropriate
survey reports.
iv)
(1 September 2012) Upon satisfactory completion of all of the required engineering design review
and survey processes (inspection, testing, installation and commissioning), ABS may issue the
Classification Certificate to the operating unit, including the Class notation CDS (abbreviation
for Classed Drilling System).
15
15.1
ii)
All repairs found necessary by the Surveyor are to be carried out to the Surveyors
satisfaction.
15.1.2 Repairs
i)
Where repairs to the drilling system, subsystems, equipment, and/or components which
may affect Classification are planned in advance to be carried out, a complete repair procedure
including the extent of the proposed repair and the need for Surveyors attendance is to be
submitted to and agreed upon by the Surveyor reasonably in advance.
ii)
Failure to notify ABS in advance of the repairs may result in suspension of the drilling
systems Classification until such time as the repair is redone or evidence is submitted to
satisfy the Surveyor that the repair was properly carried out.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
15.1.3 Representation
Nothing contained in this section or in a Rule or regulation of any government or other administration,
or the issuance of any report or certificate pursuant to this section or such a Rule or regulation, is
to be deemed to enlarge upon the representations expressed in 1/1.1 through 1/1.7 hereof, and the
issuance and use of any such reports or certificates are to be governed in all respects by 1/1.1
through 1/1.7 hereof.
15.1.4 Temporary Installation, Maintenance, Modification, Repair or Replacements
15.1.4(a) Temporary Installation
i)
ii)
iii)
ABS reserves the right to approve such equipment and is to be advised of temporary
installations.
15.1.4(b) Maintenance
i)
When the subsystems, equipment, and/or components of the drilling system are subject to
annual maintenance or inspections due to repairs by qualified personnel on the drilling
unit or by an authorized company/manufacturer offshore or onshore, ABS is to be notified
for survey of the subsystems, equipment, and/or components preferably before it is placed
into service (see Subsection 9/3).
ii)
These surveys will be carried out in accordance with API requirements or other recognized
codes/standards referenced in this Guide and are to be considered part of ABSs Annual
Survey for Drilling Systems.
15.3
For the purpose of Surveyor monitoring, the attending Surveyors are also to have access to classed
drilling systems, subsystems, equipment, and/or components at all reasonable times. Such access
may include attendance at the same time as the assigned Surveyor or during a subsequent visit
without the assigned Surveyor.
ii)
The Owner/Operator or their representatives are to notify the Surveyors for inspection on occasions
when the units on which the drilling systems are installed are in dry dock or on a slipway.
iii)
The Surveyors are to undertake all surveys on classed drilling systems, subsystems, equipment, and/or
components upon request, with adequate notification, of the Owner/Operator or their representatives,
and are to report thereon to the Committee.
iv)
Should the Surveyors find occasion during any survey to recommend repairs or further examination,
notification is to be given immediately to the Owner/Operator or their representatives so that
appropriate action may be taken.
v)
The Surveyors are to avail themselves of every convenient opportunity for carrying out periodical
surveys in conjunction with surveys of damages and repairs in order to avoid duplication of work.
Section
17
19
Fees
Fees in accordance with normal ABS practice will be charged for all services rendered by ABS. Expenses
incurred by ABS in connection with these services will be charged in addition to the fees. Fees and
expenses will be billed to the party requesting that particular service.
21
Disagreement
21.1
21.3
Surveyor
In case of disagreement between the Owner/Operator or builders and the Surveyors regarding the material,
workmanship, extent of repairs or application of the Rules and Guides relating to any system classed or
proposed to be classed by ABS, an appeal may be made in writing to the Committee, who will order a
special survey to be held. Should the opinion of the Surveyor be confirmed, expense of this special survey
is to be paid by the party appealing.
23
Limitation of Liability
The combined liability of the American Bureau of Shipping, its committees, officers, employees, agents or
subcontractors for any loss, claim or damage arising from its negligent performance or nonperformance of
any of its services or from breach of any implied or express warranty of workmanlike performance in
connection with those services, or from any other reason, to any person, corporation, partnership, business
entity, sovereign, country or nation, will be limited to the greater of a) $100,000 or b) an amount equal to
ten times the sum actually paid for the services alleged to be deficient.
The limitation of liability may be increased, up to an amount twenty-five times the sum paid for services,
upon receipt of Clients written request at or before the time of performance of services, and upon payment
by Client of an additional fee of $10.00 for every $1,000.00 increase in the limitation.
25
10
ABS Guidance Notes on Review and Approval of Novel Concepts (Novel Concepts Guide)
ABS Guide for Risk Evaluations for the Classification of Marine-Related Facilities
ABS Guidance Notes on Risk Assessment Applications for the Marine and Offshore Oil and Gas Industries
ABS Guide for Surveys Using Risk-Based Inspections for the Offshore Industry (RBI Guide)
Section
EN European Norm
UL Underwriters Laboratory
ABS is prepared to consider other recognized codes, standards, alternative design methodology and industry
practice, on a case-by-case basis, with justifications as indicated in 1/7.7 of this Guide.
27
11
Section
Autoshear System: A system that is designed to automatically shut-in the wellbore in the event of a disconnect
of the LMRP. When the autoshear is armed, disconnect of the LMRP closes the shear ram on BOP stack.
Auxiliary Line: A conduit (excluding choke and kill lines) attached to the outside of the drilling riser main
tube (e.g., hydraulic supply line, buoyancy control line, mud boost line).
Backpressure (Casing Pressure, Choke Pressure): The pressure existing at the surface on the casing side
of the drill string/annulus flow system.
Backup: An element or system that is intended to be used only in the event that the primary element or
system is nonfunctional.
Blind Rams: See Rams
Blind-shear Rams: See Rams
Blowout: An uncontrolled flow of well fluids/gas and/or formation fluids/gas from the wellbore to the
surface or into lower pressured subsurface zones (underground blowout).
Blowout Preventer (BOP): The equipment installed at the wellhead to prevent the escape of fluids under
pressure either in the annular space between the casing and drill pipe or in an open hole during drilling and
completion operations.
Blowout Preventer (BOP) Handling Crane: Gantry-type crane used to move BOP from storage location to
BOP transporter/skidder location.
Blowout Preventer (BOP) Operating and Control System: System of pumps, valves, accumulators, fluid storage
and mixing equipment, manifold, piping, hoses, control panels and other items necessary to hydraulically
operate the BOP equipment.
Blowout Preventer (BOP) Assembly: The complete assembly of BOP stack, frame, accumulators, pods, valves,
piping, connectors, jumpers, control systems, ROV interface panels, control piping, etc.
Blowout Preventer (BOP) Seafixing: Mechanism to maintain BOP stack in secured position on drilling unit.
Blowout Preventer (BOP) Stack: The complete assembly of well control equipment including preventers,
spools, valves, and nipples connected to the top of the casinghead.
Blowout Preventer (BOP) Stack Frame: Steel frame to which the lower stack is mounted for handling and
mating with LMRP. Also serves as a support structure to mount various subsea equipment, such as subsea
accumulators and control pods.
Blowout Preventer (BOP) Transporter/Skidder: Skidding mechanism to position the BOP for deployment,
retrieval or storage.
Buffer Tank: A targeted, horizontal or vertical, cylindrical tank that changes the direction of fluid flow
downstream of the choke and serves as a flow director to the flare line, gas buster or mud-gas separator.
Bulk Storage: Tanks that are designed for storage of bulk materials for drilling fluid and cement mixing
(barite, bentonite, cement, etc.).
Buoyancy Equipment: Devices added to riser joints to reduce their apparent weight, thereby reducing riser
top tension requirements.
Burner Boom: Boom which extends over the deck edge to flare hydrocarbon from kick circulation or well
test operations.
Casinghead/Spool: The part of the wellhead to which the BOP connector is connected.
Casing Stabbing Board: Folding platform located in the derrick which positions the stabbing hand (pipe
stabber) while running casing.
Catastrophic Release: Major hydrocarbon release that results from uncontrolled developments and that
may lead to serious danger to personnel, asset, and environment.
Catwalk Ramp (Riser Skate): Conveyer transport system used to move riser sections, drill pipes, casing or
tool joints from the lower deck storage to the drill floor.
12
Section
Cementing Manifold: Used to direct high pressure cement through the cement standpipe.
Cement Pump: High pressure positive-displacement-type pump used for cementing operations, often connected
to the kill line for emergency kill operations, usually smaller capacity than mud pump.
Choke: A device with either a fixed or variable orifice used to control the rate of flow of liquids and/or gas.
Chokes are also used to control the rate of the flow of drilling mud out of the hole when the well is closed
in with the blowout preventer and a kick is being circulated out of the hole.
Choke Line: The high-pressure piping (flexible lines, rigid piping, valves, connectors, fittings, etc.) between
the mud pumps and BOP outlets or wellhead outlets.
Choke Line Valve: The valve(s) connected to and a part of the BOP stack that allows fluids flow to the
choke manifold.
Choke Manifold: An assembly of valves, chokes, gauges, and piping components through which drilling
fluid is circulated when the blowout preventer is closed to control the pressure encountered during a kick.
Circulation Head: Accessory attached to the top of the tubulars to form a connection with the mud system
to permit circulation of drilling mud.
Clamp Connection: A pressure sealing device used to join two items without using conventional bolted
flange joints. The two items to be sealed are prepared with clamp hubs. These hubs are held together by a
clamp containing a minimum of four bolts.
Classified Area: A location in which flammable gases or vapors are or may be present in the air in
quantities sufficient to produce explosive or ignitable mixtures (see the ABS MODU Rules, API RP 500 or
API RP 505 for additional details).
Closing Unit: The assembly of pumps, valves, lines, accumulators, and other items necessary to open and
close the BOP equipment.
Computer-Based System: A system of one or more microprocessors, associated software, peripherals and
interfaces.
Control Panel/Console: Main operator interface for various installation systems (may be hydraulic, electric,
electronic, mechanical, pneumatic, or any combination thereof).
Control Manifold: An assembly of valves and piping to control the flow of hydraulic fluid to operate the
various components of systems, equipment or components.
Control Panel, Remote: A panel containing a series of controls that will operate the valves on the control
manifold from a remote point.
Control Pod: An assembly of subsea valves and regulators that when activated from the surface will direct
hydraulic fluid through special apertures to operate the BOP equipment.
Control Stations: Spaces containing the following, as applicable:
Battery room
Fire pumps
Control Systems: An assembly of devices interconnected or otherwise coordinated to convey the command
or order.
Crown: Upper section of the derrick
Crown Block: Assembly of sheaves mounted at the derrick top (crown) through which the drilling line is reaved.
Deadline Anchor: Device to securely fasten one end of drill line to the drill floor or derrick structure.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
13
Section
Deadman System: A system that is designed to automatically close the wellbore in the event of a simultaneous
absence of hydraulic supply and signal (control and communication) transmission capacity in both subsea
control pods.
Degasser: Device used to remove entrained gas from a drilling fluid in normal well circulation.
Desander: Centrifugal device for removing sand from drilling fluid.
Desilter: Centrifugal device used for removing silt from drilling fluid.
Derrick (Mast): Main load-bearing structure in drilling unit used as support structure for various equipment
associated with hoisting, lifting, handling, etc.
Design Approved Products (PDA): See 1-1-A2/5.1.3 of the ABS Rules for Conditions of Classification
Offshore Units and Structures (Part 1).
Design Pressure: The pressure used in the design of pressure-retaining equipment or piping systems for
the purpose of determining the minimum permissible thickness or physical characteristics of the different
parts of the pressure-retaining equipment or piping systems. When applicable, static head and other external
loads (e.g., bending, torsional, tension, compression, temperature gradient, etc.) are to be added to the design
pressure to determine the thickness of any specific part of the pressure-retaining equipment or piping systems.
Diverter: A device attached to the wellhead or marine drilling riser to close the vertical access in order to
prevent upward flow of well fluids and direct flow into a line away from the rig floor.
Diverter Control System: The assemblage of pumps, accumulator bottles, manifolds, control panel, valves,
lines, etc., used to operate the diverter system.
Diverter System: The assemblage of an annular sealing device, flow control means, vent system components,
and control system that facilitates closure of the upward flow path of well fluids and opening of the vent to
atmosphere.
Diverter Vent Line/Diverter Piping: The conduit which directs the flow of gas and wellbore fluids away
from the drill floor to the atmosphere.
Drape Hoses (Moonpool Line): A flexible line connecting a choke, kill, and auxiliary line terminal fitting
on the telescopic joint to the appropriate piping on the rig structure. A U-shaped bend in this line allows for
relative movement between the vessel and the outer barrel of the telescopic joint as the vessel moves.
Drawworks: Large winch typically located on the drill floor area used to raise and lower the drill string,
top drive assembly by taking in or paying out the drilling line through the crown block and traveling block.
Drill Floor Substructure: The foundation structure(s) on which the derrick, rotary table, drawworks, and
other drilling equipment are supported.
Drill Pipe Safety Valve: A full-opening valve located on the rig floor with threads to match the drill pipe
connections in use. This valve is used to close off the drill pipe to prevent flow from the well.
Drillers Cabin: An enclosed space on or near the drill floor that provides clear view for the driller to
monitor and control drilling activities.
Drilling Spool: A fitting placed in the blowout preventer stack with internal diameters at least equal to the
bore of the BOP to provide space between preventers with smaller side outlets for facilitating stripping and
other operations, to permit attachment of choke and kill lines, and for localizing possible erosion by fluid
flow to the spool.
Dump Tank: Calibrated tank used to measure the volume of a liquid, may be drilling mud or reservoir fluids.
Electrical Control System: Control systems that are based on relays and analog discrete components without
a central processor unit. Manual switches, relays and potentiometers are used for control of the equipment.
In most situations, hydraulic and/or pneumatic medium is controlled by the electrical control system.
Elevator, Drilling: Hinged clamp-type device used to grasp drill pipe or casing for lifting by the drilling
hook, may be either manually or hydraulically/pneumatically operated.
Elevator, Personnel: Lifting device used for rig personnel, may be on or off the drill floor.
14
Section
Equipment: Structure or device designed to perform a function, individually or combined into system.
Escape Routes: Designated path used by personnel to evade an immediate danger and ultimately leads to a
temporary refuge or muster station.
Finger Board: A rack located in the derrick that supports the top of the stands of pipe stacked in the derrick.
Fill-up Valve: A special riser joint having a valve means to allow the riser annulus to be opened to the sea.
To prevent riser pipe collapse, an automatic actuator controlled by a differential-pressure sensor may open
the valve.
Flammable Fluid: Any fluid, regardless of its flash point, capable of feeding a fire. Examples are diesel
fuel, hydraulic oil (oil-based), lubricating oil, crude oil, or hydrocarbons.
Flash Point: The minimum temperature at which a combustible liquid gives off vapor in sufficient
concentration to form an ignitable mixture with air near the surface of the liquid or within the vessel used,
as determined by the test procedure and apparatus specified in NFPA 30.
Flex Joint: A steel and elastomer assembly having central through-passage equal to or greater in diameter
than the riser bore that may be positioned in the riser string to reduce local bending stresses.
Flexible Lines/Hydraulic Hoses: Conduits that can accommodate the relative motion and/or vibration
encountered on the drilling facility and are used to transfer fluids (mud, cement, hydraulic fluids, etc.).
Typical uses for flexible lines and/or hydraulic hoses within the drilling facility are:
Cementing hoses
Choke and kill flexible lines, and auxiliary lines (drapes and jumpers)
Floating Installation: An offshore facility designed to provide hydrocarbon processing and/or hydrocarbon
storage, and offload hydrocarbons. The term is used to generically identify a buoyant facility that is sitespecific. The installation is securely and substantially moored so that it cannot be moved without a special
effort.
Gimbal: Support for the riser spider which allows some angular movement of the spider and riser relative
to the rig support structure.
Gooseneck: Curved connection between the rotary hose and the swivel or top drive.
Hazardous Area: See Classified Areas.
Heave: Vessel motion in the vertical direction due to marine environment.
High-Pressure High-Temperature (HPHT): Wells with a potential pressure greater than 103.43 MPa
(15,000 psi) at the wellhead, or with a potential reservoir temperature of greater than 177C (350F).
Hook, Drilling: Hook-shaped lifting device attached to the traveling block from which the swivel (or top drive)
is suspended.
Horizontal to Vertical Equipment: Equipment to move tubulars from/to horizontal position to/from vertical
position for stand building or breaking, and tubulars operations.
Hydraulic Cylinder: Mechanical device used to convert hydraulic fluid pressure to linear action.
Hydraulic Hoses: Conduits that can accommodate the relative motion, and/or vibration encountered on a
drilling facility and are used to transfer fluid for hydraulic system functions.
Hydraulic Power Unit (HPU): Skid-mounted systems used to provide hydraulic power, usually comprised
of a hydraulic fluid reservoir, filters, hydraulic pump, motor and control.
Hydrocarbon: A compound of hydrogen and carbon, such as any of those that are the chief components of
petroleum and natural gas, can be liquid or gas.
Hydrogen Sulfide (H2S): A highly toxic, flammable, corrosive gas sometimes encountered in hydrocarbonbearing formations.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
15
Section
Hydrogen Sulfide (Sour) Service: Refers to equipment designed to resist corrosion and hydrogen embrittlement
caused by exposure to hydrogen sulfide.
Ignitable Mixture: A mixture that is within the flammable range (between the upper and lower limits) and
is therefore capable of propagation of flame away from the source of ignition.
Inside Blowout Preventer (IBOP): Check valve installed in drill string to prevent a blowout inside the drill
string. Flow is possible only downward, allowing mud to be pumped in but preventing any flow back up
the drill string.
Iron Roughneck: Tool with automated combination of spinning and torqueing for make-up or break-down
of drill string pipes during drilling operation.
Jumper Line: A flexible section of choke, kill, or auxiliary line that provides a continuous flow around a
flex/ball joint while accommodating the angular motion at the flex/ball joint.
Kelly: The uppermost component of the drill string; the kelly is an extra-heavy joint of pipe with flat or
fluted sides that is free to move vertically through a kelly bushing in the rotary table; the kelly bushing
imparts torque to the kelly and thereby the drill string is rotated.
Kelly Bushing: Device which imparts torque to the kelly from the master bushing and permits vertical
movement of the kelly.
Kelly Cock: A valve immediately above the kelly that can be closed to confine pressures inside the drill string.
Kelly Spinner: Pneumatically-operated device mounted to the top of the kelly used to spin up the kelly for
making connections on a rotary table-type rig.
Kelly Valve, Lower: A full-opening/full-closing valve installed immediately below the kelly, with outside
diameter equal to the tool joint outside diameter.
Kick: Unscheduled, unwanted entry of water, gas, oil or other formation fluid into wellbore. It occurs because
pressure exerted by the column of drilling fluid is not great enough to overcome the pressure exerted by the
fluids in the formation drilled. If prompt action is not taken to control the kick or kill the well, a blowout
will occur.
Kill: In drilling/well servicing, to prevent a threatened blowout by taking suitable preventative measures
(e.g., to shut in well with blowout preventer, circulate kick out, and increase weight of drilling/completion/
workover fluid).
Kill Line: The high-pressure piping (flexible lines, rigid piping, valves, connectors, fittings, etc.) between
the pumps (cement or mud pumps) and BOP outlets or wellhead outlets.
Kill Unit: A unit to pump kill mud to kill the well.
Links, Drilling (Bell Nipple): Strong rods which connect the drilling elevators to the hook and allow
movement for the elevator to be pushed out of the way when not in use.
Lower Explosive Limit (L.E.L.): The lowest concentration of combustible vapors or gases, by volume in
mixture with air, which can be ignited at ambient conditions.
Lower Marine Riser Package (LMRP): Part of the blowout preventer stack assembly; usually contains LMRP
connector, one or more annular-type preventers, lower flex joint, riser adapter, and MUX control pods.
Lower Marine Riser Package (LMRP) Connector: Hydraulic connector used to securely latch the LMRP to
the BOP stack.
Lower Marine Riser Package (LMRP) Frame: Structural frame which is used for handling of the LMRP
and integration with the BOP stack. It also serves as a support structure to mount various subsea equipment
such as subsea accumulators and control pods.
Machinery Spaces of Category A: All spaces which contain internal combustion-type machinery used either:
16
For other purposes where such machinery has in the aggregate a total power of not less than 375 kW; or
Which contain any oil-fired boiler or oil fuel unit; and trunks to such spaces.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
Machinery Spaces (other than Category A): All spaces containing machinery, boilers, and other fired processes,
oil fuel units, steam and internal combustion engines, generators, and major electrical machinery, oil filling
stations, refrigerating, stabilizing, ventilation, and air-conditioning machinery and similar spaces.
Manifold: An accessory system of piping to a main piping system (or another conductor) that serves to
divide a flow into several parts, to combine several flows into one, or to reroute a flow to any one of several
possible destinations.
Manipulator Arm: Mechanism to guide tubulars from/to well center to/from the V-door.
Manriding Winch: Winch used for personnel lifting operations.
Marine Drilling Riser System: The extension of the well bore from the subsea BOP stack to the floating
drilling vessel which provides for fluid returns to the drilling vessel, supports the choke, kill, and control lines,
booster lines, auxiliary lines, guides tools into the well, and serves as a running string for the BOP stack.
Master Bushing: Device which imparts torque from the rotary table to the kelly bushing and accepts the slips.
Maximum Allowable Working (Operating) Pressure (MAWP) or Rated Working Pressure (RWP): The
maximum internal pressure equipment or system is designed to operate or work and to contain and/or
control the pressure.
Minimum Design Temperature (MDT): The lowest predictable metal temperature occurring during normal
operation including start-up, shut-down and ambient situation is to be used.
Monkey Board: Elevated platform on the derrick structure for the support of the derrickman to place and/or
withdraw tubulars into the finger board.
Mud Agitator: Device to mix, or maintain mixture of, drilling mud in the mud pits.
Mud Boost Line: An auxiliary line which provides supplementary fluid supply from the surface and injects it
into the riser at the LMRP to assist in the circulation of drill cuttings up the marine drilling riser, when required.
Mud-Gas Separator (Poor Boy): A vessel for removing free gas from the drilling fluid returns, generally
used when circulating a gas kick out of the well.
Mud Pump: Large high-pressure pump used to circulate drilling fluid, usually positive-displacement type.
Multiplex (MUX) Control System: A system utilizing electrical or optical conductors in an armored subsea
umbilical cable such that, on each conductor, multiple distinct functions are independently operated by
dedicated serialized coded commands.
Nonhazardous Areas (Unclassified Locations): Locations determined to be neither hazardous areas nor
classified areas (see Classified Area for definition).
Operating Conditions: A set of conditions (e.g., pressure, temperature, flow rates, composition, loads, etc.)
chosen for normal operation of a system, subsystem, equipment or component.
Personnel Basket: Device in which personnel ride in during lifting operations in personnel cranes, elevators,
and man-riding winches.
Pipe Rams: See Rams
Pipe Racking Mechanism: Automated equipment to place and/or withdraw tubular strands to/from the
setback area.
Power Slips: Automated slips typically controlled by the driller, usually hydraulically or pneumatically
operated.
Power Subs: A power sub is a device which moves with a hoisting system and is designed to provide
rotary power to the top of the tubular/string. It attaches to the bottom of the rotary swivel, but does not
include a rotary seal or bearing for supporting the tubular/string.
Power Swivels: A power swivel is a device which moves with a hoisting system and is designed to
provide rotary power to the top of the tubular/string. It replaces the rotary swivel and includes a rotary seal
and bearing for supporting the tubular/string weight.
17
Section
Process Area: Area where processing equipment is located to handle hydrocarbon. This includes
wellhead/manifold areas, well testing equipment.
Pulsation Dampeners: Chambered device used to dampen pressure pulsations in a fluid flow.
Pup Joint: A shorter-than-standard-length riser joint, tool joint, or drill pipe.
Rams: Mechanical device used for closing, shearing and sealing component of a blowout preventer. One of
three types blind, shear, or pipe may be installed in several preventers mounted in a stack on top of the
wellbore.
Blind rams: Blind ram ends are not intended to seal against any drill pipe or casing. The rams seal
against each other to effectively close the hole.
Shear rams:
Shear rams (non-sealing): Shear rams have a built-in cutting edge that will shear tubular that may
be in the hole.
Blind-shear rams: Blind rams with a built-in cutting edge that will shear against any drill pipe or
casing. They seal against each other to effectively close the hole.
Super shear ram: Shear rams that are capable to shear drill collars and large diameter casing. These
rams are also capable of shearing heavy wall drill pipe and tool joints. The super shear rams are
non-sealing rams.
Pipe ram is a sealing component with an indentation and packing for drill pipe, drill collars or casing
that closes the annular space between the pipe and the blowout preventer or wellhead. Separate rams
are necessary for each size (outside diameter) pipe in use. Pipe rams can include:
-
Fixed bore pipe ram: Closing and sealing component in a ram blowout preventer that is capable of
sealing only specified tubular size
Variable bore pipe ram: Closing and sealing component in a ram blowout preventer that is capable
of sealing on a range of tubular sizes
Rated Setback Load: The maximum weight of tubular goods which can be supported by the substructure in
the setback area.
Rated Working Pressure (RWP) or Maximum Allowable Working (Operating) Pressure (MAWP): The
maximum internal pressure equipment or system is designed to operate or work and to contain and/or control
the pressure.
Remotely Operated Vehicle (ROV): An unmanned vehicle for offshore subsea use.
Reels (MUX, Hotline): Large spool and winch system used to store, deploy, and retrieve flexible lines.
Riser Adapter: Crossover between riser and flex/ball joint.
Riser Chute: To guide risers from vertical position at set back area to drill-floor.
Riser Feeding Machine: A machine designed for horizontal transportation of casing, riser/slip joint and
material from pipe deck to drill floor and vice versa.
Riser Joint: A section of riser main tube having flanged connector (or equivalent ) ends fitted with a box
and pin and including choke, kill and (optional) auxiliary lines, booster lines, and their support brackets.
Riser Recoil System: A means of limiting the upward acceleration of the riser for uplanned disconnect (EDS)
or failure of a riser.
Riser Running/Handling Tool: A device that joins to the upper end of a riser joint to permit the lifting and
lowering of the joint and the assembled riser string in the derrick by the elevators.
Riser Spider Fixed: A device having retractable jaws or dogs used to support the riser string on the
uppermost coupling support shoulder during deployment and retrieval of the riser.
Riser Spider Elevator: Riser spider that is capable of being used as elevators.
18
Section
Riser Tensioners: Systems for providing and maintaining top tension on the deployed riser string to prevent
buckling.
Riser Tensioner Ring: The structural interface of the telescopic joint outer barrel and the riser tensioners.
The tensioner ring may be an integral part of the telescopic joint.
Rotary Hose (also known as Kelly Hose): Flexible hose which conducts high-pressure drilling fluids from
the standpipe to the gooseneck/swivel and kelly or top drive.
Rotary Swivel: A device hanging on the traveling hook that allows the drill string to rotate while hanging
and provide path for fluids flow.
Rotary Table: A device through which passes the bit and drill string and that transmits rotational action to
the kelly.
Rupture (or Bursting) Disc: A device designed to rupture or burst and relieve pressure at a defined pressure
and rate. The device will not close after being activated.
Safe Working Load (SWL): The maximum rated load within the lifting appliance rated capacity for the
given operating conditions.
Safety Factor: The relationship between maximum allowable stress level and a defined material property,
normally specified minimum yield strength.
Safety System Equipment: A system designed to automatically lead equipment being controlled to a
predetermined less critical condition in response to a fault which may endanger the equipment or the safety
of personnel and which may develop too fast to allow manual intervention.
Shale Shaker: Any of several mechanical devices utilizing screens and vibration that remove cuttings and
other large solids from drilling fluid.
Shear Rams: See Rams.
Sheaves: Grooved pulley for use with wire rope.
Shut-in: A condition resulting from a shutting-in of the wellbore caused by the occurrence of one or more
undesirable events and/or actions of the safety shutdown.
Shutdown: A system action that will be initiated upon signal or failure and is to result in shutdown of systems,
subsystems, equipment, component, or part of the facility.
Sour Service: Exposure to environments that contain H2S and can cause cracking of materials by the
mechanisms addressed in NACE MR0175/ISO 15156.
Spudding: The start of drilling the subsea well.
Subsystem: An assembly of interconnected or interrelated parts that performs tasks as a component as a
subset of a system.
System: An assembly of various subsystems combined into a unified whole.
Surveyor: ABSs representative on location to perform examination or inspection activities.
Survival Condition: Condition during which a unit may be subjected to the most severe environmental loading
for which the unit is designed. Drilling or similar operations may have been discontinued due to the severity
of the environmental loading. The unit may be either afloat or supported on the sea bed, as applicable.
Telescopic Joint (Slip Joint): A riser joint having an inner barrel and an outer barrel with sealing means
between. The inner and outer barrels of the telescopic joint move relative to each other to compensate for
the required change in the length of the riser string as the vessel moves due to marine environment.
Tensioning System: Systems for providing and maintaining top tension on the deployed equipment.
Test Pressure: The pressure at which the component or system is tested to verify structural and pressure
integrity.
Test Stump: Stump with wellhead profile used to support the BOP during surface pressure test operations.
Also used during BOP storage.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
19
Section
Tongs (Power or Manual): Automated or manual tongs used to torque drill pipe to final torque or to break
out pipe connections.
Top Drive: A top drive is either a power swivel or a power sub, typically with integrated pipe handling and
hoisting capabilities below the drive. The pipe handler may comprise an elevator, elevator links, link tilt
system and a pipe gripper mechanism to assist in making and breaking connections.
Transit Condition: Unit movements from one geographical location to another.
Traveling Block: Set of sheaves which move up and down in the derrick as drilling line is paid out or taken in.
Trip: The operation of hoisting the drill string from and returning it to the wellbore.
Trip Tank: Small mud tank used to keep track of the volume of mud displaced by the drill string during
trip in and trip out.
Tubulars: Tubular goods can be tubing, casing, drill pipe, and line pipe.
Tubular Feeding Machine: A machine designed for horizontal transportation of tubulars and materials
from pipe deck to drill floor and vice versa.
Type Approval: See Appendix 1-1-A2 of the ABS Rules for Conditions of Classification Offshore Units
and Structures (Part 1).
Uninterruptible Power Supply (UPS): Device supplying output power in some limited time period after
loss of input power with no interruption of the output power.
Unit Certification: Unit certification is a review of individual systems, subsystems, equipment, components,
and materials for compliance with ABS Rules, Guides, or other recognized codes and standards. This allows
these items to be placed on a vessel, marine structure or system to become eligible for classification.
Certification is a one-time review (see Appendix 1-1-A2 of the ABS Rules for Conditions of Classification
Offshore Units and Structures (Part 1).
Umbilical: A control hose bundle or electrical cable that typically runs from the reel onto the control pod
on the LMRP.
Upset Condition: A condition that occurs in a system, subsystem, equipment or component when an operating
variable deviates substantially from its normal operating limits. If left unchecked, this condition will result
in a threat to safety, or undesirable events, and may cause shutting-in of system, subsystems, equipment or
component.
Utility Systems: Various systems providing the supporting functions to the drilling operations. Typical utility
systems are cooling water, hot oil for heating, chemical systems for injection, hydraulic, potable water,
nitrogen generation and system, instrument air and power generation system, etc.
Vibratory Hose: A flexible hose assembly used to convey high-pressure drilling liquids between two
piping systems or between the mud-pump discharge outlet and the high-pressure mud piping system for the
purpose of attenuating noise and/or vibration, or compensating for misalignment and/or thermal expansion.
Wellhead Connector: Hydraulic connector used to securely latch the lower BOP stack to the wellhead.
Wire Rope: Cable composed of steel wires twisted around a central core of wire or fiber.
Wireline Spoolers: System consisting of a drum, motor and control system used for running or retrieving
wireline. Often skid-mounted, may be electrically, pneumatically or hydraulically operated.
Working Load: The mass of the load lifted plus the mass of the accessories (e.g., sheave blocks, hooks,
slings, etc.).
20
Section
29
AHC
BHA
BOP
Blowout Preventer
CoC
Certificate of Conformity
CTOD
CTU
CVN
Charpy V-Notch
DCS
DEMP
DN
Diameter Nominal
EDS
ESD
Emergency Shutdown
FAT
FMEA
FMECA
GA
General Arrangement
H 2S
Hydrogen Sulfide
HAZ
Heat-Affected Zone
HAZOP
HAZID
Hazard Identification
HP
High Pressure
HPHT
High-Pressure High-Temperature
I/O
Input/Output
IRC
IBOP
ITP
LEL
LMRP
LP
MT
MAC
MASP
MAWP
MDT
21
Section
22
MDST
MIT
MRN
MTR
MUX
Multiplex Systems
NDE
Nondestructive Examination
NDT
NPS
NPT
OEM
P&ID
PO
Purchase Order
PDA
PHC
PLC
PPM
PQR
RT
Radiographic Examination
RWP
ROV
RQS
SG
Specific Gravity
SIT
SMYS
SR
Survey Report
SSL
SWL
TA
Type Approval
UT
Ultrasonic Examination
UTS
VIV
Vortex-Induced Vibration
WP
Working Pressure
WPS
SECTION
1.1
1.3
Equipment Layout
Equipment layout and work areas associated with the drilling activities are to be arranged with the following
objectives:
i)
ii)
iii)
iv)
v)
Minimizing the spread of flammable liquids and gases which may result in a hazardous event and
facilitating rapid removal of any accumulations
vi)
vii)
viii)
ix)
x)
xi)
Minimizing dropped object hazards to personnel, equipment (on facility and subsea), and structure
xii)
(1 September 2012) Protection of critical systems, subsystems, equipment and/or components from
damage during drilling operation, such as:
xiii)
Fire/gas detection, and fire-fighting equipment are to be arranged so that they are protected
from damage during drilling operations.
Equipment arrangements are to provide access for inspection and servicing and safe means of
egress from all machinery spaces.
23
Section
1.5
1.7
xiv)
The installation of electrical equipment within hazardous areas is to be in compliance with the ABS
MODU Rules. Combustion equipment and combustion engines are not to be located in hazardous
areas.
xv)
Equipment arrangement drawings are to show the location of all equipment, living quarters, all
machinery spaces, tanks, derrick, wellheads/moon pool, flare and vents, escape route, evacuation
equipment, air intake, opening to close spaces, and any fire and barrier walls.
xvi)
Additional requirements related to general arrangement and equipment layout are also to consider the
applicable requirements of the ABS MODU Rules.
xvii)
The equipment arrangement drawings are to indicate the hazardous areas throughout the facility,
as defined in Section 4-3-6 of the ABS MODU Rules.
Overpressurization Protection
Systems, subsystems, equipment, and/or components that may have the potential of exposure to pressure
greater than for which they are designed are to be protected by suitable pressure protection devices:
i)
The drilling systems, subsystems, equipment and/or components that may have the possibility of
overpressure are to be protected by suitable means, acceptable to ABS, such as relief valves, burst
disk, fusible plug, etc., or the equivalent. The equipment will be reviewed for the specified design
parameters, as specified in the applicable Design Basis in Subsection 2/7 of this Guide.
ii)
It is to be the responsibility of the systems and equipment designers to specify and consider the
most severe combination of pressure sources, such as formation pressure, pumps, flow restriction,
static heads, hammer effects, fire and/or thermally-induced pressures, in the design and selection
of suitable overpressure protection devices.
1.9
1.11
Design Specifications
The design specification for drilling systems, subsystems, equipment and/or components is to consider as a
minimum, but not limited to, the most adverse combination of applicable loads listed in 2/5.7 and consisting of
design plans, drawings, data, and calculations, as outlined in Subsection 2/7, to substantiate the design.
24
i)
In addition to the design specifications, the manufacturing specifications are to include material
specifications, WPS/PQR, NDE, and testing procedures/specifications utilized in the manufacturing,
installation, and commissioning of each system, subsystem, equipment, and/or component and are to
comply with the applicable section of this Guide, in addition to the codes or standards used.
ii)
Design plans and data are to be submitted for ABS approval of drilling systems, subsystems,
equipment, and/or components, in accordance with Subsection 2/7 and the requirements of this Guide.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
Design Considerations
5.1
5.3
5.5
i)
Designs complying with other international or national standards not listed in Appendix 1 will be
subject to special consideration in accordance with 1/7.7 of this Guide.
ii)
ABS advises the designer/manufacturer to contact the ABS Technical office early in the design
phase for acceptance of alternate design codes and standards.
iii)
When alternate design codes and standards are proposed, justifications can be achieved through
equivalency, gap analysis or appropriate risk analysis/philosophy to demonstrate that the proposed
alternate design code and standard will provide an equivalent level of safety to the recognized
standards as listed in this Guide, and are required to be performed in accordance with 1/7.7 of this
Guide.
The manufacturer will be required to demonstrate by way of testing or analysis that the design criteria
employed results in a level of safety consistent with that of a recognized standard or code of practice.
ii)
Where strain gauge testing, fracture analysis, proof testing or similar procedures form a part of the
manufacturers design criteria, the procedure and results are to be submitted for ABS review.
iii)
iv)
ABS will consider the application of risk evaluations for alternative or novel features for the basis
of design in accordance with 1/7.7 of this Guide, as applicable.
ii)
The amount of additional material needed is to be determined based on the predicted rate of corrosion
and/or erosion and the design service life of the component.
iii)
Alternative allowances will be considered when supplemented with technical justifications for the
life-cycle of the equipment, such as:
iv)
a)
b)
c)
In the absence of 2/5.5i) through 2/5.5iii), a minimum corrosion allowance of 1.6 mm (0.0625 in.) is
to be utilized.
25
Section
5.7
Design Conditions
The drilling systems, subsystems, equipment, and/or components are to be designed to account for all applicable
environmental, operational, and test loads, or combination thereof. These include, but are not limited to,
the following:
i)
ii)
5.9
Earthquake
Wind
Ice
Temperature
Current, waves
Operational
Static pressure
Vibration
Temperature excursion
Tension
Retrieval
Drifting
iii)
Bending
Transportation
iv)
Installation
v)
Commissioning
vi)
vii)
Test Loads
Identifying and assessing major hazards, but not limited to, those defined in 1/7.9 of this Guide
ii)
Potential risks associated with the drilling system, including its impact on other systems
iii)
iv)
v)
5.9.1
i)
Qualitative hazard identification studies such as HAZID, HAZOP, What-if, etc., or similar
ii)
Functional FMEA/FMECA
iii)
These assessments are to be performed sequentially, starting with the identification of hazards for
the overall design, and focusing to detailed risk studies driven by the findings of the previous
studies, as necessary.
5.9.2
26
Section
5.9.3
5.9.4
5.9.5
Qualitative risk assessments as defined in 2/5.9.1i) above are to performed covering the integrated
drilling system as defined in Subsection 3/1 of this Guide.
Qualitative risk assessments as defined in 2/5.9.1ii) above are to performed covering the integrated
control system for various drilling subsystem.
Functional FMEA/FMECA
Functional FMEA/FMECA as specified in 2/5.9.1ii) above are to be performed covering individual
systems, subsystems, equipment and components as defined in Subsection 3/1 of this Guide.
i)
The functional FMEA/FMECA is to evaluate the intended control functions such as hydraulic,
pneumatic, electrical, electro-hydraulic, acoustic, or computer-based systems components,
as applicable, will not cause unsafe operation in compliance with the design principles in
Subsection 3/3, 3/15.1, 3/15.3, 3/15.5.
ii)
The functional FMEA/FMECA is to evaluate the well control, drilling support, and general
support systems will not cause unsafe operation in compliance with the design principles
in Subsection 3/3, 3/15.1, 3/15.3, 3/15.5.
iii)
ii)
5.11
i)
FMEA/FMECA validation is to be carried out at the vendors plant, in accordance with 4/3.3.1
and Subsection 8/3 of this Guide.
ii)
When final testing requires assembly and installation on-board facility, it may not be possible to
perform all required testing at vendors plant. In this case, FMEA/FMECA validation is be carried
out as part of the system integration testing (SIT) during commissioning, in accordance with
4/3.3.2 and Subsections 8/5 and 8/7 of this Guide.
iii)
The test program results are to be documented to confirm that the FMEA/FMECA conclusions are
valid.
27
Section
Section 4 of this Guide provides the general process for ABS approval of a drilling system.
Subsequently, Section 4, Table 1, Approval Codes for Drilling Systems and Equipment identifies
the typical drilling system, subsystems, equipment and/or components that require approval for
ABS Classification of the drilling system.
ii)
It should be noted that Section 4, Table 1 is provided as a general reference listing, and is not to be
considered as the complete drilling system, subsystem, equipment or component listing. For drilling
systems, subsystems, equipment or components not listed in Section 4, Table 1, the designer/
manufacturer should contact the appropriate ABS Technical office for guidance on technical and
survey requirements and completion of the approval process.
iii)
The manufacturers plans and data, as specified in Subsection 2/7 of this Guide, are generally to be
submitted electronically to ABS. However, hard copies will also be accepted.
iv)
All plan submissions originating from manufacturers are understood to be made with the knowledge
of the main contracting party.
v)
(1 September 2012) Design plans and data, as listed in Subsection 2/7 of this Guide, are expected
to be submitted by the entity(ies) outlined in the table below. Depending on the contractual
agreement between entities, the responsible party for design plans and data submittal may vary.
Submittal of Design Plans and Data
Shipyard
Owner/Operator/Designer
Manufacturers
Drilling Systems
General arrangement
X
X
Well control
Well circulation
Marine interface
Electrical
Control
X
X
Drilling Equipment
X
Components
Installation integration
Note:
7.1
28
X
X
Subsystems
X
Where multi-entities are indicated, any one entity or all entities may be responsible for the
design plan and data submittals, dependent on contractual agreement between entities.
General arrangement of the installation/facility where the drilling system and its machinery are
installed
ii)
Piping systems associated with the drilling systems, and support systems
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
7.3
Locations of all control panels/stations for drilling systems, including all drilling support systems
Locations of the fire and gas monitoring and fire-fighting control locations
Detailed arrangements of the well test areas or location of well test equipment
Escape and egress routes, including their protections, and muster stations
The locations of openings (air intake, exhaust, windows, doors, etc.) for all closed spaces
Ventilation arrangements
iii)
HAZOP and/or HAZID study reports for the entire drilling systems and all associated subsystems
on the drilling unit
iv)
FMEA/FMECA or similar analysis, and its validation program for systems, subsystems, equipment
or components, and integrated systems in accordance with 2/5.9 and 2/5.11, respectively, of this Guide
v)
Classified areas (hazardous areas) drawings and/or details identifying nonhazardous areas and
hazardous areas in accordance with the ABS MODU Rules, API RP 500 or API RP 505
vi)
Diverter equipment
(1 September 2012) The following are to be submitted for the well control systems and equipment:
i)
ii)
FMEA/FMECA or similar analysis for the well control systems and subsystems (see 2/5.9, 2/5.11
and 3/15.3)
7.3.1
i)
ii)
Design basis:
Descriptions of the well control systems and equipment for surface and subsurface BOPs
Shutdown logic
(1 September 2012) All control panel arrangements for BOP control systems
29
Section
iii)
iv)
(1 September 2012) Design and manufacturing details for BOP stack equipment to include
preventers, drill spools, wellhead connectors, clamps, spacer spools, adapter spools, etc.:
Individual BOP (annular and ram) details. This is to include manufacturer documentation
to specify and to attest BOP minimum and maximum capability with regard to:
vi)
30
Wire line, or
Tool joints
Casing
Data and documentation to confirm the shear rams capability of shearing the various
tubulars (sizes, grades, strengths, etc.) under the specified design conditions
v)
BOP stack configuration with individual annular and ram preventer details. This is to
include the manufacturers documentation to specify and to attest BOP stack minimum
and maximum capability with regard to:
-
Wire line, or
Tool joints
Casing
Risk assessment for BOP stack arrangement identifying ram and annular placements
and configurations
Lift points/attachments
Design details and structural analysis for BOP structural frame and lifting attachments
Control panel and control equipment arrangements, showing locations on drilling unit
Pressure relief system: arrangements, size, materials, back pressure and capacity calculations,
as applicable
Section
vii)
viii)
ix)
7.3.2
x)
xi)
xii)
Load cases and limit states for all design and operating conditions
Design analysis methodology for the lower marine riser package, including computer
modeling and computer program used
ii)
Design analysis of lower marine riser package mechanical-load bearing components (see
2/7.13) and pressure-retaining equipment (see 2/7.21), as applicable.
iii)
LMRP components and systems are typically integrated into the BOP system and equipment.
See 2/7.3.1 for applicable submittal requirements for the following items:
Equipment, component
Control system
Electrical systems
iv)
Subsea control pods details, drawings and arrangements inclusive of component descriptions
v)
vi)
vii)
viii)
ix)
31
Section
7.3.3
Chokes
Drape hoses
Hydraulic hoses
Swivel joints
i)
Union connections
Kill unit
Control system
Design basis:
Descriptions of the choke and kill systems and equipment and kill unit, including
design parameters, pressure rating (internal/external), temperature rating (min/max.)
ii)
iii)
Details of prime movers, such as diesel engines, motors, and generators, as applicable
iv)
v)
Temperature rating
vi)
vii)
x)
ix)
viii)
32
xi)
xii)
xiii)
Section
7.3.4
Diverter Equipment
i)
(1 September 2012) Design basis:
ii)
Descriptions of the diverter system and equipment, including design parameters, pressure
rating, temperature rating (min/max)
iii)
iv)
v)
7.5
7.3.5
vi)
vii)
viii)
i)
ii)
iii)
Pup joints
Buoyancy devices
Riser joints
Telescopic joints
Submit the following documentation for the marine drilling riser system and/or its components, as applicable:
i)
Descriptions of the marine drilling riser system and its components (telescopic joint, flexible
joint, connectors, etc.)
Load cases and limit states for all design and operating conditions
33
Section
Assumptions used in the global design analysis of the marine drilling riser system and design
analysis of its components
Design analysis methodology for the marine drilling riser system, including computer modeling
and computer program used
Design analysis methodology of marine drilling riser components, including loading parameters
from global marine drilling riser analysis, computer modeling, and computer program used
Support unit reports with information pertaining to any supporting units that affects the marine
drilling riser system. Reports to include unit response amplitude operators (RAOs), physical
layout of the drilling floor, derrick and pipe racks, and auxiliary lifting equipment.
ii)
iii)
iv)
Installation analysis
v)
vi)
vii)
viii)
Input data:
Riser configuration
Components interface/interactions
Boundary conditions/constraints
ix)
Maximum stress
Displacement/deflection
x)
See 3/5.7 of this Guide for additional details on marine drilling riser design requirements.
xi)
xii)
xiii)
34
Design temperatures
(maximum, minimum)
Section
xiv)
7.6
xv)
xvi)
ii)
Design basis:
Descriptions of the conductor tensioning system and associated equipment and components
Load capacity
iii)
iv)
v)
vi)
ix)
viii)
vii)
7.7
x)
xi)
35
Section
Submit the following documentation for the drill string compensation system and associated equipment, as
applicable:
i)
ii)
Design basis:
Descriptions of the drill string compensation systems and associated equipment, inclusive of
fast and dead line compensation, as applicable
Load capacity
iii)
iv)
v)
vi)
7.9
viii)
vii)
ix)
x)
Degasser
Submit the following documentation for the bulk storage, circulation and transfer systems, as applicable:
36
i)
ii)
Design basis:
Descriptions of the bulk storage, circulation and transfer systems, and all associated equipment
(e.g., mud-gas separator, degasser, desilter, desanders, shale shakers, agitators, etc.)
Design parameters, pressure rating (internal/external), temperature rating (min/max) and flow
simulation
Section
iii)
iv)
Details of prime movers, such as diesel engines, motors, and generators, as applicable
v)
vi)
Temperature rating
vii)
viii)
7.11
x)
ix)
xi)
xii)
Load cases and limit states for all design and operating conditions
Assumptions used in the design analysis of the derrick structure and associated
components
Environmental
Temperature, min/max
Operating
Field transit
Static
Ocean transit
Storm survival
Lifting, if applicable
Waiting on weather
Combined load cases and limit states for all design and operating conditions
The center of rotation (floating condition) specified in terms of the vertical and horizontal
distances between the derrick base and the center of flotation of the vessel/unit
Design analysis methodology for the derrick structure and associated components,
and component analyses including computer modeling and computer program used
37
Section
Material specifications and material properties for all load-bearing components and
bolts (if bolted design), including CVN testing requirements, as applicable
Rigging arrangement
ii)
iii)
Descriptions of all computer programs, analysis methodologies and limits, and other
calculation procedures that will form the basis of the structural design and analysis
iv)
v)
38
Design load development and computer input for all design conditions
Computer model geometry plots (group IDs, joint numbers, members and lengths, critical
unity checks)
Allowable stresses
Attachment locations for other equipment (e.g., drill string compensation, tubulars
handling, blowers, air reservoir, accumulator, tugger winches, ancillary equipment, etc.)
Supplemental calculations:
-
Sheave shaft strength (including shafts for cluster, fastline, and deadline sheaves)
Padeyes, as applicable
Structural drawings:
Geometry layout drawing; showing overall dimensions of derrick and indicating the
size of each member
Section
Detailed drawings of the main structural elements of the derrick, crown frame, and
water table beams, including:
-
Bolts sheet
vi)
vii)
Load cases and limit states for all design and operating conditions or combination thereof:
-
Dead, live and dynamic loads, including loads due to list and/or trim of the drilling
unit, as applicable
Environmental loads including the effects of wind, sea state, snow and ice
ii)
General arrangement, assembly plans and description of operating procedures and design
service temperature
iii)
iv)
Stress diagram, stress analysis and other supporting calculations, suitably referenced. Where
computer analysis is used for the determination of scantlings, details of the programs
describing input and output data and procedures are to be included together with the basic
design criteria.
v)
vi)
vii)
viii)
Welding details and procedures and a plan indicating extent and locations of nondestructive
inspection of welds for crane structure and foundation
ix)
x)
xi)
xii)
xiii)
39
Section
Description of system
Design conditions:
Environmental
Survival
Operating
Lifting, if applicable
Static
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
ii)
iii)
iv)
40
v)
vi)
Section
7.13
ii)
iii)
iv)
v)
vi)
vii)
viii)
7.15
ix)
x)
ii)
Shutdown logic
41
Section
iii)
iv)
i)
Equipment list
Load cases and limit states for all design and operating conditions
Assumptions used in the design analysis of the burner flare boom structure and associated
components
Environmental
Survival
Operating
Lifting, if applicable
Combined load cases and limit states for all design and operating conditions
Design analysis methodology for the burner flare boom structure and associated
components, and component analyses including computer modeling and computer
program used
Material specifications and material properties for all load-bearing components and
bolts (if bolted design), including CVN testing requirements, as applicable
ii)
Descriptions of all computer programs, analysis methodologies and limits, and other
calculation procedures that will form the basis of the structural design and analysis
iii)
iv)
42
Design load development and computer input for all design conditions
Computer model geometry plots (group IDs, joint numbers, members and lengths, critical
unity checks)
Allowable stresses
Justifications for any stress exceeding the stated allowable stress, as applicable
Structural drawings:
Geometry layout drawing; showing overall dimensions of burner flare boom and
indicating the size of each member
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
Detail drawings of the main structural elements of the burner flare boom, including:
-
Bolts sheet
7.17
7.19
Control Systems
The following control system plans and data are to be submitted for design review, as applicable:
i)
Arrangement plans showing location of units controlled, instrumentation and control devices
ii)
iii)
iv)
v)
Volumetric capacity calculations for the accumulator systems, primary and secondary (as
applicable)
43
Section
7.21
Pressure relief system: Arrangements, size, materials, back pressure and capacity calculations,
as applicable
vi)
(1 September 2012) FMEA, FMECA or similar analysis for control systems as defined in Subsection
3/15 for system, subsystem, and equipment (see 2/5.9)
vii)
Documentation in accordance with the recognized industry standard is to be submitted for review
to justify the safety integrity levels, when applicable [see 3/15.5.2(c)].
viii)
Calculations for control systems demonstrating the systems ability to react adequately to anticipated
occurrences, including transients
ix)
Arrangements and details of control consoles/panels, including front views, installation arrangements
together with schematic plans and logic description for all power, control and monitoring systems,
including their functions
x)
Type and size of all electrical cables and wiring associated with the control systems, including
voltage rating, service voltage and currents, together with overload and short-circuit protection
xi)
Schematic plans and logic description of hydraulic and pneumatic control systems together with all
interconnections, piping sizes and materials, including working pressures and relief-valve settings
xii)
Description of all alarm and emergency tripping arrangements and functional sketches or description of
all special valves, actuators, sensors and relays
xiii)
xiv)
(1 September 2012) Hydrocarbon and sour gas detection system plans and data, including detectors,
piping, set points, type of detectors, and location of alarm panels, and recalibration program for
gas detectors
Pressure-Retaining Equipment
Unless required otherwise in 2/7.3 through 2/7.11, the following documentation for pressure-retaining
equipment is to be submitted for ABS review and approval, as applicable:
i)
ii)
Design parameters: pressure rating (internal/external), temperature rating (min/max), loads, etc.
iii)
iv)
v)
vi)
vii)
See Section 4, Table 1, Approval Codes for Drilling Systems and Equipment for ABS approval requirements.
7.23
44
Piping Systems:
Pipe stress and flexibility analyses, including design verification of erosional allowance due to
fluid velocity
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
ii)
Piping components are considered, but not limited to, pipes, valves, hoses, fittings, flanges, bolts,
etc. Piping component design specifications to include the following information in accordance
with piping standard rating, as applicable:
Technical specifications
Fluid medium (specifically note if piping standard rating is for sour service)
Corrosion/erosion allowances
See Section 4, Table 1, Approval Codes for Drilling Systems and Equipment for ABS approval requirements.
7.25
7.27
ii)
iii)
Design analysis
iv)
v)
Stress analysis
Material specifications
vi)
vii)
ii)
iii)
iv)
Detailed Inspection and Test Plans (ITPs), including associated test procedures for system, subsystem,
equipment or component, as outlined in Section 4, Table 1 of this Guide, as applicable during:
Manufacturing
Installation
Commissioning
In-service
45
Section
46
v)
vi)
vii)
SECTION
Drilling Systems
Drilling Support
Well Control
Blowout Preventers (BOP)
Lower Marine Riser Package
(LMRP)
Marine Drilling Risers
Diverter System
Choke & Kill Systems
Well Circulation (HP)
Auxiliary Well Control
Equipment
Secondary Well Control
Systems
- Acoustic
- ROV Interface
Emergency Well Control
Systems
- Deadman
- Autoshear
- Emergency Disconnect
System (EDS)
Derrick/Mast
Mud Conditioning/Return
Cementing
Conductor Tension System/Unit
Drill String Compensators
Riser Tensioning
Hoisting Equipment
Lifting/Cranes
Pipe/Riser/BOP Handling
Rotary Equipment
Hydraulic Power Units (HPUs)
Well Test
Hydrocarbon Disposal
- Burner
- Flare Boom
Support
Storage
- BOP, LMRP, Xmas-tree, etc.
- Bulk Materials and Transfer
- Risers
- Tubulars
- Fluids
Nitrogen Generation and
Charging
Hydraulic and Pneumatic
Systems and Equipment
Utilities ans Instrument Air
Chemical Injection Unit
Sea Water
This Guide provides detailed procedures for ABS approval of drilling systems, subsystems, equipment,
and/or components for Classification of a drilling system. The term Classification, in this document, indicates
that a drilling system and its equipment have been designed, constructed, tested, installed and surveyed in
compliance with relevant ABS Rules, Guides, this Guide or other recognized standards.
The following is to be considered in ABS Classification of Drilling Systems:
i)
The drilling system, subsystems, equipment, and/or components are to be designed and manufactured
in compliance with the recognized codes and standards, as listed in Appendix 1, and the additional
requirements specified in this Guide.
ii)
Where a certain aspect of the design is not in compliance with the recognized code, standard or the
requirements of this Guide, the specific variations are to be advised and justified and will be
specially considered by ABS in accordance with 1/7.7 of this Guide, on a case-by-case basis.
iii)
ABS approval requirements for typical drilling systems, subsystems, equipment, and/or components
are outlined in Subsection 4/1 and Section 4, Table 1, Approval Codes for Drilling Systems and
Equipment of this Guide.
47
Section
Drilling Systems
Acoustic
ROV Interface
Diverter System
Deadman
Autoshear
Control Systems
The well control systems, subsystems, equipment, and/or components are to be in compliance with the
following API standards and the additional requirements of this Guide:
Blowout Preventer (BOP) System and Equipment
API RP 2A WSD
AISC
FMEA/FMECA or similar analysis for major systems, subsystems, equipment or components, and integrated
systems.
3.1
ii)
48
Section
Drilling Systems
iii)
Two (2) shear rams for moored or dynamically-positioned units, one being a blindshear ram and the other to be a casing shear
iv)
The BOP stack configuration is to be able to close BOPs on all sizes of drill pipe, drill
collars and casing that may be used within a drilling program.
v)
The ram-type BOP positions and outlet arrangements on subsea BOP stacks are to provide
reliable means to handle potential well control events. Specifically for floating operations,
the arrangement is to provide means to:
Close and seal on open hole and allow volumetric well control operations
Hang off the drill pipe on a ram-type BOP and control the wellbore
Shear logging cable or the drill pipe and seal the wellbore
vi)
vii)
For subsea BOP, the use of drilling spools is not recommended in order to reduce the overall
height of the subsea BOP stack arrangements.
viii)
Spacer spools can be used to provide separation between two (2) drill-through components
with equal-sized end connections (nominal size designation and pressure rating). If installed,
spacer spools for BOP stacks are to meet the following minimum specifications:
ix)
x)
Have a vertical bore diameter the same internal diameter as the mating equipment
Have a rated working pressure equal to the rated working pressure of the mating
equipment
Are not to have any penetrations capable of exposing the wellbore to the environment,
without dual isolation capabilities
The BOP equipment is to be designed for the specific drilling envelope, and suitable for
the intended facility. The BOP manufacturer is to specify and to attest to BOP stack minimum
and maximum capability with regard to the following, including shearing and pressuretemperature capabilities:
Tubulars
Pressure
Wire lines
Temperature
Water depth
The BOP structural frame and lifting attachments are to be designed considering applicable
loads as specified in 2/5.7 of this Guide and in accordance with the requirements of API
RP 2A-WSD or other recognized standards. Allowable stresses are to be in accordance
with design standards and/or AISC.
49
Section
3.1.2
Drilling Systems
Control Systems for Blowout Preventers Surface and Subsea (1 September 2012)
i)
The control systems and components (hydraulic, pneumatic, electric, electro-hydraulic, etc.)
are to comply with Subsection 3/15 of this Guide and are to be in compliance with API
Spec 16D and API RP 53.
ii)
Calculations are to demonstrate compliance with the standards referenced above for the
hydraulic fluids volumetric capacity of the accumulator system, pump system and reservoir
capacity, including the rapid discharge systems.
iii)
Well control systems and components are to comply with the functional requirements of API
RP 53, and this is to include response time, pump system sizing, arrangements, and charging
of accumulator systems.
iv)
One (1) well control panel is to be at the drillers station or cabin and where it is protected
from drilling activities.
ii)
iii)
Well control panels are to be mutually independent (i.e., directly connected to the control
system, and not connected in series).
iv)
For the subsea BOP stack, adequate measures are to be provided to prevent accidental
unlatching of the wellhead connector until the well is secure, such as two-hand function,
two-step action, protective cover or equivalent.
v)
Shear ram functions are to be two-hand function, two-step action, protective cover or
equivalent.
vi)
The well control panels are to include controls for at least, but not limited to:
Close or open of all rams, annular preventers, and choke and kill valves on BOP stack
Diverter operations
3.1.2(b) Hydraulic Fluid Capacity and System for BOP Stack. For a subsea or surface BOP
stack, stored energy using hydraulic fluids and accumulators are to be provided with required
capacity, volume and pressure, calculated in accordance with API Spec 16D for specified closing
and shearing functions, and demonstration of adequate functional capacity in accordance with API
RP 53, and the requirements of this Guide.
i)
50
The minimum precharge pressure for the BOP system is to be determined based on the
following in accordance with API Spec 16D and API RP 53, as applicable:
Water depth
Local regulations
Operational sequence
Section
Drilling Systems
ii)
The required hydraulic fluid capacity is to be calculated in accordance with API Spec 16D
to perform the following functions:
a)
b)
To close and open one (1) largest volume annular-type preventer from
full-open position
2)
To close and open four (4) largest ram-type preventers from full-open
position
3)
4)
2)
3)
iii)
The calculations for the precharge pressure [3/3.1.2(b)i)] and hydraulic fluid capacity
[3/3.1.2(b)ii)] are to consider the operational sequence during well control to provide
sufficient hydraulic pressure and fluids for the shearing operation for the specified operational
sequence and without pumps being operative.
iv)
When stripping accumulators are installed on BOP stack, subsea or surface, additional
hydraulic fluids volumes are to be provided in addition to 3/3.1.2(b)ii) of this Guide. The
additional hydraulic fluids required are to be based on the BOP hydraulic operator rated
working pressure, and the minimum specified precharge pressure of the stripping
accumulators.
v)
For hydraulic fluid drawdown tests, the system is to have sufficient usable fluid volume
as required by API RP 53 to demonstrate the following:
a)
To perform all functions specified in 3/3.1.2(b)ii) of this Guide for subsea or surface
BOP stack, respectively, against zero wellbore pressure while pumps are inoperative.
b)
The remaining pressure after completion of 3/3.1.2(b)ii) of this Guide for subsea
or surface BOP stack, respectively, is to be 1.38 MPa (200 psi) or greater, above the
minimum precharge pressure.
3.1.2(c) Secondary and Emergency Well Control Systems. Secondary and emergency well control
systems, such as acoustic (if installed), deadman and autoshear systems, are to be provided for DP
or moored units with dedicated rapid discharge system with dedicated subsea accumulator unit.
The main hydraulic supply for the secondary and emergency well control systems can be powered
by a shared dedicated subsea accumulator unit.
The accumulator capacity, volume and pressure, is to be calculated in accordance with API Spec
16D and is to consider all applicable closing sequences to shut in the well.
i)
ii)
Deadman System
Autoshear System
51
Section
Drilling Systems
iii)
3.1.3
Subsea BOP stack is to be equipped with ROV intervention equipment and control systems,
and is to be provided with the following provisions:
a)
ROV intervention equipment which at a minimum allows the closing of one set
of pipe ram, closing of one each blind-shear rams, and unlatching of the LMRP.
These functions are to operate independently of the primary BOP control system.
b)
i)
(1 September 2012) Surface and subsea, ram and annular blowout preventers, including
workover and well servicing BOPs, ram blocks, annular packing units, valves, wellhead
connectors, drilling spools, adapter spools and clamps are to be designed, fabricated and
tested by the respective manufacturers for compliance with API Spec 6A, Spec 16A, and
the additional requirements of this Guide.
ii)
Hydraulically-operated wellhead, riser and choke and kill line connectors are to have
redundant mechanisms for unlock and disconnect.
iii)
The secondary unlock and disconnect mechanism may be hydraulic or mechanical, but
must operate independently of the primary unlocking and disconnect mechanism.
iv)
In addition to the design conditions/loads listed in 2/5.7 of this Guide, the design of preventers
is to consider the following loads, as applicable:
v)
The weight of a specified length of drill string suspended in the pipe ram preventer
On fixed units, if the tool joints cannot be sheared, the following is to be considered:
vi)
vii)
(1 September 2012) The shear rams are to be capable of shearing the largest section and
highest-grade of tubulars (drill pipe, casing, wireline, etc.), as applicable, in accordance
with API Spec 16A, and API RP 53, as applicable, or the specified drilling program.
viii)
(1 September 2012) The shearing capacity calculations for the shear rams are to consider
the following, simultaneously, as applicable:
Frictional force
Shearing ratio
Shear test data (historical and/or project specific) to justify and validate shear capacity
calculation are to be submitted.
ix)
52
The annular, pipe and blind ram BOP operator design pressure is to consider the following,
simultaneously, as applicable:
Frictional force
Section
Drilling Systems
x)
Procedures to test preventers during manufacturing and on-site are to be developed and
submitted for ABS review.
xi)
For subsea BOP and associated components such as valves, control system components,
sealing components, elastomeric components, etc., are to be designed with consideration
to marine conditions and external pressure gradient due to rated water depth.
xii)
All nonmetallic materials are to be suitable for the intended service conditions, such as
temperature and fluid compatibility.
xiii)
xiv)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
3.3
i)
Blowout preventer manufacturers are to provide the Owner/Operator with product operations
and maintenance manuals to assist in the safe operation of each assembly on each installation.
ii)
ii)
Lower marine riser package disconnect arrangements are to be designed for all possible operating
and loading conditions. The loading conditions of the LMRP are to consider, but not limited to,
the following:
Side loads
Internal pressure
Bending loads
Currents
The LMRP design is to consider the induced loads as defined in API Spec 16F and API RP 16Q,
as a minimum, for the following modes:
Installation
Drilling
Hang-off
Retrieval
Drifting
iii)
iv)
(1 September 2012) The emergency disconnect is to initiate and complete disconnection in correct
sequence. A typical emergency disconnect sequence would be:
v)
Blind-shear
Close well
Disconnect LMRP
LMRP and associated components, such as valves, control system components, sealing components,
elastomeric components, etc., are to be designed with consideration to marine conditions and external
pressure gradient due to rated water depth.
53
Section
vi)
vii)
3.5
Drilling Systems
Adapter spools for BOP stacks are to meet the following minimum specifications:
Have a minimum vertical bore diameter equal to the internal diameter of the mating equipment
Have a rated working pressure equal to the lowest rated end connection of the mating equipment
LMRP structural frame and lifting attachments are to be designed with consideration to all applicable
loading conditions. The applicable structural design code and standard, including loading conditions,
are provided in 3/3.1.1x) of this Guide.
54
For surface BOP stacks, one of these two valves is to be arranged for remote hydraulic
operation.
For subsea BOP stacks, these two valves are to be arranged for remote hydraulic
operation.
ii)
The design pressure of the pipes, valves, flexible lines, connectors, fittings, and the choke
manifolds from the BOP stack to the isolation valve downstream of the choke is to be the
same as that of the ram-type BOPs or greater.
iii)
For subsea BOP stack, the line connected to the lowermost outlet of the BOP is to be
designated as the kill line. Placement of this outlet is to be below the lowermost well
control pipe ram.
iv)
For surface BOP stack, a documented risk assessment is to be performed to determine the
type and placement of valves (hydraulic, manual, and/or check) for the designated kill
line. This is to be submitted for ABS review and approval.
v)
One (1) choke line and one (1) kill line connection is to be located above the lower most
ram BOP.
Section
Drilling Systems
vi)
vii)
The choke line that connects the BOP stack to the choke manifold and lines downstream of
the choke are to:
Be firmly anchored to prevent excessive dynamic effect of fluid flow and the impact
of drilling solids and/or vibration
Supports and fasteners located at points where piping changes direction are to be
capable of restraining pipe deflection in all operating conditions
Have bore of sufficient size to prevent excessive erosion or fluid friction due to velocity
For flexible lines, the requirements contained in 5/3.7 of this Guide are applicable.
3.5.2
3.5.3
End connectors are to be in accordance with the applicable parts of Section 5 of this
Guide.
ii)
For choke end connections, only flanged, welded or clamped connections, and rated hammer
unions are to be used, regardless of rated working pressure.
iii)
For rated working pressure less than 69 MPa (10000 psi), the minimum size for the choke
lines is to be 50.8 mm (2.0 in.) nominal diameter.
iv)
For rated working pressure of 69 MPa (10000 psi) and higher, the minimum size for the
choke lines is to be 76.2 mm (3.0 in.) nominal diameter.
v)
For drilling of HPHT wells, gas wells and other drilling operations where high volume air
or gas may be expected, the minimum internal diameter for valves and pipes downstream
of the last HP valve (isolation valve downstream, next to the choke) is to be 101.6 mm
(4.0 in.) internal diameter.
vi)
Minimum size for vent lines downstream of the choke is to be at least the same internal
diameter as for the chokes end connections.
vii)
When buffer tanks are utilized, provisions are to be made to isolate a failure or malfunction
without interrupting flow control.
viii)
All choke manifold valves subject to erosion from well control are to be full-opening and
designed to operate in high pressure gas and abrasive fluid service.
a)
b)
Any one of the chokes is to be capable of being isolated and replaced while the
manifold is in use.
c)
Choke and kill manifold is to permit pumping or flowing through either choke or
kill line.
d)
For subsea BOP, the arrangement is to allow circulation through all chokes through
either choke or kill line, without interference from pumping through the other
line.
e)
f)
55
Section
Drilling Systems
ii)
The manifolds downstream of the choke are to be designed to minimize erosion or abrasion
from high velocity flow, by avoiding sharp bends. If 90 degree cannot be avoided, these
should be buffered by targeted flanges.
iii)
Each of the manifolds inlet and outlet lines is to be fitted with an isolation valve with the
pressure-temperature rating as the choke inlet and outlet accordingly.
iv)
b)
v)
The routing downstream of the chokes to mud-gas separator or discharge overboard are to be
provided with an alternate path for redundancy so that eroded, plugged, or malfunctioning
parts can be isolated without interrupting flow.
vi)
In the event the capacity of the mud-gas separator is exceeded, the choke manifold is to
have the capability to divert flow to alternate locations for emergency discharge, such as
flare or discharge overboard (port and starboard), as applicable.
The minimum internal diameter for such routing downstream of the isolation valve is to be
127 mm (5.0 in.) internal diameter.
3.5.4
vii)
The bleed line (bypassing the chokes), if installed, is to be at least equal to or greater than
the internal diameter to the choke line.
viii)
The Joule-Thompson effects are to be considered in the design and material selections of
choke and kill manifold and downstream piping and associated components.
ii)
iii)
Pressure relief valve or rupture disc is not considered necessary as the mud-gas separator is
vented to the atmosphere.
iv)
v)
Precautions are to be taken to prevent erosion at the point the drilling fluid and gas flow
impinges on the vessel wall.
vi)
Design pressure of the mud-gas separator is to be determined by the vent line being filled
with mud at 2.2 SG, or the specified maximum mud weight.
vii)
The vent line is to be sized and designed to minimize backpressure in order to assist with
separation of gas from the mud. As a minimum, the following guidelines are to be considered
for the design of the vent line:
The maximum design backpressure in the vent line is to allow for the maximum
specified gas flow without gas breaking through the mud outlet liquid seal with the
design mud/condensate weight of 0.6 SG
viii)
56
Where heavier design mud is used, continuous injection of the heavy mud into
the liquid seal is required.
Mud-gas separator is to be provided with a high level sensor (LSH) or equivalent for
notification of re-routing of flow from choke to overboard or alternate route. Alternate
arrangements for the LSH sensor will be specially considered by ABS.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
Drilling Systems
ix)
x)
3.5.5
3.5.6
Mud-gas separator is to be equipped with provisions to prevent gas blow-by to the mud
condition equipment downstream of the mud-gas separator and for the notification of manual
or automatic re-routing of flow from choke for overboard discharge or to stop the flow.
These provisions are to be achieved by:
a)
b)
2)
For HPHT operations, the liquid seal is to be a minimum 6 meters (19.69 ft).
b)
xi)
Mud-gas separator and liquid seal is to be equipped for easy clean out and drain at lowest
point. Drain line is to slope downward to prevent backflow.
xii)
Sizing of the mud-gas separator is to be performed in accordance with SPE Paper No.
20430: Mud-Gas Separator Sizing and Evaluation.
xiii)
xiv)
xv)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
Degasser
Degasser design and arrangements are to comply with the requirements of API RP 13C and the
additional requirements of this Guide.
i)
Degasser is be designed and manufactured in accordance with ASME Section VIII Boiler
and Pressure Vessel Code and Subsection 3/17 of this Guide.
ii)
ii)
iv)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
v)
Typically, the degasser is designed so that it can be operated under partial vacuum to assist
in removing the entrained gas.
vi)
vii)
The degasser is to be placed as the first stage in the mud conditioning system to reduce
the possibility of gas breaking out of the drilling fluid in the mud treatment pits.
Mud return and processing systems, and associated equipment design and arrangements are to
comply with the requirements of API RP 13C and the additional requirement of this Guide.
i)
The piping system design is to allow the returns from the flowlines to installed mud
conditioning equipment as listed above to the mud pit.
ii)
The mud return system, associated equipment and piping systems are to be designed in
accordance with Subsection 3/17 and Section 5 of this Guide.
57
Section
3.5.7
Drilling Systems
iii)
iv)
v)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
Gas Vents
i)
Vent lines from mud-gas separator (poor boy) are to extend a minimum of 4 m (13 ft)
above the crown block and to have a minimum nominal diameter of 250 DN (10 NPS).
ii)
The vent line is to be as straight as possible, free of obstructions, and is to be sized and
arranged to minimize backpressure in the upstream equipment of the vent line.
iii)
The vent line from the mud-gas separator is not to be interconnected to any other vent lines.
iv)
Vent lines are to be routed to avoid low point and to be self-draining to avoid accumulation
of mud and to be sloped toward the mud-gas separator.
v)
Vent line from liquid seal siphon breaker of the mud-gas separator is:
a)
b)
c)
d)
vi)
Bypass lines to alternate locations from choke manifold, such as vent lines, flare or overboard
(port and starboard), as applicable, must be provided in case of malfunction or in the event
the capacity of the mud-gas separator is exceeded. These lines are not to be interconnected
to the diverter lines.
vii)
Overboard lines (port or starboard) are to be directed for discharge in downwind directions
and away from the drilling facility. Routing along the diverter lines is preferred.
viii)
ix)
3.5.8
For HPHT drilling operations, the vent lines are to have a minimum nominal diameter
of 300 DN (12 NPS).
a)
Individual lines
b)
As straight as possible
c)
Free of obstructions
d)
e)
f)
The vent lines from the degasser must not be interconnected to any other vent lines.
Kill Unit
Typical components of the kill unit would include pumps, connecting piping from the kill unit and
cementing unit and drilling fluid manifold, pulsation dampeners and safety valves.
High-pressure kill unit (pump system) is to comply with the following requirements:
58
i)
ii)
It is to consist of at least two (2) pumps with each pump being powered by either:
Section
3.5.9
Drilling Systems
iii)
Pumps required to transfer drilling fluid from the mud pits to the high pressure kill
pumping system should also be connected to a back-up power supply, independent of the
main power supply.
iv)
It is to be equipped to allow the equipment operator to monitor the pressure, flow rate,
and volume of the fluid being pumped.
v)
Materials used for discharge manifold components on pumps designated as kill pumps are
to comply with 6/5.1 of this Guide regardless of minimum design temperature (MDT).
vi)
Additional considerations to the kill unit are provided in 3/9.7 of this Guide.
vii)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
viii)
ix)
Piping systems and their components, and flexible lines are to be in accordance with
Section 5 of this Guide.
x)
Materials used for well circulation systems and equipment are to be in accordance with
Section 6 of this Guide.
xi)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
ii)
The choke control station, whether at the choke manifold or remote from the rig floor, is
to be easily accessible and is to include all monitors necessary to furnish an overview of
the well control situation.
iii)
A minimum of one remote control station is to be away from the choke manifold and
protected to avoid any human and equipment hazards caused by leakage from the manifold,
valves or chokes.
iv)
Any remotely operated valve and choke is to be equipped with emergency operation
provisions as required by API Spec 16C. Alternative power sources other than specified
in API Spec 16C can be utilized as long as the availability and redundancy of the system
is equivalent or better.
v)
All remotely operated valves are to be provided with open and close indicators on the
control panel.
vi)
Remotely operated valves that have alternative means of local control in an emergency are
to be provided with local markings to enable the operator to determine the valve positions.
vii)
A choke position indicator showing the relative position of the choke trim or relative
orifice size as a percent of fully open is to be provided at the control panel.
viii)
All manual chokes and valves are to be provided with local marking or indicators to enable
the operator to determine the valve positions, open or closed.
ix)
Electronic pressure and temperature transmitters and analog gauges are to comply with
the requirements of API Spec 16C, as a minimum.
x)
The instrumentation gauges and/or transmitter on the choke manifold are to be at a minimum:
xi)
a)
Analog test pressure measurements are to be made at not less than 25% and not
more than 75% of the full pressure span.
b)
Electronic pressure gauges and chart recorders, or data acquisition systems are to
be utilized within the manufacturers specified range.
59
Section
3.7
Drilling Systems
Diverters
i)
A diverter with a securing element for closing around the drill string in the wellbore or open
hole is to be provided when it is desired to divert wellbore fluids away from the rig floor.
ii)
3.7.2
3.7.3
60
The diverter is to be equipped with two (2) 10 in. or larger lines that are to be piped to
opposite sides of the rig floor. Alternative arrangements will be specially considered with
justification in accordance with 1/7.7 of this Guide.
ii)
Valves and their actuators are to be sized to be capable of operating the diverter valve
under all design conditions.
iii)
During the operational tests at the manufacturers plant, a full design differential pressure
opening test is to be carried out for each valve and actuator combination.
iv)
The diverter valve assembly and a control system are to be designed to safely vent well
bore fluids at the surface or subsea.
ii)
iii)
The diverter system is to be controlled from two (2) locations; one is to be located near
the drillers console/workstation and the other is to be located at an accessible location
away from the well activity area and reasonably protected from physical damage from
drilling activities on the drill floor. Both controls are to be arranged for ready operation by
the driller.
iv)
The control systems are to have interlocks so that the diverter valve opens before the annular
element closes around the drill string.
v)
When the diverter element close function is activated, the return flow to the mud system
is to be isolated.
vi)
The range of diverter elements is to be suitable to seal on all sizes of drill string elements
on which the diverter is required to operate.
vii)
viii)
ix)
Section
3.7.4
Drilling Systems
ii)
iii)
iv)
Flexible lines are to be avoided where possible. When this is not practicable, data is to be
submitted substantiating their suitability for the maximum pressure, maximum reaction
loads, fire-resistance, erosion resistance, expected range of temperatures, and their
compatibility to associated piping provided it is adequately supported and connected.
v)
vi)
vii)
viii)
ix)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
3.9
3.11
Auxiliary well control equipment, such as kelly valves, drill pipe safety valves, IBOP, drill string
float valves, are to be used in a rotary drilling system.
ii)
For drilling installation using a top drive system, an automated or manual drill pipe safety valve
must be installed.
iii)
iv)
Auxiliary well control equipment is to be in compliance with API Spec 7-1, API RP 53, and
Section 5 of this Guide and the additional requirements of this Guide.
ii)
(1 September 2012) The lower kelly cock is a full-opening valve that backs up the upper
kelly cock. For surface BOP stack, the lower kelly cock is to be sized so that it can be run
through the blowout preventer stack.
iii)
Testing of kelly cocks are to be performed bi-directionally and at a low and high pressure,
with the low pressure tests first.
ii)
The wrench to operate the valve is to be readily accessible to the crew to perform this
operation.
61
Section
Drilling Systems
ii)
IBOP is spring-operated and is locked in the open position with a removable rod lock screw.
ii)
The two (2) most common types of floats are spring-operated piston (plunger) and flapper
types.
Pup joints
Buoyancy devices
Riser joints
Telescopic joints
The marine drilling riser system and associated components listed above are to be designed and fabricated in
accordance with applicable sections of API Spec 16R, API Spec 16F, API RP 16Q, API RP 2RD, API
Bull. 16J, and the additional requirements of this Guide.
5.1
62
ii)
The manufacturer is to establish a rated capacity through appropriate design analysis and
prototype testing.
iii)
(1 September 2012) Design analysis is to be submitted for review, showing that the drilling
riser system and all associated components will not be overstressed at the rated capacity,
either in axial loading, lateral loading or bending, overpressure at rated tensioning capacity
in specified design conditions.
iv)
v)
vi)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
vii)
viii)
ix)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
5.1.2
Drilling Systems
The riser recoil system is typically integrated with the riser tensioning system and its control
system by incorporating various control valves, sensors, hydraulic/pneumatic energy sources, and
computer-based control systems, etc.
The riser recoil system is to control the released energy in the EDS event or upon failure of the
marine drilling riser for all drilling operating conditions. This is to be achieved through the
following:
5.1.3
5.3
i)
Design of the marine drilling riser recoil system is to consider emergency situations, such
as an EDS event, failure of marine drilling riser, etc. during all phases of drilling operations
such as deployment and retrieval modes, drilling, drifting, etc., as applicable.
ii)
Riser recoil system is to complete an orderly and controlled shutdown of the riser tensioning
system to a predetermined safe position, regardless of the sea state or location of the
separation of the marine drilling riser.
iii)
In the event of a separation at the bottom of the marine drilling riser, the riser tensioning
system is to retract the marine drilling riser such that vessel motions do not result in a
collision of the marine drilling riser with the BOP stack.
iv)
Separation of the marine drilling riser near the tension ring, in the upper part of the
marine drilling riser will result in a fast-acting recoil which must be dissipated within the
available extension of the telescoping joint such that the drilling rig equipment cannot be
damaged.
ii)
Provisions for load monitoring are to be provided for the riser tensioning system.
iii)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
iv)
v)
In order to provide a set of criteria for the drilling operation, an envelope of operating parameters
is to be established, preferably in the form of a chart. The chart is to clearly show the limits not to
be exceeded for each marine drilling riser type in use for any combination of applied loading
conditions and the anticipated environmental conditions.
ii)
Where applicable, consideration is to be given to the limits on dynamically-positioned or turretmoored drill ships and the heading change limitations imposed by the length of the choke and kill
lines, and restrictions with the slip joint fluid ring.
iii)
The development of the chart is to take into consideration all applicable loading conditions, load
effects, mechanical stops or other limitations on the marine drilling riser system and any component
of the drilling riser.
iv)
The drilling riser is to be designed so that the maximum stress intensity for the operating modes, as
described in API RP 16Q, is not to be exceeded.
63
Section
v)
vi)
Drilling Systems
The design limits or combination thereof for consideration in the design and structural analysis of
the drilling riser system are to consider, but not limited to:
Maximum stress
Strain
Maximum deflection or
curvature
Temperature
Hydrostatic collapse
Functional, as applicable:
5.5
64
Internal pressure
Thermal
Hang-off
Inertia
Installation
Weight of riser
Environmental, as applicable:
-
Waves
Wind
Seismic
Current
Ice
Accidental, as applicable:
-
Emergency disconnect
Tensioner failure
Technical Requirements
Marine drilling riser system technical requirements are to comply with the following:
i)
ii)
The design analyses of the individual marine drilling riser components are to be performed using
loads obtained from a global drilling riser analysis.
iii)
The marine drilling riser system and components are to be evaluated for the design conditions and
service life criteria as indicated in 3/5.3 of this Guide.
iv)
The individual components of the marine drilling riser system are to be adequately designed to
withstand stresses expected throughout the service life of the particular component. In design,
consideration is to be given to the maximum stress, fatigue damage, maximum deflection and
stability against column buckling.
v)
The maximum permissible deflection of the drilling riser system is to be limited to that value
which not would cause interference with the passage of any downhole tools that would be used in
the different operating modes.
vi)
The drilling riser running equipment, which includes the drilling riser running/handling tool, riser
spider, gimbal and shock absorber (if applicable) is to be designed and rated in accordance with
API Spec 8C and the additional requirements of this Guide.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
5.7
Drilling Systems
vii)
The mud boost system is to be provided with safety relief valves capable of protecting system
equipment with the lowest pressure rating, including the marine drilling riser.
viii)
Riser make-up and break-out equipment and procedures are to be provided for ABS review.
Design Documentation
Design documentation is to include the reports, calculations, plans, manuals and other documentation necessary
to verify the global riser analysis and structural integrity of the individual riser components. Additional
documentation may be required based on the relative complexity of the marine drilling riser system or
relevant conditions in the geographic area of operation.
5.7.1
5.7.2
Reports
i)
Reports are to fully describe the loads and resulting stresses for the global drilling riser
system, individual components, and the operating and environmental conditions that produce
those loads and/or restrict the ability of the drilling riser system to meet its designed function.
ii)
The environmental reports are to be based on appropriate original data. Data from analogous
areas may be considered. The information contained therein is to include all environmental
phenomena that would affect the drilling riser system.
iii)
Data presented is to include tables that summarize wave height vs. percentage of time,
wave height vs. direction, wave and overall current statistics for return periods of 1 year,
10 years and 50 years.
iv)
v)
Design air and water temperature ranges are to be specified and suitably accounted for
should their extreme values interfere with the operation of any system component.
System Calculations
i)
Design analyses are to be submitted that clearly demonstrate the capability of the marine
drilling riser system to withstand the imposed loads for the intended operating envelope.
ii)
The operating envelope defines the range of individual operating conditions for which the
drilling riser system is suitable and which also defines the boundaries for combinations of
operating conditions within the acceptable ranges of individual conditions (e.g., the
combination of offset, water depth, mud weight, etc.)
iii)
Riser section properties for each type of riser joint. This includes joint length, principal
tube dimensions, overall drag diameter, number of attached lines, buoyancy devices,
bare joint weight, total joint weight in air and water, material characteristics.
5.7.3
5.7.4
Plans
Plans are to include arrangement plans, elevations and plan views clearly showing in sufficient
detail the overall configurations, dimensions and layout of the marine drilling riser system and all
of its components. Plans are to be submitted for each type of connector used in the drilling riser
system. See Subsection 2/7 of this Guide for additional details.
65
Section
Drilling Systems
5.7.5
Other Data
This is to include information in support of novel features utilized in the marine drilling riser system.
Novel features will be specially considered by ABS with justifications in accordance with 1/7.7 of
this Guide.
6.1
6.3
Load-carrying parts are to be in accordance with design codes and standards as referenced in
3/11.3.4 of this Guide.
ii)
iii)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
iv)
Piping and flexible lines/hoses are to be in accordance with Section 5 of this Guide.
v)
vi)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
7.1
ii)
iii)
iv)
v)
The design of these equipment and/or components is to be in accordance with the applicable sections of
this Guide.
66
Section
Drilling Systems
7.1.1
7.1.2
ii)
iii)
If the locking mechanism is in the load path, it is to be in accordance with 3/11.3.4 of this
Guide, as applicable.
iv)
v)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
vi)
vii)
viii)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
ii)
iii)
9.1
Provisions are to be made so that utility air used to transport cement or bulk mud is dried to a
water dew point of at least 7C (13F) below the minimum ambient air temperature.
ii)
All utility air piping is to be designed to be purged with dry air prior to transfer operations.
iii)
The utility air transfer piping is to be fitted with relief valves set at a pressure not greater than the
working pressure of the bulk storage tanks.
iv)
Bulk storage vessels are to be fitted with safety relief valves or rupture disks piped to a safe relief
area. Unless they are fitted with a relief line to an open area, the use of rupture disks is to be
limited to tanks installed in open areas.
v)
A P&ID or equivalent schematic of the bulk transfer system is to be clearly posted at the operator
station to facilitate operation of the system during various bulk transfer operations.
vi)
The control systems are to be in accordance with Subsection 3/15 of this Guide, as applicable.
vii)
viii)
Piping systems and their components are to be in accordance with Section 5 of this Guide.
67
Section
9.3
9.5
9.7
68
Drilling Systems
ix)
Materials used for bulk storage and transfer equipment are to be in accordance with Section 6 of
this Guide.
x)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
If the cement pumps are to be arranged to be capable of emergency well kill circulation, using the
drilling fluid transferred from the mud pits, then compliance with 3/3.5.8 is required.
ii)
iii)
The interconnect lines between systems that are used only for emergency well kill circulation are
to be fitted with blind or spectacle flanges, lockable valves or similar devices that can be opened
as needed, but positively isolate the systems during normal operations. These flanges are to be clearly
identified and labeled on the P&ID, and corresponding flanges or valves are to be appropriately
identified and their function indicated.
iv)
v)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
vi)
vii)
viii)
Piping systems and their components are to be in accordance with Section 5 of this Guide.
ix)
Materials used for cementing system and equipment are to be in accordance with Section 6 of this
Guide.
x)
The mud circulating piping system is to be arranged so that the mud reconditioning system may be
run in a series with the degasser, desander, desilter and centrifuge so as to prevent mud from entering
other piping systems.
ii)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
iii)
iv)
v)
Piping systems and their components are to be in accordance with Section 5 of this Guide.
vi)
Materials used for mud return system and equipment are to be in accordance with Section 6 of this
Guide.
vii)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
Section
Drilling Systems
High-pressure mud pumps are to be fitted with safety relief valves whose maximum setting is no higher
than the maximum allowable pressure of the system.
i)
ii)
Where rupture disk type pressure relief devices are installed, rupture disks are to be certified to
meet a recognized standard and the disk assembly is to be subjected to survey in accordance with
the manufacturers specifications.
iii)
Rotary hoses in the well circulation system are to be designed and constructed in accordance with
5/3.7 of this Guide and API Spec 7K.
iv)
Piping systems and their components, and flexible lines are to be in accordance with Section 5 of
this Guide.
v)
Materials used for well circulation systems and equipment are to be in accordance with Section 6
of this Guide.
vi)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
9.7.1
9.7.2
i)
ii)
Materials and Welding/NDE used for major pressure-retaining equipment of the fluid
ends and mechanical load-bearing components are to be in accordance with Section 6 and
Section 7 of this Guide, respectively.
iii)
The fluid end and associated manifolds (suction and discharge) are to be hydrostatically
tested as required by Section 4, Table 1 of this Guide.
iv)
Motor couplings and shafting are to comply with a recognized standard and be suitable
for intended service in terms of maximum power and minimum operating temperature.
v)
The pumps are to be equipped with suitable vibration (pulsation) dampening devices.
vi)
Installation of pulsation dampeners is not mandatory for cement pumps, when all of the
following conditions are met:
Fluid-ends, discharge piping, and supports are designed and installed to withstand
pressure pulsation and they are to be in accordance with recognized codes and standards,
and
Intermittent duty.
vii)
Discharge high pressure piping to comply with ASME B31.3, or equivalent recognized
standard, and Section 5 of this Guide.
viii)
The prime movers (electric motor or diesel) are to be in accordance with Subsection 3/21
of this Guide.
ix)
Gears and couplings are to be in accordance with 3/21.5 and are to be suitable for their
intended service in terms of maximum power rating, service life and minimum operating
temperature.
69
Section
Drilling Systems
9.7.3
11
ii)
iii)
11.1
Hoisting
Derricks/Mast
Hoisting equipment/Drawwork
Lifting
Handling
-
BOP/Tubular (Pipe/Riser)
Rotary equipment
Miscellaneous equipment
Derricks/Masts
11.1.1 Recognized Codes and Standards
i)
Except as provided below, the design and fabrication of drilling derricks/masts are to be in
accordance with API Spec 4F, the ABS MODU Rules, and the additional requirements of
this Guide.
ii)
Alternatively, other recognized standards may be used when agreed to by ABS. When
alternate codes or standards are proposed, comparative analyses are to be provided to
demonstrate an equivalent level of safety to the recognized standards as listed in this Guide
and to be performed in accordance with 1/7.7 of this Guide, on a case-by-case basis.
iii)
Upper section: crown shaft, main crown beam, main top beams/water table beams
Lower section: legs, V door beams, shoes, and girths above and attached to the V
door beams
iv)
v)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
vi)
Complete Data Book, as specified in Annex A A.3 SR3 of API Spec 4F, is to be provided
for Surveyor review.
70
i)
ii)
The derrick design is to consider both fixed and pinned boundary conditions.
iii)
For fixed boundary condition, ABS allows a 20% increase in allowable stresses, as provided
in API Spec 4F.
iv)
The Owner/Operator is required to specify the geographic region of operation, the static loads
(dead weight, hook load, static rotary load, fluid load, setback loads, etc.) and dynamic loads
(inertial, dynamic amplification, erection, transportation, wind, transit, motion, acceleration,
seismic, etc.) on the derrick/mast, as required in API Spec 4F. Additionally, the following
loads are also to be given consideration, where applicable:
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
Drilling Systems
a)
The accumulation of ice and snow on a structure in increasing its dead load.
b)
The use of wind speeds higher than those provided in API Spec 4F,
where required by the Owner/Operator, for regions not specified within
API Spec 4F, ISO 19901-1, or API Bull 2INT-MET.
2)
The minimum wind velocity for unrestricted offshore service for all
normal drilling and transit conditions is not to be less than 36 m/s (70
knots), as specified in 3-1-3/1.3 in the ABS MODU Rules.
For host structures other than mobile offshore drilling units, such as
production unit or fixed structure, the transit conditions are to be in
compliance with ABS FPI Guide and ABS Facilities Rules.
3)
For the ABS MODU Rules unrestricted service, the wind speed to be
considered in the Survival Case (no hook load or setback loads) is not to
be taken less than 51.4 m/sec (100 knots).
4)
5)
c)
The use of a higher rated setback, where required by the operational demands of
the Owner/Operator.
d)
Dynamic loading due to motion of the hull are to be provided, as specified below,
by the Owner/Operator or designer as specified in API Spec 4F for installation,
transit, operation, survival condition of the floating units, as applicable. The above
conditions are not to be less than those specified in the ABS MODU Rules, ABS
Steel Vessel Rules, ABS Facilities Rules, ABS Barge Rules, and ABS FPI Guide.
1)
2)
3)
ii)
The following are the minimum vertical live loads that are to be considered in the design
of walkways:
71
Section
Drilling Systems
iii)
ii)
AISC permits a one-third increase in permissible stress for loading conditions that include
wind loads. Approval to increase AISC-specified stress limits by one-third is to be specially
approved for loading conditions which include loads resulting from wind speeds less than
36 m/sec. (70 knots).
iii)
Where the one-third increase is granted, it is to be verified that higher stress levels would
not have resulted from a loading condition where the wind- and motion-induced loads
were ignored and the one-third increase not used. That is, a static hook load analysis is to
be performed without using the one-third increase in allowable stress.
iv)
The extent to which fatigue has been considered in design is to be indicated in submitted
design documentation.
v)
vi)
ii)
The Factor of Safety (F.S.) will be specially considered when the stress components account
for surface stress due to lateral pressures.
2
eqv, = x2 + y2 x y + 3 xy
where
xy
Fy
F.S. =
1.43
1.11
72
ii)
(1 September 2012) Bolted connections in the main load path such as on upper mast,
foundation, and crown, etc. are to be provided with a locking mechanism.
iii)
(1 September 2012) Bolted connections which can cause fall hazards are to be provided
with secondary retention.
Section
Drilling Systems
iv)
11.3
Fatigue
v)
Bolt torqueing procedures are to include, but not limited to, sequencing, torque loads, etc.
vi)
Bolt materials are to be selected with consideration to stress corrosion cracking, fatigue,
marine environment, etc.
ii)
iii)
Zone management principle is to be followed for all hoisting activity in order to provide
additional safety to personnel and collision safeguard associated with drilling activities.
Zone management consideration can be any one or combinations of the following:
Markings
Proximity sensors
Strobe light
Alarms
iv)
Drawworks control is to be provided with deceleration parameters for upper and lower
limits for the traveling block/top drive to assist in stopping the load.
v)
Drawworks construction is to comply with API Spec 7F for chains and sprockets.
vi)
All mechanical load-bearing components are to be in compliance with API Spec 7K.
vii)
The mechanical coupling between the drawworks drum and the electromagnetic brake is
to be provided with a system to prevent unintentional disengagement.
viii)
Drawworks auxiliary brakes and all other electrical power and control systems are to be
suitable for the intended hazardous area.
ix)
(bT ) 2 + (mM ) 2
mm
d = 0.10
(bT ) 2 + (mM ) 2
in.
where
d
0.073 + (19.5/Y)
0.073 + (27,800/Y)
for US units
121/(42.2 + Y)
172,000/(60,000 + Y)
for US units
73
Section
Drilling Systems
x)
For hydrodynamic brake systems, detailed drawings and supporting calculations proving
that the proposed braking system is as effective as other drawworks braking systems are
to be submitted for review.
xi)
xii)
Cooling water temperature and flow indicators and alarms for abnormal or upset
conditions.
b)
c)
A system that monitors either electrical faults within the system or the kinetic energy
of the traveling block arranged to actuate the emergency stop system. Where a
fault monitoring system is provided, provisions are to include the following:
d)
1)
2)
3)
4)
5)
Audible and visual alarms at the drillers control panel to indicate when
the limiting parameters of the auxiliary brake have been reached or when
the emergency stop system has been activated
6)
xiii)
Drawwork designs, including drums and wire ropes, are to comply with the applicable
part of 3/11.5.2 of this Guide.
xiv)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
xv)
xvi)
Gears and couplings are to be in accordance with 3/21.5 and are to be suitable for their
intended service in terms of maximum power rating, service life and minimum operating
temperature.
xvii)
xviii)
xix)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
74
ii)
Power swivels, rotary swivel and top drives are to be designed in compliance with API
Spec 8A or Spec 8C and the additional requirements of this Guide.
iii)
iv)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
Drilling Systems
v)
vi)
vii)
Gears and couplings are to be in accordance with 3/21.5 and are to be suitable for their
intended service in terms of maximum power rating, service life and minimum operating
temperature.
viii)
ix)
x)
Welding and NDE are to be carried out in accordance with Section 7 of this Guide, as
applicable.
ii)
Anti-crown collision/upper limits and lower limit safety devices are to be installed to prevent
the traveling block from contacting the crown block. These safety devices are to be designed
to be fail-safe.
iii)
Testing intervals for the safety devices are to be agreed upon by the Owner/Operator, but
is not to be less frequent than as specified by the drawworks manufacturer.
iv)
ii)
The results of the prototype load test if required in API Spec 8A or Spec 8C along with
design calculations for the component tested are to be submitted with the design specification
outlined in Subsection 2/7 of this Guide.
iii)
iv)
v)
Lighting fixtures and other equipment installed in the derrick are to be secured against
vibration to prevent falling.
vi)
Gears and couplings are to be in accordance with 3/21.5 and are to be suitable for their
intended service in terms of maximum power rating, service life and minimum operating
temperature.
vii)
viii)
Welding and NDE are to be carried out in accordance with Section 7 of this Guide, as
applicable.
75
Section
11.5
Drilling Systems
Lifting Equipment
(1 September 2012) Typical lifting equipment are cranes (gantry, king post, knuckle boom, bridge racker),
base-mounted winches, personnel handling devices, specialized automated handling equipment for lifting
purpose, etc., that are used for pipe handling, riser handling, LMRP handling, BOP handling, and for other
lifting activities associated with drilling operations.
11.5.1 Cranes (1 September 2012)
i)
Cranes are to be designed, constructed, and tested in accordance with the requirements of
API Spec 2C or the ABS Lifting Appliances Guide.
ii)
When alternate codes or standards are proposed, comparative analyses are to be provided
to demonstrate an equivalent level of safety to the recognized standards as listed in this Guide
and to be performed in accordance with 1/7.7 of this Guide, on a case-by-case basis.
iii)
Design loads of the crane winches are to be the maximum line pull based on the design
loading or the load created by dynamic braking, in accordance with the above design code.
In either case, the distribution of loading from the reeving system is to be taken into account.
iv)
v)
Drums and brakes are to be in accordance with API Spec 2C or the ABS Lifting Appliances
Guide.
vi)
vii)
Design loads of the crane cylinders are to be the loads applied by the crane boom(s), in
accordance with the design code. Allowable stresses or minimum scantlings are to be in
accordance with ABS Rules or other recognized standard.
viii)
Design loading for crane accumulators and crane piping systems is the resultant pressure
as a result of the design loadings from the design code.
ix)
Zone management principle is to be followed for all lifting activity in order to provide
additional safety to personnel and collision safeguard associated with drilling activities. See
3/11.3.1iii).
x)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
xi)
xii)
xiii)
Gears and couplings are to be in accordance with 3/21.5 and are to be suitable for their
intended service in terms of maximum power rating, service life and minimum operating
temperature.
xiv)
xv)
xvi)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
76
Recommended single line pull at specified speed, drum size and layers of wire rope
(1 September 2012) Where the final elevation of the load being lifting is higher than the winch
elevation, the designer is to consider that the weight of active line towards winch is not to
exceed the dead load.
Section
Drilling Systems
Bases and other structural steel components are to be designed in accordance with AISC
or other recognized standard. Allowable stress for bending, tension, shear and buckling
are to be as specified herein.
ii)
Factors of safety and critical ratios for wire rope, drums, shafts and other parts are as follows:
(1 September 2012) Wire rope for lifting application is to be rated in accordance with
API Spec 9A or equivalent.
Fcr/1.25
Fcr/1.55
Fa
Fy/1.33
Fa
(Fy + Fu)/3.25
Fs
0.577Fa
Fa
Fs
Fy
Fu
Fcr
where
iii)
All mechanical parts where failure could terminate the load-carrying capabilities of the
systems are to be made of steel.
ii)
Use of ductile iron for gears and drum and the use of aluminum for fabrication will be
specially considered.
iii)
(1 September 2012) Gears and couplings are to be in accordance with 3/21.5 and are to be
suitable for their intended service in terms of maximum power rating, service life and
minimum operating temperature.
iv)
(1 September 2012) Piping systems are to be in accordance with Section 5 of this Guide.
v)
vi)
Welding, heat treatment and NDE are to be in accordance with Section 7 of this Guide, as
applicable.
11.5.2(d) Drums.
i)
The drum capacity is to accommodate the recommended rope size and length necessary to
perform the function required for the load-handling equipment.
ii)
Plain or grooved drums will normally be considered acceptable, provided no less than five
(5) full wraps of rope remain on the drum with the load in its lowest possible position. Other
design specifications/standards will be subject to special consideration based on calculations
submitted to ABS.
iii)
Each drum end of the rope is to be anchored by a clamp attached to the drum, or by a
socket arrangement approved by the hoist or rope manufacturer, providing for attachment
of rope to the drum.
77
Section
Drilling Systems
iv)
The outermost wrap layer of a wire rope in any load case must be at least two rope
diameters below the edge of the drum flange.
v)
The diameter of the drum is to provide first layer rope pitch diameter of not less than 18
times the nominal diameter of the rope used.
vi)
vii)
Welding, heat treatment and NDE are to be in accordance with Section 7 of this Guide, as
applicable.
(1 September 2012) Wire ropes are to be constructed in accordance with a recognized standard
applicable to the intended service, such as API Spec 9A or equivalent.
ii)
Usage records such as ton-mile records are to be maintained and wire rope changed out in
accordance with manufacturers recommendations.
iii)
11.5.2(f) Brakes.
i)
A power control braking means such as regenerative, dynamic, counter torque breaking,
controlled lowering or a mechanically-controlled braking means are to be provided and
are to be capable of maintaining controlled lowering speeds.
ii)
Brakes are to set automatically upon loss of power or when the winch lever is returned to
neutral.
iii)
Brakes are to have the ability to stop and hold 100% of the design load with the outermost
layer of wire on the drum.
iv)
v)
vi)
Documentation and calculations for the braking effect of the AC motors are to be submitted
when they are the only backup system to the disc brakes.
11.5.3(b) Personnel Baskets. Personnel baskets also known as maintenance or service baskets are
intended for lifting of personnel for access to work positions. Personnel baskets can be attached to
other lifting equipment or can be a dedicated assembled unit (basket and lifting machinery).
i)
Structural and mechanical components are to comply with the ABS Lifting Appliances
Guide, for personnel rating.
Alternative design codes and standards will be specially considered by ABS with justifications
in accordance with 1/7.7 of this Guide.
ii)
A SWL is to be specified for the personnel basket, considering all applicable static and
dynamic loads for intended service.
iii)
The personnel basket is to be marked with the SWL and the maximum number of personnel
it is designed to carry.
iv)
The dimensional sizing of the personnel basket is to be based on the maximum number of
personnel and working tools in the basket.
78
Section
Drilling Systems
v)
vi)
Safety principle of personnel basket system is to have positive load control at all times in
order to prevent free-fall of basket upon failure and/or malfunction of system/component
and/or their control system.
vii)
All load control systems/mechanisms (e.g., brake, hydraulic cylinder, system etc.) are to
be fail-safe in order to satisfy the safety principle of 3/11.5.3(b)vi).
viii)
Provision is to be made for emergency stop of the basket operations by the operator(s) at
the control station in the personnel basket, at a remote control station and/or at any other
control station, as applicable.
ix)
All slewing arrangements are to be provided with fail-safe system to have positive swing
control all time.
x)
Control levers for personnel basket control systems are to return automatically to their
center (neutral) positions upon release.
xi)
Brake is to be automatically engaged when the control lever is returned to the neutral position.
xii)
All brakes shall be designed to stop and hold the personnel basket at all operating speeds
and configurations.
xiii)
The personnel basket is to be provided with anchorage point for attachment of personnel
fall protection lanyards.
xiv)
The access gate on a personnel basket, including sliding or folding types, if installed, is to
have a positive-acting device to restrain the gate from accidental opening. Swinging type
access gates are to open only to the interior of the personnel basket.
xv)
xvi)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
xvii)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
xviii)
Electrical systems are to be in accordance with Subsection 3/19 of this Guide and the
ABS MODU Rules.
xix)
xx)
Materials are to be in accordance with Section 6 of this Guide and the ABS MODU Rules.
xxi)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
11.5.3(c) Manriding Winches. Manriding winches are to comply with the general requirements
of this section. In addition, the following minimum criteria are to be complied with:
i)
The personnel rated load is to be no greater than 20% of the load calculated in accordance
with 3/11.5.2 of this Guide.
ii)
The winch operating lever is to automatically return to neutral upon release from any
position. All positions are to be clearly marked as to their intended function.
iii)
iv)
v)
Brakes are to set automatically upon loss of power or when the winch lever is returned to
neutral.
vi)
A secondary brake is to be provided to prevent the load from falling in the event of failure
of the primary automatic brake.
vii)
79
Section
Drilling Systems
viii)
Devices are to be fitted to prevent the winch from overriding or underriding, and a secondary
means of lowering personnel is to be provided in case of winch or power failure.
ix)
Wire rope for personnel lifting devices is to be in accordance with API Spec 9A or equivalent.
x)
Setting of upper limit is to provide at least a vertical clearance of six (6) feet from the
upper block, and the lower limit is to be set so that the winch cannot be operated with
number of wraps less than specified in 3/11.5.2(d) of this Guide.
xi)
All winches are to be identified as Manrider Only and marked with their SWL.
xii)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
xiii)
11.5.4 Lifting Attachments: Anchor Points and Pad Eyes (1 September 2012)
i)
Design loads and allowable stresses for lifting attachment are to be for offshore applications
in accordance with the requirements of API RP 2A WSD or specified design code and
standard.
ii)
Lifting attachments are to be free from stress concentration points (e.g., geometric
discontinuities, sharp weld edges, etc.).
iii)
ABS
Review
Load
Testing
a)
b)
c)
d)
Sea-fastening anchor points for drilling unit transit with no designated SWL.
NA
e)
Anchor points used for secondary retention with no designated SWL and
SWL > 0.25 MT.
NA
f)
NA
NA
ii)
iii)
80
The air supply lines are to be sized to operate the winch at safe working loads
(SWL).
b)
c)
Motor exhaust is to be vented to a point where it will not present hazard to personnel
and noise reduction devices are to be provided.
An air regulator and pressure relief valve, located upstream of the non-return valves, are
to be provided to limit air supply pressure to the winch, and the supply lines serving the
winches are to be fitted with appropriate non-return valves and water separators/filters
before the operating valves.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
11.7
Drilling Systems
i)
ii)
Zone management principle is to be followed for all BOP handling activity in order to provide
additional safety to personnel and collision safeguard associated with drilling activities.
See 3/11.3.1iii).
iii)
iv)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
v)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
vi)
Electrical systems are to be in accordance with Subsection 3/19 of this Guide and the
ABS MODU Rules.
vii)
viii)
Materials are to be in accordance with Section 6 of this Guide and the ABS MODU Rules.
ix)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
i)
ii)
Zone management principle is to be followed for all tubular handling activity in order to
provide additional safety to personnel and collision safeguard associated with drilling
activities. See 3/11.3.1iii).
iii)
All drill pipes, collars, tubing and casing that may be racked in the derrick are to have
provisions to be secured in place.
iv)
All storage racks are to be designed to prevent drill collars, pipe and other tubulars from
being unintended release from the rack.
v)
Foundations and storage racks are to be designed to withstand the maximum anticipated
setback load of the racked pipe, drill collars and other intended loads.
vi)
Storage racks are to be provided with appropriate drip pans and drains to direct mud and
other liquids to appropriate drain system.
vii)
viii)
ix)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
x)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
xi)
81
Section
Drilling Systems
i)
The rails and masts supporting the casing stabbing board are to be securely attached to their
supports, designed so that they are unable to open under operating conditions and capable
of supporting the casing stabbing board in the event of the operation of the safety gear.
ii)
The guides and runners are to be designed so that in the event of a roller or wheel failure,
the platform cannot become detached from the mast.
iii)
Plates that are capable of supporting the weight of the fully loaded platform are to be
fitted at the bottom of the rail.
iv)
Upper and lower limits are to be provided and tested before use.
v)
The controls are to be arranged to stop the platform if the raising and lowering handle is
released.
ii)
Two (2) independent locking devices are to be provided. One (1) locking device is to be
engaged when the lifting handle is in neutral and the second is to engage upon failure of
the hoisting system.
iii)
iv)
All platforms are to be fitted with sufficient anchoring points for safety harnesses.
v)
A non-slip surface is to be provided on the platform, and adequate handrails, midrails and
toe-plates are to be provided in accordance with Section 5-3-1 of the ABS MODU Rules.
vi)
The platform is to be fitted with a lock latch mechanism that secures it when it is not in
motion.
vii)
Additionally, adequate safety gear of the progressive type is to be provided, and designed
so that it will be engaged within free fall conditions.
viii)
Where two-point operation is used, the operator station in the basket is to override the remote.
ix)
A safety override at the remote station is to be installed for use in the event that the workperforming personnel are incapacitated.
82
i)
Lifting is to be arranged for both raising and lowering of the platform. The arrangement is
not to be such that it is possible to lower the platform by brake only.
ii)
Means of lowering the man to the drill floor must be provided that will function in case of
failure of the normal lifting mechanism.
iii)
iv)
The factor of safety for rope or chain is not to be less than 10:1.
v)
If rack and pinion systems are used, they are to be designed so that the failure of either a
rack or pinion will not cause the platform to fall.
vi)
The lifting system is to incorporate sufficient rope so that there are at least five (5) full
turns of rope remaining on the winding drum when the platform is at its maximum level.
vii)
The equipment associated with the operation of the casing stabbing board is to be securely
anchored to the derrick structure.
viii)
The anchorages for rope or chain are to be designed such that they will not be adversely
affected by corrosion.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
11.9
Drilling Systems
All mechanical load-bearing components are to be in compliance with API Spec 7K.
ii)
Load-bearing beams are to be in accordance with 3-2-2/5 of the ABS MODU Rules and the
requirements for structural materials in Section 6 of this Guide.
iii)
The rotary table transmission and associated motor couplings and shafting are to comply with a
recognized standard and be suitable for the intended service in terms of maximum power and minimum
operating temperature.
iv)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
v)
vi)
vii)
viii)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
All tongs are to be capable of being securely attached to the derrick mast or back-up post and anchored
by appropriate means such as a wire rope line or stiff arm that will have a breaking strength greater
than the force exerted by the tongs.
ii)
Safety lines on tongs are to be positioned in such a manner that the tongs cannot rotate beyond
anticipated limits.
iii)
Power tong pressure systems are to be equipped with safety relief valves that are to be set no higher
than the maximum working pressure of the system.
iv)
Safety cables attached to kelly hose, tongs and other suspended equipment are to be properly secured
to prevent their breaking loose in the event of a connection failure.
v)
Major mechanical load-bearing components are to be in accordance with 3/11.3.4 of this Guide, as
applicable.
vi)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
vii)
Hydraulic and pneumatic cylinders are to be in accordance with 3/17.3 of this Guide.
viii)
Electrical systems are to be in accordance with Subsection 3/19 of this Guide and the ABS MODU
Rules.
ix)
x)
Materials are to be in accordance with Section 6 of this Guide and the ABS MODU Rules.
xi)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable
83
Section
13
Drilling Systems
13.1
84
i)
Systems mounted permanently for at least 30 months on an installation and are intended for extended
tests or early production are also to comply with the ABS Facilities Rules.
ii)
Temporary well test systems (for less than 30 months), including burner booms, burners, well test
equipment, process pressure vessels, piping, burners and gas flares, and control/safety systems are
also to comply with the requirements of this Guide.
iii)
iv)
Individual well test equipment and/or skid-mounted equipment structural interface with the drilling
unit is to be verified for structural adequacy in accordance with the ABS MODU Rules.
Well control equipment such as flowheads, test trees and ESD valves are to be suitable for the
intended pressure. Design and fabrication are to be in accordance with recognized standards such
as API Spec 6A, API Spec 16C, API Spec 6D, and API Spec 6AV1.
ii)
Pressure-retaining equipment such as separators, heaters, treaters, nitrogen storage, surge and transfer
tanks, etc., are to be in accordance with Subsection 3/17 of this Guide.
iii)
At least two (2) relief valves or the equivalent are to be provided on test separators. The relief valve
vent lines are to be led outboard at least 120 pipe diameters or connected to a suitable hydrocarbon
disposal facility in accordance with 3/13.5 of this Guide.
iv)
Any vent line valving is to be interlocked to provide one open flow path for all vents at any time.
v)
Well test oil/gas separators are to be in compliance with the requirements of API Spec 12J.
vi)
Flexible lines are to be designed and constructed in accordance with 3-3/19.7 and Appendix 2 of
the ABS Facilities Rules and 5/3.7 of this Guide.
vii)
Pumps handling hydrocarbon are to be in compliance with the requirements of ANSI/API Std. 610.
viii)
The well test system burner/flare boom structure is to be in compliance with 3/13.3 of this Guide
and the ABS Guide for Well Test Systems.
ix)
The control systems are to be in accordance with Subsection 3/15 of this Guide.
x)
Electrical components are to be certified for use for their intended service and classified areas as
outlined in 3/13.9 of this Guide. Electrical installations are to be in accordance with Subsection
3/19 of this Guide.
xi)
xii)
Piping systems and components are to be in accordance with Sections 5 of this Guide.
xiii)
xiv)
Welding and NDE are to be in accordance with Section 7 of this Guide, as applicable.
Section
13.3
Drilling Systems
Burner/Flare Booms
13.3.1 Design
i)
The use of the flare boom is to extend and support the burner/flare at a safe distance away
from the drilling area. This is to limit exposure of personnel, equipment, and helicopter
traffic to vent gas, flare exhaust, or flare radiation.
ii)
Flare and vent analysis are to be in compliance with 3-3/11.5 of the ABS Facilities Rules
and the additional requirements of this Guide.
13.5
13.7
Dead weight of structure, piping, fittings, rigging, snow and ice, walkways, guard rails,
etc.
Wind loads
Thermal and impulsive loads resulting from the use of the flare
ii)
The values of all design loads are to be listed in the submitted design documentation.
iii)
Loads resulting from vessel motions and wind loads can be established using the procedures
given in API Spec 4F.
iv)
The derivation of loading conditions to be used in the design is to give due account of the
operational requirements of the Owner/Operator, and are to reflect both the operational and
stowed modes of the boom.
The sizing and design of the hydrocarbon disposal equipment (flare, flare tips, scrubber, piping,
pump, atomization equipment, etc.) are to follow the principles of API Std. 521.
ii)
Two (2) flares are to be provided on opposite sides of the installation to dispose hydrocarbon in an
appropriate downwind direction.
iii)
Flares and burner booms are to be arranged such that the incident heat on critical surfaces does not
exceed 1500 BTU/hr/ft2 (including solar gain).
iv)
In cases where crude oil is burned and atomization is used, atomization medium supply lines are
to be provided with a non-return valve or some other approved means of preventing backflow of
hydrocarbon into nonhazardous piping systems.
v)
Gas flare tip flow rate is generally not to exceed 0.5 Mach. (See API Std. 521).
ii)
iii)
Visual and audible alarms are to be set at 20% and 60% (LEL) lower explosive limit and in the
presence of H2S 10 PPM and 15 PPM.
iv)
85
Section
13.9
Drilling Systems
v)
The arrangement of process components onboard is to allow for complete access to process controls
and ingress for fire extinguishing agents.
vi)
vii)
Each well injection line is to be provided with a check valve located at a flowhead or test tree.
Classified Areas
Classified areas are to be in accordance with the ABS MODU Rules, API RP 500 or API RP 505 and
consideration given to the following:
i)
Hatches, companionways and ventilators within ten feet of classified areas are to be secured gas
tight for the duration of the test program.
ii)
Electrical equipment within classified areas is to be suitable for the hazard or de-energized.
iii)
(1 September 2012) Areas around valves, socket hammer unions, and articulated piping are to be
designated as Class 1 Division 2 (Zone 2) for a distance of 1 m. (3 ft).
iv)
Fired heaters and diesel driven machinery (i.e., crude oil pumps, air compressors, etc.) are to have
air intakes located at least ten (10) feet from any classified area.
v)
Exhausts are to be equipped with spark arresting devices and are to discharge outside classified areas.
ii)
Manning requirements
iii)
iv)
v)
Fire-fighting procedures
vi)
15
Control Systems
15.1
Control Systems
15.1.1 Control System General (1 September 2012)
Control system is an assembly of devices interconnected or otherwise coordinated to convey the
command or order. Control system can be hydraulic, pneumatic, electric, electro-hydraulic, acoustic,
etc., or combination thereof.
The requirements below are to apply to well control systems, drilling systems and control systems
covered by this Guide.
i)
ii)
86
Section
Drilling Systems
b)
iii)
Transfer between control stations only applies to drilling control systems and
does not apply to BOP, EDS, choke and kill, and diverter control systems.
b)
When control of the system or equipment is possible from more than one
control location, control is to be possible only from one control location
at a time.
2)
3)
iv)
v)
Visual and audible alarms are to be provided to indicate an alarm condition of a monitored
parameter.
vi)
15.3
i)
When logic circuits are used for sequential startup or for operating individual components,
indicators are to be provided at the control console to show the successful completion of the
sequence of operations by the logic circuit and start-up and operation of the component. If
some particular step is not carried out during the sequence, the sequence is to stop at this point.
ii)
Manual override is to be fitted in vital functions to permit control in the case of failure of
a logic circuit.
The control system (hydraulic, pneumatic, electric, electro-hydraulic, acoustic, etc.) is to be designed
where no single control system component failure is to lead to a failure of the controlled system, loss
of control or loss of well control.
ii)
The control system and components are to be in compliance with API Spec 16C, API Spec 16D
and with applicable recommended practices such as API RP 53, API RP 59, and API RP 64.
iii)
See 3/3.1.2, 3/3.5.9 and 3/3.7.3 of this Guide for control system requirements for individual well
control systems and/or equipment.
iv)
Computer-based control systems for well control are to comply with the requirements for control
systems for well control equipment in 3/15.3 of this Guide and the requirements for computer-based
system in 3/15.5.2 of this Guide.
v)
Computer-based control systems for BOPs are to also comply with the following additional
requirements:
Local and remote I/O modules are to fail in a predetermined fashion when there is loss of
communications with the processor.
Input and Output channels are to be diagnostic type, where the program will read the diagnostic
status of the I/O and perform safe actions. The program is to notify the operator if a channel
fails
87
Section
vi)
Drilling Systems
Alternative arrangements can be specially considered for surface BOPs, instead of redundant
components, provided it can be demonstrated that the computer-based control system complies
with the single control system component failure principle indicated in 3/15.3i) of the Guide.
For example, an arrangement with a single processor does not appear to comply. However, an
arrangement with a single processor along with additional arrangements that address the possible
single control system component failure concept can be specially considered. This special
consideration is subject to ABS review of the supporting documentation
vii)
FMEA, FMECA or similar analysis is to be conducted to determine compliance with the design
principles of Subsection 3/3, 3/15.1, and 3/15.3 of this Guide.
15.5
The Note of 3/15.1.1ii)a) is not applicable to control systems for well control equipment.
viii)
The control systems are to be provided with additional measures to prevent accidental disconnection
of the wellhead connector, the LMRP connector or the riser connector, such as two-hand function,
two-step action, protective cover or equivalent.
ix)
For BOP control systems where functions are executed manually, only visual indicators are required.
Computer-based systems are to comply with the requirements of 3/15.5.1 of this Guide and 4-9-6/3
(except 4-9-6/3.13 and 4-9-6/3.15) of the ABS Steel Vessel Rules.
In addition, computer-based systems are to comply with the following:
15.5.2(a) Fail Safe. Computer-based systems are to be designed such that any of the systems
components will not cause unsafe operation of the system or equipment being controlled.
15.5.2(b) FMEA, FMECA
i)
ii)
If the computer-based control system is for well control, the detailed FMEA, FMECA or
similar analysis is to be conducted for the computer-based systems covering all components
to determine compliance with the design principles of Subsection 3/3, 3/15.1, 3/15.3 and
3/15.5 of this Guide.
88
i)
When computer-based systems have safety-related control functions and the associated
failure modes identified in the FMEA/FMECA result in an undesirable situation, special
consideration may be given, provided the appropriate level of safety integrity has been
provided.
ii)
iii)
Section
15.7
Drilling Systems
ii)
Alarms are to be given at each control location, including any local manual control positions when
the system performs a safety action.
iii)
Drilling systems or equipment shut down by a safety action is to be designed not to restart
automatically, unless first actuated by a manual reset.
iv)
All shutdowns are to be executed in a predetermined logical manner, as specified in the shutdown
logic and/or shutdown cause and effect charts, and are to execute actions to:
Protect personnel
v)
vi)
The shutdown systems are to be designed such that when a shutdown is activated, any ongoing
operations can be terminated without leading to an unsafe situation.
17
17.1
Pressure Vessels
Pressure vessels are considered to be accumulators, heat exchangers, pulsation dampeners, separators (oil/gas),
mud-gas separators, and degassers.
i)
Pressure vessels are to be designed, constructed, and tested in accordance with ASME Boiler and
Pressure Vessel Code Section VIII Div. 1 or Div. 2. Alternative design codes and standards will
be specially considered by ABS with justifications in accordance with 1/7.7 of this Guide.
ii)
Pressure vessels utilized in drilling systems are to be submitted for ABS approval in accordance
with 6-1-5/1.1 of the ABS MODU Rules.
iii)
For the purpose of specifying the degree of survey and testing during the ABS approval process,
pressure vessels are to be categorized in accordance with 6-1-5/Table 3 of the ABS MODU Rules,
and Section 4, Table 1 of this Guide.
iv)
Well test oil/gas separators are to be in accordance with the requirements of API Spec 12J.
v)
The design is also to be such that stresses due to acceleration forces arising out of the motion of
the installation, stresses due to external nozzle loads and moments, and stresses due to any other
applicable external forces, such as winds, are within the limits allowed by the design code.
vi)
All pressure vessels, accumulators, heat exchangers, and separators are to be suitably supported
and properly secured to skid structure or rig floor.
vii)
Materials of manufacturing for pressure vessels are to be in accordance with the specified design
code and Section 6 of this Guide, and appropriately selected for the intended service.
viii)
Welding and NDE for pressure vessels are to be in accordance with the specified design code and
Section 7 of this Guide.
89
Section
17.3
19
Drilling Systems
Hydraulic Cylinders
Hydraulic cylinders are to comply with the following requirements:
i)
Design and manufacturing are to be based upon the strength criteria of the ASME Boiler and Pressure
Vessel Code Section VIII Div. 1 or Div. 2, National Fluid Power Association or other recognized
standards.
ii)
Hydraulic cylinders in critical load path and/or applications are to be submitted for ABS approval
in accordance with Section 4, Table 1 of this Guide.
iii)
Hydraulic cylinders that are part of overhead lifting or hoisting equipment are to meet 3/11.3.4 of
this Guide, as applicable.
iv)
Materials of manufacturing for hydraulic cylinders are to be in accordance with the specified
design code and Section 6 of this Guide, and appropriately selected for the intended service.
v)
Welding and NDE for hydraulic cylinders are to be in accordance with the specified design code
and Section 7 of this Guide, as applicable.
(1 September 2012) Compliance with industry standards, such as the following, will be specially
considered:
API RP 500
IEEE Std. 45
API RP 505
API RP 2003
IEC 61892
NFPA 70
IEEE C37.06.1
NFPA 496
IEEE C37.20.6
ii)
ABS is prepared to consider other industry standards and practices for electrical equipment, on a
case-by-case basis, with justifications through novel features and/or comparative analyses to be
provided to demonstrate equivalent level of safety to the recognized standards as listed in this
Guide, performed in accordance with 1/7.7 of this Guide.
iii)
All electrical components are to be designed to meet safe operating conditions by accounting for
maximum and minimum temperatures and vibrations expected during service.
iv)
21
21.1
90
i)
ii)
iii)
The recommended service applications together with curves showing the recommended maximum
standard brake horsepower within the recommended speed range for each service are to be submitted.
iv)
Testing is to be performed under an approved quality assurance program or in the presence of the
Surveyor, and the test report/data is to be included in the manufacturers affidavit of compliance.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
21.3
21.5
23
Drilling Systems
All rotating machines (if any) 100 kW (135 hp) and above are to be of an ABS-approved design in
accordance with the ABS MODU Rules, tested in the presence of and inspected by the Surveyor,
preferably at the plant of the manufacturer.
ii)
For machines of less than 100 kW (135 hp), the tests may be carried out by the manufacturer whose
certificate of tests (test reports) may be acceptable and is to be included in the manufacturers
affidavit of compliance.
All gears and couplings having a rated power of 100 kW (135 hp) and over are to be designed,
constructed, certified and installed in accordance with AGMA, ISO or equivalent. ABS is to review
the design and the gears are to be constructed under the attendance of the ABS Surveyor.
ii)
All gears and couplings having a rated power of less than 100 kW (135 hp) are to be designed,
constructed and equipped in accordance with recognized commercial and marine practice.
Acceptance of such gears will be based on manufacturers affidavit stating compliance with a
recognized standard, verification of gear nameplate data and subject to a satisfactory performance
test after installation conducted in the presence of the Surveyor.
iii)
Pressure Wash
Chemical injection
Cementing skid
Sea water
The control systems are to be in accordance with Subsection 3/15 of this Guide.
ii)
iii)
iv)
Piping systems and their components are to be in accordance with Section 5 of this Guide.
v)
vi)
91
Section
23.1
23.3
92
Drilling Systems
Skid Structures
Skid structures including the lifting attachments are to comply with the following requirements:
i)
Skid structures for drilling system equipment packaged units are to be sufficiently rigid to support
the mounted equipment and piping and, as required, to permit lifting during shipment without
damage to the equipment or piping.
ii)
Structural design calculations for skid units with a center of gravity height of more than 1.5 m (5 ft),
or a maximum operating weight in excess of 10 MT (metric tons) or 22.05 Kips, calculated in dry
conditions, are to be submitted for review.
iii)
(1 September 2012) Lifting attachment, including the attachment to the skid structure are to be
designed in accordance with the requirements of API RP 2A WSD and/or the ABS Lifting Appliances
Guide.
iv)
(1 September 2012) Load testing of the lifting attachments, including the attachment to the skid
structure is to be performed in accordance with 3/11.5.4 and Section 4, Table 1 of this Guide.
Drip Pans
Drip pans are to comply with the following requirements:
i)
Drip pans are to be provided to contain liquid spills and leaks from skid-mounted equipment and
piping, and to drain the liquid with adequate slope of 1 cm per meter (0.125 inch per foot) into
open drain systems.
ii)
A minimum 150 mm (6 in.) coaming around the entire perimeter of a skid is to be provided.
iii)
(1 September 2012) Spill containment with less than 150 mm (6 in.) coaming arrangement is subject
to special consideration (see 1/7.7, Alternatives).
iv)
Calculations showing sufficient spillage containment for the skid are to be submitted for verification.
v)
Skid beams that extend above the drip pan may be considered as meeting the coaming requirement,
provided that the drip pan is seal-welded to the skid beams.
SECTION
General
This section provides detailed procedures for ABS approval of typical drilling systems, subsystems, equipment,
and/or components for Classification of drilling system, that require design approval and survey in accordance
with Section 4, Table 1.
i)
Section 4, Table 1 is provided as a general reference listing, and is not to be considered as the complete
drilling system, subsystem, equipment or component listing.
ii)
For drilling systems, subsystems, equipment or components not listed, the designer/manufacturer
is to contact the appropriate ABS Technical office for guidance on the approval process.
iii)
ABS is prepared to consider alternative design methodology and industry practice for drilling system,
subsystems, equipment, and/or component designs, on a case-by-case basis, with justifications through
novel features as indicated in 1/7.7 of this Guide.
Drilling systems, subsystems, equipment, and/or components, including drilling support systems,
are to be approved according to the following general procedures:
a)
Design plans and data are to be submitted in accordance with this section and Subsection
2/7 of this Guide.
b)
ABS design review for issuance of the following documents (see 4/3.5 of this Guide):
c)
1)
2)
ABS survey at plant (see 4/3.3.1), and at installation and commissioning (see 4/3.3.2), as
applicable, for issuance of the following documents (see 4/3.5 of this Guide):
1)
Survey Report (SR) [see Section 4, Table 1 and Appendix 5 of this Guide]
2)
ii)
ABSs issuance of reports and certificates is to be in accordance with 4/3.5 and Appendices 3, 4
and 5 of this Guide.
iii)
Approval of individual or unit equipment and/or components can be combined towards the approval
of complete systems or subsystems.
iv)
ABS design review, survey, and the issuance of applicable reports or certificates constitute the
ABS Classification of the drilling system inclusive of the subsystems, equipment and components.
93
Section
3.1
Design Review
Drilling system, subsystems, equipment, and/or components that require ABS design review and, subsequently,
an ABS approval letter, and an IRC, as required for ABS Classification, are listed in Subsection 2/7 and
Section 4, Table 1 and are detailed throughout this Guide.
i)
ABS design review verifies that the design of systems, subsystems, equipment, and/or components
meets the requirements of this Guide and the specified design codes, standards, or specifications,
as applicable.
ii)
iii)
(1 September 2012) Upon satisfactory completion of the design review process, ABS will issue an
ABS approval letter/PDA, and an IRC, as applicable in accordance with 4/3.5 and Section 4,
Table 1 of this Guide.
iv)
Stress calculations/analysis
Testing
In this case, the manufacturer must provide details of the exception(s) to part(s) or section(s) of
recognized design standards in the Design Basis submittal, as referenced in Subsection 2/7 and
clearly stated in detail on the manufacturers affidavit of compliance as specified in 4/3.1.2 of this
Guide.
v)
3.1.1
3.1.2
94
(1 September 2012) It is recommended that at beginning of each project a kick-off meeting between
the manufacturer/fabricator and ABS Engineering office engineer/project manager is to be scheduled
in order, but not limited to:
Confirm and/or establish the main point of contacts (PoC) for the design review
Confirm submission requirement for design review and manufacturing such as specification,
drawings and/or documentation associated with the design and manufacturing process
ii)
It is to be noted that no changes can be made to the design details on the PDA from the
date of issuance. Any design changes will require a revision to the PDA.
iii)
Manufacturer/designers with existing PDAs for other equipment or components, not specified
in Section 4, Table, 1 of this Guide will be specially considered.
Section
ii)
3.1.3
iii)
iv)
Extension of Approval
i)
If drilling equipment and/or components have been previously approved by ABS, the
manufacturer can request extension of approval for a new project, clearly stating that no
changes have been made to the equipment and/or components from the previous approval.
ii)
3.3
If changes are made from previously approved equipment and/or components, documentation
identifying and justification of the changes are required to be submitted for ABS review
and approval.
ABS Survey
3.3.1
Survey at Plant
i)
ABS Surveyors attendance is required at the plant of manufacturing for drilling system,
subsystems, equipment, and/or components approval, as indicated in Section 4, Table 1
and in accordance with Subsection 8/3 of this Guide.
ii)
Load testing
Post-test NDE
FMECA validations
FAT
Where final testing requires assembly and installation on-board a facility, a partial survey
report will be issued by the attending Surveyor for the work and partial testing completed
at the manufacturing facility. After final testing on-board, the attending Surveyor will
issue the final survey reports or CoC.
iv)
(1 September 2012) Upon satisfactory completion of the Surveyors witness of the completed
drilling system, subsystems, equipment, and/or components manufacturing process, a survey
report and/or CoC will be issued in accordance with 4/3.5.
95
Section
3.3.2
ii)
3.5
Functional testing
3.5.2
ii)
The ABS approval letter will describe the scope and results, including any applicable
comments and correspondences for the design review performed of the submitted design
plans and data, and the specified engineering criteria. The approved rating and/or capacity
will be indicated for each system, subsystem, equipment or component in the ABS approval
letter.
iii)
(1 September 2012) The ABS Surveyor will issue appropriate survey report(s) (SR) for all
survey activities as specified in Section 4, Table 1 and Subsection 8/3 of this Guide.
ii)
96
In Section 4, Table 1, Testing Onboard typically covers the testing of the assembled or
integrated systems/subsystems/equipment/component. This is to include, but not limited
to, as applicable:
The IRC will describe the scope and results of the design review performed by ABS for the
submitted design plans and data, and the specified engineering criteria. The approved rating
and/or capacity will be indicated for each system, subsystem, equipment or component
covered by the certificate.
a)
b)
IRC is valid for five (5) years from date of issuance with no changes to the design
and manufacturing specifications (see 7/27).
c)
Revalidation of IRC is required after five (5) years from date of issuance.
iii)
Upon issuance of an ABS approval letter, an IRC, and satisfactory completion of the required
testing and survey, a Certificate of Conformity (CoC) will be issued when indicated by
Section 4, Table 1 of this Guide.
iv)
The CoC will affirm that, at the time of assessment and/or survey, the systems, subsystems,
equipment, and/or components met the applicable codes and standards, and the requirements
of this Guide with respect to design, manufacturing and testing.
a)
b)
CoCs are to be correlated to the IRC for the specific equipment model number.
v)
Appendix 3 and Appendix 4 of this Guide provide examples of IRC and CoC, respectively.
vi)
The contents of the IRC and CoC are to be specific to the equipment and its respective design
parameters.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
3.7
3.9
The individual equipment approval processes are outlined in Subsection 4/3 of this Guide.
ii)
(1 September 2012) The final installation and commissioning surveys, as outlined in Subsections
4/3i)c), 8/5, and 8/7 of this Guide, are the responsibility of the Owner/Operator.
In such cases, an electronic database reflecting the contents of Section 4, Table 1 of this Guide
will be made available to the key personnel associated with the project; the Owner/Operator, the
manufacturer, designers/engineers and ABSs Engineers and Surveyors.
ii)
Upon completion of each task outlined in Section 4, Table 1 of this Guide, the respective participant is
to update the corresponding field in the database. The completed database is to be documented as
part of the final ABS CDS Classification of the drilling system.
97
Section
98
TABLE 1
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Blowout Preventer
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
(1, 3, 10)
(10)
Testing
at
Vendor
SR
Testing Remarks
a and b2
a and b2
Blowout Preventer
Blowout Preventer
Equipment
Accumulators (Seamless)(9)
SR
b1
a and b2
Blowout Preventer
Equipment
Accumulators (Welded)
SR
b1
a and b2
Blowout Preventer
Equipment
SR
a and b1
a and b2
Blowout Preventer
Equipment
Autoshear System
SR
Blowout Preventer
Equipment
SR &
CoC
a and b1
a and b2
Blowout Preventer
Equipment
SR
a and b1
Blowout Preventer
Equipment
SR
Testing
Onboard
SR &
CoC
a and b2
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
Testing
Onboard
Testing Remarks
Blowout Preventer
Equipment
SR &
CoC
a and b1
a and b2
b1 is to be performed on
wellbore side and on operator,
individually.
b2 is to be performed after
assembly onto BOP
Blowout Preventer
Equipment
Clamps
SR &
CoC
b1
a and b2
See Note 2
Blowout Preventer
Equipment
SR &
CoC
a and b1
a and b2
See Note 2
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
Blowout Preventer
Equipment
Control System/Console/Panel
SR
a and b1
a and b2
Blowout Preventer
Equipment
SR
b1
a and b2
Blowout Preventer
Equipment
SR
a and b1
a and b2
Blowout Preventer
Equipment
Deadman System
SR
Blowout Preventer
Equipment
Drilling Spools
SR &
CoC
b1
b2
Blowout Preventer
Equipment
SR
a and b1
a and b2
Blowout Preventer
Equipment
SR
b1
a and b2
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
99
Section
100
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
Blowout Preventer
Equipment
SR
a and b1
a and b2
Blowout Preventer
Equipment
SR
b1 and e
Blowout Preventer
Equipment
Spacer Spools
SR &
CoC
b1
b2
Blowout Preventer
Equipment
Test Stump
SR
b1
b2
Blowout Preventer
Equipment
Test Tool
SR
a and b1
a and b2
LMRP
SR
LMRP
Annular Preventer
LMRP
Control System
LMRP
LMRP
Flex/Ball Joint
LMRP
Frame (LMRP)
Testing Remarks
a and b2
SR &
CoC
a and b1
a and b2
If annular is installed in
LMRP, see Blowout
Preventer Equipment above.
See Note 2
SR
a and b1
a and b2
SR &
CoC
a and b1
a and b2
SR
e See Lifting
Attachment in this Table for
test loads
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
Testing Remarks
LMRP
SR &
CoC
b1
a and b2
LMRP
SR &
CoC
a and b1
a and b2
LMRP
SR &
CoC
a and b1
a and b2
See Note 2
a and b2
SR
Diverter
Accumulators (Seamless)(9)
SR
b1
a and b2
Diverter
Accumulators (Welded)
SR
b1
a and b2
Diverter
Control System/Console/Panel
Diverter
Diverter
Flex/Ball Joint
Diverter
Diverter
SR
a and b1
a and b2
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
SR &
CoC
a and b1
a and b2
See Note 2
SR &
CoC
a and b1
a and b2
See Note 2
SR
a and b1
a and b2
SR &
CoC
b1
a and b2
See Note 2
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
101
Section
102
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
Testing Remarks
Diverter
Piping System
SR
b1
b2
Diverter
Test Tool
SR
a and b1
a and b2
Diverter
Valves
SR &
CoC
a and b1
a and b2
See Note 2
a and b2
SR
See Note 2
SR
a and b1
a and b2
If hydraulic or pneumatic
controls, then b1 and b2 are
required, as applicable
a is the functional testing
and failure modes validation,
as required
SR &
CoC
a and b1
a and b2
See Note 2
SR &
CoC
a and b1
a and b2
See Note 2
SR &
CoC
a and b1
a and b2
See Note 2
SR &
CoC
a and b1
a and b2
See Note 2
SR &
CoC
b1
b2
See Note 2
SR &
CoC
a and b1
a and b2
Control System/Console/Panel
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
Testing Remarks
Kill Unit
SR
a and b1
a and b2
SR
a and b1
a and b2
Auxiliary Equipment
SR &
CoC
b1
a and b2
See Note 2
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
103
Section
104
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
Hang-Off Joint
Hydraulic Connectors
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
SR
Tensioner Ring
MAC
SR
IRC (4)
Testing
Onboard
SR &
CoC
a and b1
a and b2
SR
a and e
SR &
CoC
a and b1
SR
a and e
SR &
CoC
b1
SR
a and e
SR &
CoC
Testing Remarks
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
Onboard
a, b1,
and e
a and b2
(1, 3, 10)
(10)
Testing
at
Vendor
SR &
CoC
Telescopic Joint
Riser Running
Equipment
SR
Riser Running
Equipment
Gimbal (fixed)
Riser Running
Equipment
Riser Running
Equipment
Riser Running
Equipment
Riser Running
Equipment
Pumps, Gears, Motors, Electrical, Controls, etc., see Common Systems and Equipment, as applicable
Testing Remarks
a and e
SR
a and e
SR
b1 and e
SR
a, b1
and e
a and b2
SR
a, b1
and e
a and b2
SR
105
SR
Accumulators (Seamless)(9)
SR
b1
a and b2
Accumulators (Welded)
SR
b1
a and b2
SR
b1
b2
SR
a and b1
a and c
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Section
106
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
Compressors(11)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
Testing
Onboard
Control System/Console/Panel
SR
Dryers
SR
b1
SR
a and b1
a and b2
SR
a and b1
a and b2
Piping System
SR
a and b1
a and b2
Pressure Vessels
SR
b1
b2
SR
a and b1
a and b2
SR
SR
a and b1
a and b2
SR
Telescopic Arms
SR
a and b1
a and b2
(11)
Testing Remarks
(5)
Wire Ropes
Pumps, Gears, Motors, Electrical, Controls, Hydraulic Cylinders, etc., see Common Systems and Equipment, as applicable
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
a is the functional testing
and failure modes validation,
as required
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
(10)
Testing
at
Vendor
(1, 3, 10)
Conductor Tensioning
System/Unit
Conductor Tensioning
System/Unit
Accumulators (Seamless)(9)
SR
Conductor Tensioning
System/Unit
Accumulators (Welded)
SR
Testing
Onboard
Testing Remarks
a and b2
b1
a and b2
Hydraulic or Pneumatic
b1
a and b2
SR
Conductor Tensioning
System/Unit
Control System/Console/Panel
SR
Conductor Tensioning
System/Unit
SR
a and b1
a and b2
Conductor Tensioning
System/Unit
Piping System
SR
a and b1
a and b2
Conductor Tensioning
System/Unit
Sheaves(8)
SR
Conductor Tensioning
System/Unit
Wire Ropes(11)
Conductor Tensioning
System/Unit
Pumps, Gears, Motors, Electrical, Controls, Hydraulic Cylinders, etc., see Common Systems and Equipment, as applicable
X(5)
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
107
Section
108
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
Testing
Onboard
a and b2
b1
a and b2
Hydraulic or Pneumatic
SR
b1
a and b2
SR
a and b1
a and b2
SR
a and b1
SR
b1
a and b2
Accumulators (Seamless)(9)
SR
Accumulators (Welded)
Compressors(11)
Dryers
Compensator Assembly
SR
Control System/Console/Panel
SR
a and b1
a and b2
SR
a and b1
a and b2
Pressure Vessels
SR
b1
b2
SR
(8)
Sheaves
(11)
Testing Remarks
(5)
Wire Ropes
Pumps, Gears, Motors, Electrical, Controls, Hydraulic Cylinders, etc., see Common Systems and Equipment, as applicable
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
Bulk Storage
Bulk Storage
SR
b1 or c
Bulk Storage
SR
b1
a and b2
Bulk Storage
Pumps, Gears, Motors, Electrical, Controls, etc., see Common Systems and Equipment, as applicable
Mud Return
Mud Return
SR
Testing
Onboard
(11)
Mud Return
Chemical Mixers
Mud Return
Degasser
X
(11)
SR
a and b2
SR
SR
Mud Return
Mud Return
Mud Return
Piping System
(11)
a and b2
SR
a and b1
a and b2
SR
SR
SR
a and b1
a and b2
Mud Return
Shale Shakers
SR
Mud Return
Trip Tank
SR
Mud Return
Pumps, Gears, Motors, Electrical, Controls, etc., see Common Systems and Equipment, as applicable
Testing Remarks
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
109
Section
110
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Circulation Head
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
SR
SR &
CoC
Testing
Onboard
a and b2
a and b1
Control System/Console/Panel
SR
a and b1
a and b2
Charge Pumps
SR
a and b1
a and b2
Gooseneck, Swivel
SR &
CoC
a and b1
a and b2
Kelly
SR &
CoC
a and b1
a and b2
Kelly Bushing(11)
Mixing Pumps
SR
X
SR &
CoC
a and b2
Testing Remarks
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
a
a and b1
a and b2
SR &
CoC
b1
a and b2
SR &
CoC
b1
a and b2
SR
b1
a and b2
SR
a and b1
a and b2
See Note 2
Equipment
Section
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
SR
a and b1
a and b2
SR
a and b1
a and b2
Pulsation Dampeners
SR
b1
SR &
CoC
b1
a and b2
SR
a and b1
Standpipe Manifold
SR
b1
b2
Pumps, Gears, Motors, Electrical, Controls, etc., see Common Systems and Equipment, as applicable
Cementing
Cementing
Cementing
Cementing
Cementing
Cementing
Control System/Console/Panel
SR
X
SR
a and b2
b1
SR
b1
a and b2
SR
b1
a and b2
Testing Remarks
SR
a and b1
a and b2
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
111
Section
112
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
Cementing
SR
a and b1
a and b2
Cementing
SR
b1
a and b2
Cementing
SR
b1
a and b2
Cementing
Pulsation Dampeners
SR
b1
Cementing
Safety Valves
SR
a and b1
Testing Remarks
Equipment
Section
Derrick
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
(1, 3, 10)
(10)
Testing
at
Vendor
SR &
CoC
Hoisting
SR
Hoisting
Deadline Anchors
SR
Hoisting
SR
Drawworks
Hoisting
SR
SR
a and b2
a and e
X
(11)
Testing Remarks
See 8/5vi)
Hoisting
Hoisting
Testing
Onboard
a and e
(5)
113
Hoisting
Hoisting
Elevators (6, 8)
SR
Hoisting
SR
Hoisting
SR
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Section
114
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
(1, 3, 10)
(10)
Testing Remarks
Hoisting
Kelly Spinner
SR
Hoisting
SR
Hoisting
SR &
CoC
e and b1
a and b2
SR &
CoC
e and b1
a and b2
SR
Traveling Block
SR
Hoisting
SR
Hoisting
X(5)
Hoisting
Wireline Spooler/Unit(11)
Hoisting
Rotary Swivel
Hoisting
Hoisting
Lifting
Lifting
SR
SR
SR
a and b2
a, b1
and e
a, b2
and e
Equipment
Section
Lifting
Lifting
Design
Review &
Approval
Letter (7)
X
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
Testing
Onboard
SR
a, b1
and e
a, b2
and e
SR
a, b1
and e
a, b2
and e
(1, 3, 10)
(10)
Testing Remarks
Lifting
Personnel Baskets
SR
a, and e
a and e
Lifting
SR
a, b1
and e
a, b2
and e
Lifting
SR
a, b1
and e
a, b2
and e
Lifting Attachments
BOP Handling
Bulkhead Guiding
BOP Handling
Handling Crane
BOP Handling
e Test loads:
- SWL < 10 MT = 1.5 SWL
- 10 < SWL < 20 MT = SWL +
5 MT
- SWL > 20 MT = 1.25 SWL
SR
SR
SR
a, b1
and e
a, b2
and e
Seafixing
SR
BOP Handling
Transporter/Skidder
SR
a and b1
a and b2
BOP Handling
SR
a and b1
a and b2
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
115
Section
116
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
(1, 3, 10)
(10)
a and b1
a and b2
b2 Before installation of
mast/derrick
SR
SR
a and b1
a and b2
Tubular Handling
Bridge Crane
SR
Tubular Handling
Finger Board
Tubular Handling
Hydraulic Cathead
Tubular Handling
Tubular Handling
Manipulator Arms
Tubular Handling
Monkey Board
SR
SR
a and b2
SR
SR
a and b1
a and b2
SR
(11)
Tubular Handling
Mousehole Fixed
Tubular Handling
Mousehole Powered
Tubular Handling
Mudbucket(11)
Tubular Handling
Tubular Chute
Tubular Handling
Tubular Handling
Tubular Handling
Tubular Handling
Testing Remarks
a and b2
(11)
Testing
Onboard
Tubular Handling
Tubular Handling
Testing
at
Vendor
SR
Applicable to mechanical
systems only
SR
a and b1
a and b2
SR
a and b1
a and b2
b1 and b2 If hydraulic
mousehole installed.
X
X
X
X
SR
X
SR
SR
a and b2
a and e
a and e
b2 - If hydraulic tubular
horizontal transporter is installed
Equipment
Section
Tubular Handling
Tubular Handling
Tubular Handling
Tubular Handling
Tubular Handling
Tong Suspension
Design
Review &
Approval
Letter (7)
X
(11)
(11)
Rotary
Survey
at
Vendor
CoC/
SR
SR
Testing
Onboard
a and e
(1, 3, 10)
(10)
Testing
at
Vendor
SR
SR
Testing Remarks
X(5)
Wire Ropes
MAC
(11)
Rotary
IRC (4)
SR
X
SR
a
a
Hoisting, Lifting,
Rotary, Handling (BOP
and Tubulars)
Control System/Console/Panel
SR
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
Hoisting, Lifting,
Rotary, Handling (BOP
and Tubulars)
SR
a and b1
a and b2
Hoisting, Lifting,
Rotary, Handling (BOP
and Tubulars)
Piping Systems
SR
a and b1
a and b2
Hoisting, Lifting,
Rotary, Handling (BOP
and Tubulars)
Pumps, Gears, Motors, Electrical, Controls, Hydraulic Cylinders, etc., see Common Systems and Equipment, as applicable
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
117
Section
118
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Well Test
Components
Well Test
Well Test
Burner Boom
Well Test
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
(1, 3, 10)
(10)
Testing
at
Vendor
Testing
Onboard
SR
SR
SR
Well Test
Control System/Console/Panel
SR
Well Test
SR
a and b1
a and b2
Well Test
Heat Exchangers
SR
b1
b2
Well Test
Piping System
SR
b1
a and b2
Well Test
SR
b1
b2
Well Test
Well Test
Safety Valves(11)
SR
Well Test
Valves(11)
SR
a and b2
Testing Remarks
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
Equipment
Section
Control Systems
Components
Drillers Console
Control Systems
Electrical Systems
Hydraulic Cylinders
Hydraulic Cylinders
Internal Combustion
Engines
Piping
Expansion Joints
Piping
Interconnecting Piping
Pressure Vessels
Design
Review &
Approval
Letter (7)
X
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
SR
Testing
Onboard
a and b2
If hydraulic or pneumatic
controls, then b1 and b2
are required, as applicable
a is the functional testing
and failure modes validation,
as required
(1, 3, 10)
(10)
Testing
at
Vendor
SR
a and b1
Testing Remarks
Design review and testing in accordance with 6-1-7/Table 1 of the ABS MODU Rules
X
X
X
SR
SR
X
SR
a
a
a and b1
a and b2
X
Design review and testing in accordance with 6-1-3/Table 1 of the ABS MODU Rules
X
SR
b1
b2
Design review and testing to be in accordance with 6-1-6/Table 1 (except for Material tests to be witness by
Surveyor) of the ABS MODU Rules
X
b2
Equipment
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
119
Section
120
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
Components
Pressure Vessels
Pumps
Pumps
Pumps
Support Systems,
Non-Hydrocarbon Handling,
Hydraulic Pumps(11)
Rotating Electrical
Machinery
Rotating Electrical
Machinery
Design
Review &
Approval
Letter (7)
IRC (4)
MAC
Survey
at
Vendor
CoC/
SR
Testing
at
Vendor
(1, 3, 10)
(10)
Testing
Onboard
Testing Remarks
Design review and testing to be in accordance with 6-1-5/Table 1 (except for Material tests to be witness by
Surveyor) of the ABS MODU Rules
X
SR
X
X
X
X
SR
a and b1
SR
X
a and b2
SR
See 3/21.3i)
SR
See 3/21.3ii)
Equipment
(1 September 2012) If specified Testing at Vendor cannot be completed at vendors facility, the specified test(s) can be performed at the shipyard or during commissioning
(see 4/3.3 and Subsections 8/5 and 8/7 of this Guide).
All well control components are to be tested on-board; first to a low pressure of 1.38 MPa to 2.1 MPa (200 psi to 300 psi) and then to the rated working pressure, as
applicable (see API RP 53).
(1 September 2012) MAC is to be provided with manufacturers certification in accordance with API Spec 9A/ISO-10425, or equivalent.
(1 September 2012) Only Elevators, Links, Spiders (when capable of being used as elevators), and Safety Clamps (when capable of being used as hoisting equipment)
require proof load testing for each production unit as per Section 8.6 of the API Spec 8C.
(1 September 2012) ABS Type Approval (TA) Program is accepted with the following conditions:
a. Manufacturing Assessment program under Recognized Quality System (RQS)
b. Surveyors attendance only for final hydrostatic test (b1) for unit-certification
10
(1 September 2012) Vendor (OEM or shipyard) is the entity responsible for manufacturing, assembling and/or installation of drilling systems, subsystems, equipment or components
11
(1 September 2012) ABS Type Approval can be granted upon request. See Appendix 1-1-A2 of ABS Rules for Conditions of Classification Offshore Units and Structures
(Part 1) for details.
Testing Notes:
Types of Testing
Conditions of Testing
Functional Test
b1
Hydrostatic Test
1.5 times the design pressure, or in accordance with applicable design codes/standards.
b2
Pneumatic Test
Leak Test
121
Load Test
Factory Testing
Factory Testing
Testing in accordance with 6-1-7/Table 2 (Items 2 through 10, and Item 12) of the ABS MODU Rules. Surveyors attendance to
witness testing is not required
Notes:
Section
TABLE 1 (continued)
Approval Codes for Drilling Systems and Equipment (1 September 2012)
SECTION
General
This section contains general requirements for piping systems and/or associated components that form part
of the drilling systems, as follows:
Well test
Vent system
Diverter
Well circulation
i)
Piping systems that are used for both marine and drilling services such as hydraulic piping, air
piping, seawater service, potable water, power generation, etc., are to be in accordance with Part 4,
Chapter 2 of the ABS MODU Rules.
ii)
The manufacturer is to submit to ABS for approval P&IDs, piping specifications, design plans and
data, and calculations for each piping system associated with the drilling systems listed above.
iii)
Piping component pressure-temperature ratings are to be in compliance with ASME B31.3, API
Spec 16C, API Spec 16D, API RP 14E and/or other recognized codes/standards, as applicable.
iv)
The above requirements are to be used for all drilling system piping and in conjunction with the
specific requirements contained in Section 3 of this Guide for individual subsystems used for
drilling systems.
Design Criteria
3.1
122
Design
i)
Piping and piping components are to be designed to withstand the maximum stress that
could arise from the most severe combination of pressure, temperature, and other loads or
service conditions as referenced in 5/3.1.2 below, and to be in accordance with codes and
standards referenced in Subsection 5/1 above.
ii)
For high-pressure ratings that are not within the scope of the referenced codes in
Subsection 5/1 above, pipe wall thickness calculations demonstrating suitability for the
intended service are to be submitted for ABS review.
iii)
Pipe stress and flexibility analysis are to be performed in accordance with ASME B31.3
or other recognized design code for all applicable service conditions for the following piping
systems:
Section
3.1.2
iv)
Expansion joints are not to be used in high-pressure well control piping systems.
v)
When used, expansion joints or bellows in piping systems are to be provided with shields
to prevent mechanical damage and are to be properly aligned and secured.
ii)
iii)
3.1.3
3.1.4
For surface BOP stack, all rigid lines between the control system and BOP stack are to comply
with the following:
a)
b)
To have RWP equal to the RWP of the BOP control system, as applicable
All rigid lines between the control system and BOP are not required to meet the
fire test requirements of API Spec 16D, on those rigs with an autoshear and
deadman system installed.
b)
All rigid lines between the control system and BOP are to have RWP equal to the
RWP of the BOP control system, as applicable.
Allowances
The design wall thickness of all piping is to account for, as applicable:
i)
Mill under-tolerances (12.5% of nominal piping thickness, unless otherwise stated in the
material specification)
ii)
iii)
iv)
Fabrication allowance
Alternative Criteria
i)
ABS is prepared to consider other applicable design references, alternative design
methodology and industry practice for piping system and piping component designs, on a
case-by-case basis, with justifications through novel features as indicated in 1/7.7 of this
Guide.
ii)
iii)
The extent of NDE, service temperatures, material ductility and special fabrication methods
are also to be considered for alternative design criteria.
3.3
3.5
General
i)
Piping joints and connections greater than 50 DN (2 in. NPS) are to be made by butt-weld,
flanged or screwed union where the threads are not part of the sealing.
ii)
(1 September 2012) Box and pin joints for the choke and kill lines on drilling risers are
acceptable.
123
Section
iii)
iv)
3.5.2
b)
Specially considered for other services, such as drilling support, and support systems,
on a case-by-case basis
Piping joints and connections not in accordance with design codes and standards will be
specially considered by ABS on a case-by-case basis.
ii)
iii)
Threaded joints and connections can be utilized as permitted in the table below:
Type
Threaded connections
3.5.3
Not permitted
All
Not permitted
50 DN (2 in. NPS)
As permitted by
design code
Threaded connections
for instrumentations,
drains, vents
12 mm (0.5 in)
All
As permitted by
design code
Threaded connections
where threads are not
used for sealing
50 DN (2 in. NPS)
All
As permitted by
design code
Threaded connections
with seal weld
All
As permitted by and
to be in compliance
with design code
124
Pressure
> 20.7 MPa (3000 psi)
Socket Welds
i)
All socket-welding connections are to be identified and specially approved by ABS.
ii)
3.5.4
Size
All
Size
Pressure
50 DN (2 in. NPS)
As permitted by and
to be in compliance
with design code
All
Not permitted
Section
3.7
Well control
Choke and kill system flexible lines (surface/subsea)
API Spec 7K
Cementing hoses
API Spec 7K
Flexible lines and hydraulic hoses are to comply with the following general requirements:
i)
The hose body is to be secured to prevent falling or whipping in the event of a rupture or failure.
ii)
Hose assemblies which can pose risk to personnel upon end failure are to be properly restrained.
3.7.1
Design
3.7.1(a) Well Control
i)
Choke and kill flexible lines and auxiliary lines are to comply with the design, material,
quality control, and prototype testing, including burst testing requirements specified in API
Spec 16C, API Spec 16F, and the additional requirements specified in this Guide.
ii)
Drape hoses (moonpool lines) at the telescopic joint are to be able to accommodate the
relative movement between the riser and the drilling unit.
iii)
For subsea BOP stack, jumper lines at the flex/ball joints are be able to accommodate the
relative movement between the riser and the BOP stack.
iv)
Flexible lines for subsea services are to be designed to withstand the external pressure for
the operational depth without deforming.
125
Section
v)
Hydraulic hoses/assembly utilized for well control functions are to comply with the
requirements of applicable sections of the ABS MODU Rules (for surface hydraulic control
hoses only), API Spec 16D and recognized industry standards, such as SAE, National Fluid
Power Association, as applicable.
vi)
Flexible lines that are exposed to wellbore fluids are to consider gas permeation and
decompression in their designs.
3.7.2
i)
Hydraulic hoses/assembly utilized for drilling system control and hydraulic fluid transfer
are to comply with the requirements of applicable sections of the ABS MODU Rules,
recognized industry standards, such as SAE, National Fluid Power Association, as applicable.
ii)
Flexible lines or hydraulic hoses that are to be used in pneumatic service are to be designed
with consideration to decompression and permeation.
iii)
Rotary and vibratory hoses/assembly for drilling services are to comply with the design,
and manufactured to API Spec 7K, and the additional requirements specified in this
Guide, and be suitable for their intended service (temperature, fluid compatibility, etc.).
Fire Resistance
3.7.2(a) General
i)
ii)
All flexible lines/hydraulic hoses located in hazardous areas, irrespective of fluid category,
are to be fire-resistant, except as permitted in 5/3.7.2(c) below.
iii)
Fire resistance tests of flexible lines/hydraulic hoses are to be in accordance with API
Spec 16C and API Spec 16D and ISO 15540/15541, as applicable.
iv)
Hydraulic hoses are also to be in compliance with the applicable requirements of 4-2-1/11.29
of the ABS MODU Rules and Appendix 2 of the ABS Facilities Rules, as applicable.
3.7.2(b) Surface. For surface BOP stack, all flexible lines hydraulic hoses between the control
system and BOP stack are to comply with the following:
i)
ii)
To have RWP equal to the RWP of the BOP control system, as applicable.
3.7.3
i)
All flexible lines (except choke and kill lines) and MUX cables in the moonpool between
the control system and BOP are not required to meet the fire resistant requirements of API
Spec 16D and API Spec 16C, as applicable, on those installation with a autoshear and
deadman system installed.
ii)
All flexible lines/hydraulic hoses between the control system and BOP are to have RWP
equal to the RWP of the BOP control system, as applicable.
iii)
Moonpool choke and kill hoses or flexible lines and their end connections installed that
permit entry of gas or hydrocarbons, is to meet the design requirements, performance
verification and fire-resistance requirements in accordance with API Spec 16C.
iv)
End Connections
i)
End connections for flexible lines/hydraulic hoses are to be designed and fabricated to the
requirements of 5/3.1 this Guide and applicable recognized codes and standards.
ii)
126
End connections are to be considered as an integral part of the flexible line/hydraulic hose
assembly.
Section
3.7.4
Isolation Valves
Isolation valves are to be provided to prevent potential uncontrolled release of flowing medium
from flexible lines to minimize the hazard.
3.7.5
Materials
i)
Material requirements for flexible lines and hydraulic hoses, including end fittings when
exposed to wellbore fluids or a corrosive/erosive environment, are to be in accordance
with Section 5 and Section 6 of this Guide and applicable design codes and standards.
ii)
Nonmetallic materials used in the manufacturing of flexible line and/or hydraulic hose
assemblies are to be suitable for the intended service conditions such as temperature and
fluid compatibility.
Materials
(1 September 2012) Materials are to be in accordance with the applicable design codes and standards
referenced in this section, and the requirements of Section 6 of this Guide.
5.1
Toughness
Piping component toughness requirements are to be in accordance with Section 6 of this Guide.
5.3
127
SECTION
1.1
Material Categories
Materials for drilling systems equipment/components are categorized as follows:
i)
ii)
iii)
b)
Structural load-bearing components are to comply with the requirements of Subsection 6/3
of this Guide.
b)
Mechanical load-bearing components are to comply with the requirements of Subsection 6/5
of this Guide.
b)
1.3
Material Properties
To determine the suitability of a material to withstand design stresses, the ultimate tensile strength (UTS),
specified minimum yield strength (SMYS), elongation and reduction of area are to be specified in accordance
with recognized material standards.
1.5
1.7
128
i)
Materials that are exposed to well bore fluids are to be selected within appropriate limits of chemical
composition, heat treatment and hardness to resist sulfide stress cracking.
ii)
Selection of material is to be guided by the applicable part of NACE MR0175/ISO 15156: Materials
for use in H2S containing environment in oil and gas production.
Section
ii)
For hoisting structures, the primary load-bearing structural members for the derrick and
mast are defined in 3/11.1.1iii) of this Guide.
b)
3.1
Material applications and associated toughness requirements are to comply with the applicable
codes and standards, such as API Spec 2C, ABS Lifting Appliances Guide, or equivalent.
iii)
For guidance on the selection of steel for plates, shapes and structural pipe sections, reference is to
be made to recognized standards such as API RP 2A-WSD or Section 3-1-4 of the ABS MODU
Rules.
iv)
Any structural load-bearing components that are in the critical load path are to be considered as
primary.
Toughness
i)
Structural materials are to exhibit fracture toughness which is satisfactory for the intended applications
(hoisting, handling, lifting), as evidenced by appropriate Charpy V-notch (CVN) impact testing
results, and are to be based on the specified minimum design service temperature (MDST) and
materials specified minimum yield strength (SMYS), as specified in the table below.
ii)
Other CVN criteria or alternative test data, such as crack-tip opening displacement (CTOD), nil
ductility transition (NDT) temperature, or related service experience will be considered if submitted
to ABS prior to manufacturing.
129
Section
Category
MDST
Primary
SMYS/Material
270 MPa (39 ksi)
or
[SMYS ((ksi)/1.45) * 0.7375] (ft-lb) at MDST
Primary
lower than
10C to 20C
(14F to 4F)
lower than
20C (4F)
(4)
(4)
(4)
Non-primary
0C to 10C
(32F to 14F)
All
Non-primary
lower than
10C (14F)
or
[SMYS ((ksi)/1.45) * 0.7375] (ft-lb) at MDST
(2)
3.3
130
(4)
lower than
20C (4F)
Any
All
Individual value for each of the (3) test specimens cannot be less than 2/3 of the specified minimum average.
For miscellaneous structures, under the scope of this Guide, refer to items such as ladders, supports, walkways,
handrails, cable trays, and other ancillary structures. In general, materials for these structures are low in thickness
and are to be suitable for their intended application, as evidenced by previous satisfactory services.
Primary load-bearing structural bolts and nuts are to be produced to a material specification that requires Charpy
impact tests at, or below, the specified minimum design service temperature.
For materials with a specified minimum yield strength (SMYS) of greater than 690 MPa (100 ksi), Charpy V-Notch
properties are to be submitted for ABS review and consideration.
For materials with SMYS of greater than 690 MPa (100 ksi), Charpy V-Notch properties are to be submitted for
ABS review and consideration.
Galvanizing
Materials for galvanized structures are to be fabricated and designed in accordance with industry-recommended
practices. Galvanizing procedures and/or process are to be in accordance with ASTM A143, A153, A384,
A385, BCSA 40/05, and/or other hot-dip galvanizing standards. The following are to be considered in the
development of galvanizing procedures and process:
Section
Double-dipping practices are not permitted, except in case of galvanizing tank size limitations
Maximum CE of 0.44% (see CEZ calculation below) based upon the Product Analysis or if Ladle
Analysis then maximum specified chemistry values should be applied in the calculation. Steel which is
produced from scrap may contain trace elements that influence the susceptibility to hot dip galvanizing
cracking.
CEZ = C + Si/17 + Mn/7.5 + Cu/13 + Ni/17 + Cr/4.5 + Mo/3 + V/1.5 + Nb/2 + Ti/4.5 + 420B
5.1
Toughness
Toughness testing for mechanical load-bearing components is to be performed in accordance with relevant
API or applicable recognized standards.
i)
Toughness testing procedures, size, locations and retesting (as applicable) are to be in accordance
with the applicable recognized standard.
ii)
Charpy V-Notch (CVN) impact testing is to be performed at the required temperature in the relevant
API or applicable standard or the minimum design temperature (MDT), whichever is lower.
iii)
For a specified MDT above 0C (32F), Charpy V-Notch impact testing is to be performed at 0C
(32F).
iv)
The absorbed energy requirement is to be in accordance with the relevant API or applicable recognized
standard.
v)
Material for mechanical load-bearing components not covered by, or not in full compliance with API
standards or applicable recognized standards, the following Charpy V-Notch criteria applies:
a)
b)
For materials with specified minimum yield strength (SMYS) of 450 MPa (65 ksi) or below:
1)
SMYS (N/mm2)/10 = Minimum Absorbed Energy (ave) (J), but not less than 27 J
or
2)
SMYS [(ksi)/1.45] * 0.7375 = Minimum Absorbed Energy (ave) (ft-lb) but not
less than 20 ft-lb
For materials with a SMYS greater than 450 MPa (65 ksi) and less than or equal to 690 MPa
(100 ksi)
1)
c)
For materials with a specified minimum yield strength (SMYS) of greater than 690 MPa
(100 ksi), Charpy V-Notch properties are to be submitted for ABS review and consideration.
vi)
Other CVN criteria or alternative test data, such as crack-tip opening displacement (CTOD), nil
ductility transition (NDT) temperature, or related service experience will be considered if submitted
to ABS prior to manufacturing.
vii)
It should be noted that other national and international regulatory bodies may have additional
requirements for toughness. ABS will include these additional toughness requirements in the scope
of the design review and fabrication inspection, as applicable, and/or as requested.
131
Section
7.1
Toughness
Toughness testing for pressure-retaining equipment or piping components is to be performed in accordance
with the relevant API, ASME or applicable recognized standard.
i)
Toughness testing procedures, size, locations and retesting (as applicable) are to be in accordance
with the applicable recognized standard.
ii)
Charpy V-Notch (CVN) impact testing is to be performed at the required temperature in the
relevant API, ASME or applicable standard or the minimum design temperature (MDT), whichever
is lower.
iii)
For a specified MDT above 0C (32F), Charpy V-Notch impact testing is to be performed at 0C
(32F).
iv)
The absorbed energy requirement is to be in accordance with the relevant API, ASME or applicable
recognized standard.
v)
Materials for pressure-retaining equipment or piping components not covered by, or not in full
compliance with API, ASME or applicable recognized standards, the following Charpy V-Notch
criteria apply:
a)
b)
c)
For materials with specified minimum yield strength (SMYS) of 450 MPa (65 ksi) or below:
1)
SMYS (N/mm2)/10 = Minimum Absorbed Energy (ave) (J), but not less than 27 J
or
2)
SMYS [(ksi)/1.45] * 0.7375 = Minimum Absorbed Energy (ave) (ft-lb), but not
less than 20 ft-lb
For materials with a SMYS above 450 MPa (65 ksi) to 690 MPa (100 ksi):
1)
2)
In addition, lateral expansion opposite the notch is not to be less than 0.38 mm
(0.015 in.).
For materials with a SMYS above 690 MPa (100 ksi), Charpy V-Notch properties are to
be submitted for consideration.
1)
132
In addition, lateral expansion opposite the notch is not to be less than 0.38 mm
(0.015 in.).
vi)
Other CVN criteria or alternative test data, such as crack-tip opening displacement (CTOD), nil
ductility transition (NDT) temperature, or related service experience will be considered if submitted
to ABS prior to manufacturing.
vii)
It should be noted that other national and international regulatory bodies may have additional
requirements for toughness. ABS will include these additional toughness requirements in the scope
of the design review and fabrication inspection, as applicable, and/or as requested.
Section
Fabrication Considerations
9.1
Welding
Welding of drilling equipment and/or components is to comply with the following requirements:
9.3
i)
Welding is to be in accordance with the specified design/manufacturing code and Section 7 of this
Guide.
ii)
(1 September 2012) Weldments hardness, weld metal and/or heat-affected zone (HAZ), subject to
sour (H2S) service are to be in compliance with NACE MR0175/ISO 15156.
Forming
Forming of materials utilized in drilling equipment and/or components are to comply with the following
requirements:
i)
In general, for steel components, forming at temperatures around 205C (400F) is to be avoided.
ii)
Where degradation of properties is unavoidable, complete post forming heat treatment may be
required.
iii)
Suitable supporting data is to be provided to indicate compliance with the specified properties.
iv)
For materials with specified toughness properties that are to be formed beyond 3% strain* on the outer
fiber, data are to be provided indicating that the toughness properties meet the minimum requirements
after forming.
v)
After straining, specimens used in toughness tests are to be subjected to an artificial aging treatment
of 288C (550F) for one hour.
* Note:
For details, see 2-4-1/3.13 of the ABS Rules for Materials and Welding (Part 2).
11
11.1
11.3
i)
Sub-suppliers/vendors have an accredited and effective quality control system to meet the materials
specifications and manufacturing requirements in accordance with requirements as referenced in
the design codes and standards.
ii)
Material tests are carried out by accredited test facilities to recognized standards.
iii)
Material testing is performed in accordance with the requirements of the applicable material
specifications and in accordance with the design codes and standards.
iv)
v)
NDE is carried out by qualified personnel in accordance with requirements as referenced in the
design codes and standards, such as ISO 9712, ASNT, EN 473, etc.
Rolled Products
Plates, shapes and bars may be supplied in the as-rolled, thermo-mechanically processed, normalized, or
quenched and tempered condition, depending on the intended application.
133
Section
11.5
11.7
To be supplied in a fully worked condition to provide a wrought microstructure and internal soundness.
A forging reduction ratio of not less than 3:1 will be considered as meeting this requirement.
ii)
Where a net change in the cross section does not occur during a portion of the forging operation, the
hot-working ratio representing that portion will be evaluated as a complement to the forging reduction
ratio.
a)
Samples for testing are to be taken from integrally forged coupons, appropriately designed
separately forged coupons or a sacrificial forged.
b)
These coupons are to be subjected to the same heat treatment as the forging.
13
Sealing Materials
13.1
Elastomeric Sealants
i)
(1 September 2012) Materials used for sealing are to be suitable for the intended operating pressures,
temperatures, and operating mediums.
ii)
13.3
Age-sensitive materials for critical components are to have a defined storage life and be identified in
storage as to month and year of manufacture.
Gaskets that are coated with a protective coating material such as fluorocarbon or rubber for shipment
and storage are to have the coatings removed prior to installation.
15
15.1
Materials
i)
All materials used for structural load-bearing, mechanical load-bearing components, pressureretaining equipment/component, and piping are to be furnished with material manufacturer/ mills
documentation (e.g., material test reports (MTR), etc.) stating, as a minimum, the following, as
applicable:
134
Material specification
Process of manufacture
Hardness test readings (as applicable to NACE MR0175/ISO 15156), including testing standard
Section
ii)
15.3
Test coupons are required for each heat treatment for verification of mechanical properties to the
manufacturers written specification and/or industry standards.
Traceability
Traceability through the manufacturing process is to be documented on major structural load-bearing,
mechanical load-bearing components and pressure-retaining equipment. The manufacturers are responsible
for maintaining this documentation on file and, upon request, are to provide this information to ABS.
The traceability documentation is to include:
i)
ii)
Manufacturing Processes:
NDE results
135
SECTION
1.1
Welding
i)
1.3
ii)
The Surveyor can accept, at his discretion, welding procedures and welder qualifications at shipyard
or manufacturing plant where it is established to his satisfaction that they have been qualified and
effectively used for similar work under similar conditions.
iii)
The Surveyor is to be satisfied that all welders and welding operators to be employed in the
manufacturing of systems, subsystems, equipment or components are properly qualified and
experienced in the work proposed.
iv)
The Surveyor is also to be satisfied as to the employment of a sufficient number of skilled supervisors
to provide a thorough supervision and control of all welding operations.
All welds in the pressure boundary of pressure-retaining equipment, piping systems, mechanical
load-bearing and structural components are to be manufactured using qualified or ABS-approved
welding procedures and welders in accordance with the applicable equipment or component design
codes and standards. This is to include the following provisions as associated with welding procedure
and welder qualifications, as applicable:
Inspection of welds, utilizing methods outlined in this section, is to be carried out to the satisfaction
of the Surveyor.
Specifications
Welding Procedure Specification (WPS), corresponding Procedure Qualification Record (PQR), and
Nondestructive Examination (NDE) procedures are to be submitted for review as part of the design submittal
as required in Subsection 2/7 and Section 4, Table 1 of this Guide.
136
i)
WPS, PQR and NDE procedures are to be developed in accordance with the requirements of the
selected design codes for the drilling systems, subsystems, equipment and/or components for the
intended service.
ii)
The requirements and extent of NDE are to be in accordance with the requirements of the selected
design codes for the drilling systems, subsystems, equipment and/or components.
Section
3.1
The WPS is to describe in detail all essential and nonessential variables to the welding process(es)
employed in the procedure.
ii)
Welding procedure specifications are to be qualified and the PQR documenting the following data
is to be made available to the attending Surveyors:
Minimum and average toughness values for weld heat-affected zone and weld metal (absorbed
energy or lateral expansion, both by Charpy method, where the base metal is required to be
impact-tested in accordance with Sections 3 or 6 of this Guide)
iii)
Where welding equipment and consumables have not been used previously at the manufacturers
facility or are outside of the essential variable limits defined in the existing WPS or if specifically
requested by the attending Surveyor, the WPS is to be qualified by welding procedure qualification
process in the presence of the Surveyor.
iv)
The qualification process may require the submittal of relative WPS and supporting PQRs to the
ABS Technical office for review and agreement.
3.3
NDE Procedures
NDE procedures are to be specified and the parameters of test specification (method), extent of examination
and acceptance criteria are to be submitted for review and be available to the attending Surveyor.
i)
American Society for Nondestructive Testing (ASNT) Recommended Practice No. SNT-TC-1A or
equivalent is to be used as a guideline for employers to establish their written practice for qualification
and certification of their personnel.
ii)
137
Section
11
Nondestructive Examination
(1 September 2012) All weldments and other critical sections covered under Subsection 7/1 of this Guide are
to be subjected to 100% visual examination, and nondestructive examination for surface and volumetric
defects in accordance with the relevant design code, the ABS NDE Guide, and this Guide.
Examinations are to be carried out after any postweld heat treatment.
11.1
11.3
(1 September 2012) All highly-stressed areas, such as gross structural discontinuities, changes in
geometry, sharp edges/corners, etc., of forgings and castings of primary components used in well
control are to be examined for flaws by methods capable of detecting and sizing significant internal
defects.
ii)
Methods to detect surface flaws are also to be used in special applications. Substantiation is to be
provided for areas exempted from examination in the terms of stress levels, quality control procedures
at the foundry, forming or casting procedures, or documented historical data.
iii)
iv)
(1 September 2012) All welds of structural members considered primary are to be inspected 100%
by the ultrasonic or radiographic method.
v)
(1 September 2012) Twenty percent of all welds of structural members considered non-primary
are to be inspected by the ultrasonic or radiographic method.
vi)
vii)
In locations where ultrasonic test results are not considered reliable, the use of magnetic-particle
or dye-penetrant inspection as a supplement to ultrasonic inspection is to be conducted.
viii)
i)
138
Nondestructive testing of weldments in steels of 415 N/mm2 (60,000 psi) specified minimum
yield strength (SMYS) or greater is to be conducted at a suitable interval after welds have
been completed and cooled to ambient temperature. The following guidance of interval is
to be used, unless specially approved otherwise:
a)
Minimum 48 hours of interval time for steels of 415 MPa (60,000 psi) SMYS or
greater but less than 620 MPa (90,000 psi) SMYS
b)
Minimum 72 hours of interval time for steel greater than or equal to 620 MPa
(90,000 psi) SMYS
ii)
At the discretion of the Surveyor, a longer interval and/or additional random inspection at
a later period may be required. The 72 hour interval may be reduced to 48 hours for
radiographic inspection or ultrasonic inspection, provided a complete visual and random
magnetic particle or dye-penetrant inspection to the satisfaction of the Surveyor is conducted
72 hours after welds have been completed and cooled to ambient temperature.
iii)
The delay period for steels less than 450 MPa (65,000 psi) and less than 12 mm (0.47 in.)
thick may be decreased to 24 hours if the heat input applied during welding is less than
3.5 kJ/mm and there is satisfactory evidence that there is no hydrogen cracking occurring
after 48 hours.
Section
ii)
11.5
ii)
ASME Boiler and Pressure Vessel Code, Section V Article 7: Magnetic Particle
Examination
Acceptance Criteria:
ASME Boiler and Pressure Vessel Code, Section VIII, Div. 1, Appendix 6: Methods
for Magnetic Particle Examination (MT)
ii)
ASME Boiler and Pressure Vessel Code, Section V Article 6: Liquid Penetrant
Examination
Acceptance Criteria:
ASME Boiler and Pressure Vessel Code, Section VIII, Div. 1, Appendix 8: Methods
for Liquid Penetrant Examination (PT)
ii)
ASTM E186: Standard Reference Radiographs for Heavy Walled (2 to 4.5 in.)
(51 to 114 mm) Steel Castings
ASTM E280: Standard Reference Radiographs for (4.5 to 12 in.) (114 to 305 mm)
Steel Castings
Acceptance Criteria:
ASME Boiler and Pressure Vessel Code, Section VIII, Div. 1, Appendix 4: Rounded
Indications Charts Acceptance Standard for Radiographically Determined Rounded
Indications in Welds.
139
Section
ii)
ASME Boiler and Pressure Vessel Code Section V, Article 5: UT Examination Methods
for Materials and Fabrication
ASTM A388: Standard Practice for Ultrasonic Examination of Heavy Steel Forgings
ASTM E428: Standard Practice for Fabrication and Control of Steel Reference Blocks
Used in Ultrasonic Inspection
ASTM A609: Standard Practice for Casting, Carbon, Low-Alloy, and Martensitic
Stainless Steel, Ultrasonic Examination Thereof
Acceptance Criteria:
ASME Boiler and Pressure Vessel Code, Section VIII, Div. 1, Appendix 12: Ultrasonic
Examination of Welds (UT)
ii)
ASTM E10: Standard Test Methods for Brinell Hardness of Metallic Materials
ASTM E18: Standard Test Methods for Rockwell Hardness and Rockwell Superficial
Hardness of Metallic Materials
ASTM E92: Standard Test Method for Vickers Hardness of Metallic Materials
Acceptance Criteria:
13
NACE MR0175/ISO 1515: Materials for use in H2S containing environments in oil
and gas production
Record Retention
The manufacturer(s) is to maintain the following records after completion, and these records are to be
made available to the Surveyor upon request:
140
i)
ii)
iii)
Welder/welding operator performance test records, including the date and test results and identification
of work assigned to each welder
iv)
A record providing traceability and capable of identifying the welders who have carried out welding
on a particular part
v)
Qualification records for all personnel performing nondestructive examinations and evaluating
results of examination
vi)
SECTION
General
This section pertains to surveys of drilling system, subsystem, equipment, and/or components at the vendors
manufacturing plant and their installation onboard the drilling unit for system build-up and completion for
final trials prior to commencement of drilling operations.
ii)
Confirm and/or establish the main point of contacts (PoC) for the manufacturer and ABS
Confirm specification, drawings and/or documentation associated with the manufacturing process
ABS Surveyors attendance is typically for the following purposes, but not limited to:
(1 September 2012) To confirm that the facilities to manufacture, fabricate or repair drilling
system subsystem, equipment, and/or components have an accredited and maintain an effective
quality control program covering design, procurement, manufacturing and testing, as
applicable, and meeting the requirements of a recognized standard applied to their product
To qualify or verify welders qualifications to the extent deemed necessary by the attending
ABS Surveyor
To witness, as far as deemed necessary, nondestructive examination tests of welds and to review
records of nondestructive examinations
141
Section
iii)
3.1
To review records of post-weld heat treatment, in particular for piping subjected to pressurized
sour service and subject to NACE MR0175/ISO 15156 requirements
To witness pressure and/or proof-load testing of equipment and as a unit, as applicable and as
specified in the fabrication procedures
To witness final testing and functional testing of subassemblies and completed units, as specified
in the fabrication procedures
To verify all purged and pressurized systems, motor controllers, SCR banks, consoles and
instrumentation and control panels are in compliance with approved drawings
(1 September 2012) To carry out other examinations as agreed upon during prefabrication meeting
(1 September 2012) To confirm compliance with associated ABS approval letter or IRC.
(1 September 2012) To review and approve final manufacturing Data Book and issue final
survey report and CoC, as applicable.
(1 September 2012) Materials test reports (MTRs), see Subsection 6/15, are to be made available to
the attending Surveyor during the manufacturing process. In general, materials associated with
equipment and/or components that require Surveyors attendance in accordance with Section 4,
Table 1, are to have complete traceability with MTRs. As a minimum, MTRs are to be provided
for the following:
All piping, valves and fittings with an ANSI B16.5 Class 150 or greater
Prototype testing in accordance with API Spec 16A of each design is to be performed in the presence
of the Surveyor.
ii)
A hydrostatic body or shell test, hydraulic operating system test and closed preventer test in accordance
with API Spec 16A. All tests are to be documented by a chart recorder.
iii)
Shear ram test to verify shear capacity is required in accordance with 3/3.1.3vii) of this Guide and
API Spec 16A, as applicable.
iv)
The manufacturer is to test well control equipment that incorporates a dynamic mode of sealing for
low-pressure integrity at 2.07 MPa (300 psi).
Additional testing requirements are to be in accordance with Section 4, Table 1 of this Guide.
142
Section
3.3
ii)
The number of riser joints tested will be as specified in the approved design of the manufacturer,
as required in this Guide. See Section 4, Table 1 of this Guide for additional testing requirements.
3.5
3.7
3.9
3.11
i)
Mechanized tubular handling systems must have their safety controls verified on computer-based
racking systems.
ii)
Indexing of all mechanical movement must be verified by operational testing. This procedure is to
be carried out in all available fingerboard configurations, and system safety verified.
Installation and testing of well test equipment is to be witnessed by Surveyor upon installation of
the equipment.
ii)
Surveys onboard will verify that the production test plan and procedures are being observed. As a
minimum, tests and inspection are to be as follows:
Electrical equipment will be inspected for condition, suitability for operation and effectiveness
of controls.
Surface safety systems will be tested to determine if the pressure, level and temperature
transducers are in proper working order.
Fire-fighting equipment will be inspected for condition and arrangements will be surveyed to
determine accessibility of all process areas for fire-fighting purposes.
143
Section
3.13
ii)
iii)
(1 September 2012) Witness load testing of the skid structure lifting attachments/lugs or padeyes.
Load test of the skid is to be carried out at maximum static load the lifting attachments/lugs or
padeyes may be subjected to during the transportation or installation of the equipment/machinery
onboard the unit (see 3/11.5.4).
iv)
(1 September 2012) Witness surface NDE of skid structure weldments of the lifting attachments/lugs
or padeyes, after completion of the skid structure load test. MT is recommended for NDE
methodology for surface flaw detection.
v)
Piping systems are to be visually examined, nondestructively examined and pressure-tested, as required
by the ABS MODU Rules or applicable API standards.
ii)
Pressure tests conducted on Group I piping systems (refer to 4-2-1/5 of the ABS MODU Rules)
are to be preferably recorded on test charts for the duration of their tests. Minimum time for
holding pressure is to be 15 minutes.
iii)
iv)
Installed choke and kill systems are to be pressure-tested at rated working pressure and also subjected
to a low-pressure test at 2.07 MPa (300 psi). Applicable performance tests are to be carried out.
v)
Assembly and installation of the drilling derrick is to be examined, to include erection of derrick
structure, welding and bolt torqueing, water table, crown block and turn-over sheaves assembly,
guide rails for hoisting equipment, derrick-mounted equipment and outfitting items, installation
and pressure testing of drilling and related piping systems, overall dimensional control, and final
alignment and bolting on the drill floor/substructure foundations.
vi)
Derrick:
a)
Assembled and installed derrick is to be visually examined, including welding and bolting,
torqueing, its water table, crown block and turnover sheaves assembly, guide rails for hoisting
equipment, derrick-mounted equipment, and outfitting items.
b)
Derrick dimensional control, final alignment and bolting on the drill floor/substructure
foundations are to comply with manufacturers specifications and tolerances.
c)
API Spec 4F does not require load test of the derrick structure unless specified in the clients
PO as per the supplementary requirements Appendix A SR2 of the API Specification.
In this regard, this Guide does not require load testing of the derrick.
vii)
Mud pump operational test is to be carried out in accordance with a test procedure agreed by the
attending Surveyor.
viii)
144
Section
a)
b)
2)
3)
On column-stabilized or surface type units, where a full rated load test may constitute
increased risk or a safety concern to the unit or personnel, alternative testing methods
such as load testing at a reduced number of lines with corresponding rated load
may be considered on a case-by-case basis. Request for such consideration is to
be submitted to ABS and agreed upon prior to commencement of the test.
2)
3)
Brake burnishing test. Burnishing test is to be performed for the primary brake
with consideration to brakes clamping force, drum speed, RPM, or motor speed.
The following tasks are to be performed:
Verification of gapping, the distance between the brakes and the brake discs,
is to be performed and recorded.
Brake verification. After the brake burnishing test, item 8/5viii)b)1), individual
verification of each caliper is to be performed, as applicable, under drum/motor load.
Monitor and confirm brake holding capability including the caliper pressure,
as specified in the approved OEMs specification.
The dynamic/performance brake holding test may be carried out by using a reduced
number of lines with corresponding rated load and in accordance with the drawworks
approved OEMs testing procedures/specifications.
4)
5)
145
Section
c)
Rotational check:
2)
146
Gearbox temperature
Drum temperature
ix)
(1 September 2012) Systems, subsystems, equipment and component associated with tensioning
system and compensation system are to be tested in accordance with Section 4, Table 1 of this
Guide.
x)
(1 September 2012) Systems, subsystems, equipment and component associated with all hoisting,
lifting, handling and rotating systems are to be tested in accordance with Section 4, Table 1 of this
Guide.
xi)
(1 September 2012) All drilling systems and associated subsystems and equipment are to be checked
for proper operation.
xii)
Control system and shutdowns are to be tested to the satisfaction of the Surveyor.
xiii)
All wiring and electrical connections are to be checked for continuity and proper workmanship in
accordance with the ABS MODU Rules.
xiv)
(1 September 2012) The CDS equipment database developed and completed by the attending
Surveyor(s) after manufacturing, installation and commissioning of the drilling system is to be
provided to the drilling unit Owner and retained onboard. The Owner is to:
xv)
5.1
a)
b)
c)
d)
Maintain the database as long as the drilling system is maintained under ABS Classification.
The completed burner assembly is to be pressure-tested from the flexible line connection flange to
the burner head. The adequacy of the booms slewing and topping gear is to be demonstrated by
testing after the booms installation on the drilling unit. The details of the test procedure are to be
agreed upon with ABS and witnessed by a Surveyor.
Load Test After installation, the system is to be tested with a load equal to 125% of the rated
capacity in the presence of the Surveyor. Satisfactory operation of power drives and brakes is to
be demonstrated. After being tested, the system with all its components is to be visually examined
for permanent deformation and failure.
ii)
Performance Test Testing in the presence of the Surveyor is to demonstrate that rated line pull
can be achieved at rated speed with the outermost layer of wire on the drum.
iii)
Brake Holding Test It is to be demonstrated that the brakes have the ability to stop and hold
100% of the design load. Confirmatory testing to demonstrate the braking effect of variable frequency
drive AC motors is to be carried out upon installation onboard.
ABS GUIDE FOR THE CLASSIFICATION OF DRILLING SYSTEMS . 2012
Section
5.3
Proper hook-up and testing of the entire drilling system equipment and components is completed
prior to commissioning. This is to include all tests outlined in Subsection 8/5 of this Guide.
ii)
Necessary safety precautions are taken during commissioning, which are to include checks of
operational readiness of the fire and gas detection system, fire extinguishing system, ESD systems,
unobstructed escape routes, etc.
iii)
iv)
Necessary emergency procedures are readily available to deal with any contingencies such as
spillage, fire, and other hazards. Drills prior to commencement of commissioning may be carried
out to the satisfaction of the attending Surveyor to confirm readiness of these procedures.
v)
Readiness of all utility support systems, including main and auxiliary sources for the drilling system,
prior to commissioning. Random start-up and testing of the utility support systems to extent deemed
necessary by the attending Surveyor.
vi)
Readiness of the purged drilling system equipment/components, and associated alarms and shutdowns,
prior to commissioning, and random testing of the purged alarms systems during commissioning,
to the satisfaction of the attending Surveyor.
vii)
Proper operation of the mud level alarms while the drilling system is running, including random
simulation of associated alarms.
viii)
Proper operation of the hazardous area access and ventilation system while the drilling system is
running, including random simulation of associated alarms and shutdowns.
ix)
Systems capability to control the flow of the well affluent in a stabilized manner, without undue
control upsets, when drilling medium is introduced into the system.
x)
Satisfactory functioning of all drilling systems installed onboard and covered under this Guide.
This will include witnessing proper function of the following systems, as applicable, while simulating
actual drilling operations to the extent possible and practicable, and to the satisfaction of the attending
Surveyor:
xi)
Satisfactory testing of all ROV intervention functions on the subsea BOP stack during the stump
test and testing at least one set of rams in initial test to the satisfaction of the Surveyor.
147
Section
148
xii)
Satisfactory functional testing of autoshear, deadman, and EDS systems on the subsea BOP stack
during the stump test to the satisfaction of the Surveyor.
xiii)
Starting up of the permanent well test system, if applicable, including precautions taken to eliminate
the risk of explosion or fire.
xiv)
Post-commissioned drilling system is in stabilized and satisfactory functioning order for duration
of at least 12 hours.
xv)
SECTION
1.1
1.3
Survey Intervals
All Annual and Special Periodical Surveys of Drilling Systems/Equipment, as defined in 9/5.1 and 9/5.3,
respectively, of this Guide, are to be carried out at the same time and interval as the periodical Classification
survey of the drilling unit in order that they are recorded with the same crediting date.
i)
An Annual Survey of the drilling systems is to be carried out by a Surveyor within three months
before or after of each annual anniversary date of the initial Classification survey.
ii)
A Special Periodical Survey of the drilling system is to be carried out within five (5) years of the
initial Classification certification survey and at five-year intervals thereafter.
iii)
Required surveys are to be completed within three (3) months of their due dates.
iv)
Any part of the drilling system may be offered for survey prior to the due date when so desired, in
which case, the survey will be credited as of that date.
v)
Annual and Special Periodical Surveys are to be scheduled preferably when the Owner/Operator
has scheduled an overhaul of the drilling system:
a)
Annual Surveys are to be scheduled to coincide with the planned or routine MIT of the
BOP stack.
b)
The DEMP plan is to explain how each system and equipment is to be examined and tested during
annual (see 9/5.1) and special periodical survey (see 9/5.3), or alternatives of Subsection 9/7.
ii)
iii)
iv)
All ABS surveys (annual and special periodical) are to be carried out in accordance with an
ABS-agreed DEMP.
149
Section
v)
Maintenance records are to be kept and made available for review by the attending Surveyor. The
maintenance records will be reviewed to establish the scope and content of the required Annual
and Special Periodical Surveys that are to be carried out by a Surveyor.
vi)
During the service life of the drilling system equipment, maintenance records are to be updated on
a continuing basis.
vii)
The Owner/Operator is to inform ABS of any changes to the maintenance procedures and their
frequencies as may be caused, for example, by changes or additions to the original drilling equipment.
viii)
The Surveyor may determine during the periodic survey if the changes are sufficient to warrant
review by the ABS Engineering staff.
150
i)
ii)
(1 September 2012) The repair and modification plans/procedures of drilling systems, subsystems,
equipment or component are to be in accordance with OEMs and Owners specifications and
submitted for ABS approval.
iii)
Confirm and/or establish the main point of contacts (PoC) for the manufacturer and ABS
Confirm OEMs specifications, drawings and/or documentation associated with the maintenance,
repair or modification process
iv)
Surveyors are to attend the facility/plant for the required function, load and/or pressure testing
carried out on the drilling system equipment prior to their release back offshore to the drilling unit.
Tests conducted are to follow guidelines outlined in API standards or equivalent.
v)
vi)
See Appendix 5 for an example of the Maintenance Release Note (MRN) to be issued by Surveyors.
vii)
All MRNs are to be maintained onboard the drilling unit as part of the Owner/Operators maintenance
record and for verification by the attending Surveyor during Classification surveys of the unit.
Section
5.1
Annual Surveys
At each Annual Survey, the Surveyor is to verify the effectiveness of various systems and equipment by visual
examination and testing, as appropriate. As a minimum, the following is to be carried out to the satisfaction
of the attending Surveyor:
i)
b)
c)
ii)
Review of ABS-issued MRNs and/or CoCs since initial or last Annual Survey, and examination of
this equipment to extent deemed necessary by the attending Surveyor.
iii)
Review of ABS Drilling System Database for approved changes made to the drilling system
equipment, and examination of this equipment to the extent deemed necessary by the attending
Surveyor.
iv)
Exposed surfaces of the derrick, ladders, working/service platforms, arresting gear, drilling hoisting
systems, lifting devices, burner booms, stabbing boards, racking boards/platforms and drilling
equipment foundations are to be examined and placed in satisfactory condition, as found necessary.
The inspection of the derrick and related structural members will include the following:
a)
The general condition of the structure, especially bent, missing or abraded parts and lost
corrosion protection coatings.
b)
Tightness of bolts and the integrity of secondary retention mechanism where originally
installed.
c)
v)
Examination of all mounting hardware and the structure of base-mounted winches and other lifting
devices. Magnetic Particle Inspection (MPI) may be carried out as deemed necessary by the attending
Surveyor.
vi)
General external examination so far as accessible of the drilling systems, subsystems, equipment and
components as noted in the scope of 1/7.5 of this Guide for damage, excess corrosion, fracturing
or malfunctions, etc.
vii)
Protective covers, insulation, shrouds and protective guards around moving parts are to be found
in place and in functional condition.
viii)
Derrick walkways and ladders, drill floor and drill system machinery spaces to be surveyed with
particular attention to fire and explosion hazards and confirmation that emergency escape routes
are not blocked.
ix)
External examination of pressure vessels and their appurtenances, including safety devices,
foundations, controls, relieving gear, piping systems, flexible lines/hydraulic hoses, insulation and
gauges.
x)
Examination of safety shutdown devices with functional testing as deemed necessary by the attending
Surveyor.
xi)
General examination of all electrical and instrumentation systems, including protective devices
and cable supports.
xii)
151
Section
xiii)
Examination of the BOP stack, to the extent as practical, inclusive of choke and kill manifold, test
log and maintenance records.
xiv)
Testing of the BOP equipment in accordance with API RP 53, or as required by local regulations:
xv)
5.3
152
Review BOP inspections and maintenance records in accordance with Section 17 (surface BOPs)
and/or Section 18 (subsea BOPs) of API RP 53.
5.5
b)
ii)
Internal examination and/or thickness gauging of pressure vessels and pressure-retaining components,
testing of relief valves and pressure piping systems, as considered necessary by the Surveyor.
iii)
Hydrostatic testing of pressure vessels and other pressure-retaining components related to the drilling
system to their MAWP.
iv)
Hydrostatic testing of drilling system piping systems and flexible lines/hydraulic hoses to their MAWP.
v)
Examination and check of insulation resistance of motors that are part of the drilling system.
vi)
Examination of rotating drilling machinery to verify suitable operation, free from excessive vibration.
vii)
The blowout preventer is to be subjected to a complete performance test and pressure-tested to its
MAWP.
viii)
ix)
Functional testing of derrick gear, drilling hoisting systems and derrick floor lifting devices.
x)
Close examination of the condition of welded joints on the derrick and associated structure, including
nondestructive testing (including thickness gauging if required) of any suspect areas noted by the
attending Surveyor.
xi)
Examination of the equipment associated with the well control system and their maintenance records.
xii)
xiii)
Retesting of lifting appliances in accordance with the load testing requirements of the applicable
design codes and standards, such as API Spec 2C, ABS Lifting Appliances Guide, etc.
Unscheduled Survey
Upon notifications by the Owner/Operator, Surveyors attendance is required under the following conditions:
i)
If the blind-shear or casing shear ram was activated in a well control situation, the Owner/Operator is
to inform ABS of the BOP stack retrieval. ABS Surveyor is to be in attendance for the
Owner/Operators inspection and testing of the retrieved BOP stack.
ii)
When the Owner/Operator performs major MIT of the BOP stack, planned or unplanned, the
Owner/Operator is to inform ABS of the MIT plans for the BOP stack, and these are to be
performed under ABS Surveyors attendance.
Section
7.1
7.3
The completion date will be recorded to agree with the original due date of the cycle.
ii)
If the Continuous Survey is completed prematurely but within three months prior to the due date,
the Special Periodical Survey will be credited to agree with the effective due date.
iii)
Each part (item) surveyed becomes due again for survey approximately five years from the date of
the survey.
iv)
For Continuous Surveys, a suitable notation will be entered in the Record and the date of completion
of the cycle published.
v)
If any defects are found during the survey, they are to be dealt with to the satisfaction of the Surveyor.
vi)
ABS reserves the right to authorize extensions of Rule-required Special Continuous Surveys under
extreme circumstances.
7.5
When a system certified with ABS has suffered any damage to machinery, piping or equipment, etc.,
which may affect Classification, ABS is to be notified and the damage inspected by a Surveyor.
ii)
If a classed drilling system suffers any damage to its equipment, ABS is to be notified and the
damage examined by a Surveyor. Details of intended repairs are to be submitted for approval, and
the work is to be carried out to the satisfaction of the attending Surveyor.
iii)
Where component parts suffer a premature or unexpected failure, and are subsequently repaired or
replaced without Surveyor attendance, details of the failure, including the damaged parts where
practicable, are to be retained onboard for examination by the Surveyor during the next scheduled
survey/visit.
iv)
Alternatively, the component(s) may be taken ashore for examination and testing, as required. If
failures are deemed to be a result of inadequate or inappropriate maintenance, the DEMP is to be
amended and resubmitted for approval.
153
Appendix 1: Typical Codes and Standards Related to ABS Classification of Drilling Systems
APPENDIX
(1 September 2012) The latest edition of the following codes and standards are applicable and referenced
in this Guide.
ABS is prepared to consider other appropriate alternative methods and recognized codes and standards.
When alternate codes and/or standards are proposed, comparative analyses are to be provided to demonstrate
equivalent level of safety to the recognized standards as listed in this Guide and are to be performed in
accordance with 1/7.7 of this Guide.
API
154
(1 September 2012)
Bul 16J
Comparison of Marine Drilling Riser Analysis
Bul 2INT-MET
RP 2A-WSD
Spec 2C
RP 2X
Std. 4A
Steel Derricks
Spec 4F
Spec 5D
Drill Pipe
Spec 6A
Spec 6AV1
Verification Test of Wellhead Surface Safety Valves and Underwater Safety Valves
for Offshore Service
Spec 7-1
Spec 7B-11C
Spec 7F
Spec 7K
Spec 8A
Spec 8C
Spec 9A
Wire Rope
RP 9B
Application, Care, and Use of Wire Rope for Oil Field Service
Spec 12J
Spec 12K
RP 13C
Spec 14A
RP 14B
Appendix 1
RP 14C
RP 14E
RP 14F
Design and Installation of Electrical Systems for Fixed and Floating Offshore
Petroleum Facilities for Unclassified and Class I, Division 1 and Division 2
Locations
RP 14FZ
Design and Installation of Electrical Systems for Fixed and Floating Offshore
Petroleum Facilities for Unclassified and Class I, Zone 0, Zone 1, and Zone 2
Locations
RP 14G
Fire Prevention and Control on Fixed Open Type Offshore Production Platforms
RP 14J
Spec 16A
Spec 16C
Spec 16D
Control Systems for Drilling Well Control Equipment and Control Systems for
Diverter Equipment
Spec 16F
RP 16Q
Spec 16R
RP 16RCD
RP 17A
RP 17B
Flexible Pipe
Spec 17D
Spec 17E
Spec 17F
Spec 17J
Spec 17K
RP 17G
RP 17H
RP 53
RP 59
RP 64
RP 500
RP 505
Std. 520
Std. 521
Std. 610
Std. 2000
RP 2003
Protection Against Ignitions Arising Out of Static, Lightning and Stray Contents
155
Appendix 1
Nondestructive Examination
Section IX
Section X
Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
A384
Standard Practice for Safeguarding Against Warpage and Distortion During HotDip Galvanizing of Steel Assemblies
A385
A388
E8
E10
E18
Standard Test Methods for Rockwell Hardness and Rockwell Superficial Hardness
of Metallic Materials
E92
E94
E165
E186
Standard Reference Radiographs for Heavy Walled (2 to 4.5 in.) (51 to 114 mm)
Steel Castings
E280
Standard Reference Radiographs for (4.5 to 12 in.) (114 to 305 mm) Steel Castings
E428
Standard Practice for Fabrication and Control of Steel Reference Blocks Used in
Ultrasonic Inspection
E446
E609
Standard Practice for Casting, Carbon, Low-Alloy, and Martensitic Stainless Steel,
Ultrasonic Examination Thereof
E709
D1.1
AWS
BCSA (1 September 2012)
Publication No. 40/05 Galvanizing Structural Steelwork An Approach to the Management of Liquid
Metal Assisted Cracking
156
Appendix 1
EN
(1 September 2012)
473 / ISO 9712
Non-destructive testing Qualifications and certification of NDT personnel
General principles
IEC
61508
C37.06.1
Guide for High Voltage Circuit Breakers Rated on Symmetrical Current Basis
Designated Definite Purpose for Fast Transient Recovery Voltage Rise Times
C37.20.6
Std. 45
Std. 142
Std. 242
IEEE
ISO
(1 September 2012)
9712
Non-destructive testing Qualifications and certification of NDT personnel
General principles
19901-1
MR 0175/ISO 15156
Materials for use in H2S containing environment in oil and gas production
NACE
NFPA (1 September 2012)
37
Standard for the Installation and Use of Stationary Combustion Engines and Gas
Turbines
70
496
J517
Hydraulic Hoses
SAE
157
APPENDIX
158
Appendix 2
Customer PO#
: AAA-12345
Description of Equipment
: XXX-YYY
Date of Manufacturing
EXAMPLE
Temperature Rating:
(min / max) C
This affidavit is prepared by the undersigned, authorized representative of the manufacturer, to certify that
the equipment described above and supplied for this order is in full compliance with respect to the design,
assembly, manufacture, and testing of the equipment in accordance with the referenced code(s), standard(s) or
specification(s), and is suitable for the intended use in accordance with the referenced design parameters.
This affidavit is prepared by the undersigned, authorized representative of the manufacturer, to certify that
the equipment described above is in compliance with the requirements of the ABS Guide for the
Classification of Drilling Systems, and is enclosed as part of the equipment delivery/shipment documents.
Signature
Name :
Title :
Date :
159
APPENDIX
The following is an example of ABS Independent Review Certificate (IRC), issued in accordance with
Section 4, Table 1.
The contents of the IRC and associated CoC are to be specific to the equipment and its respective design
parameters and approval.
160
Appendix 3
ABS OPN/PID:
This is to certify that the design plans and data for the manufacture of the equipment listed below have
been reviewed and found to be in compliance with the specified codes, standards, or specifications, and the ABS
Guide for the Classification of Drilling Systems.
Manufacturer & Address
Description of Equipment
Equipment Part.
: XXX-YYY
Date of Manufacturing
EXAMPLE
: Jan 01, 2011
Design Temperature
Service Condition
(min / max) O C
: API 16A
ABS Engineer
Principal Engineer
Offshore Engineering Department Machinery Group
This certificate is a representation that the structure, item of material, equipment, machinery or other item covered by this certificate has met one or more of the Rules,
Guides standards or other criteria of ABS or of a National Administration and is issued solely for use by ABS, its committees, its clients or other authorized entities. The
validity, applicability and interpretation of this certificate is governed by the Rules and Standards of ABS, and ABS shall remain the sole judge thereof. Nothing contained in
this certificate or in any notation made in contemplation of this certificate shall be deemed to relieve any designer, builder, owner, manufacturer, seller, repairer, operator or
other entity of any warranty express or implied.
161
Appendix 3
ABS OPN/PID:
Date:
Manufacturer
Description of Equipment
: XXX-YYY
Date of Manufacturing
Drawing No.
EXAMPLE
Rev.
Drawing Title
RELATED CORRESPONDENCE:
IRC No: HOE-XXXXXX/2009
This certificate is a representation that the structure, item of material, equipment, machinery or other item covered by this certificate has met one or more of the Rules,
Guides standards or other criteria of ABS or of a National Administration and is issued solely for use by ABS, its committees, its clients or other authorized entities. The
validity, applicability and interpretation of this certificate is governed by the Rules and Standards of ABS, and ABS shall remain the sole judge thereof. Nothing contained in
this certificate or in any notation made in contemplation of this certificate shall be deemed to relieve any designer, builder, owner, manufacturer, seller, repairer, operator or
other entity of any warranty express or implied.
162
APPENDIX
The following is an example of ABS Certificate of Conformity (CoC), issued in accordance with Section 4,
Table 1.
The contents of the IRC and associated CoC are to be specific to the equipment and its respective design
parameters and approval.
163
Appendix 4
Date: ________________________
This is to certify that the undersigned Surveyor has surveyed the following equipment in accordance
Description of Equipment
: XXX-YYY
Date of Survey
EXAMPLE
: Jan 01, 2011
Design Temperature:
H 2 S (yes / no)
(min / max) C
Scope of Survey:
_________________________________________________________________________________________
_________________________________________________________________________________________
________________________________________________________________________________________
Temperature
:
Calibration Date :
___________________________________
ABS Surveyor
_______________________________________
Signature
This Certificate evidences compliance with one or more of the Rules, guides, standards or other criteria of ABS and is issued solely for the use of ABS, its committees, its clients or
other authorized entities. This Certificate is a representation only that the structure, item of material, equipment, machinery or any other item covered by this Certificate has met one or
more of the Rules, guides, standards or other criteria of ABS as of the date of issue. Parties are advised to review the Rules for the scope and conditions of classification and to review
the survey records for a fuller description of any restrictions or limitations on the vessel's service or surveys. The validity, applicability and interpretation of this Certificate are governed
by the Rules and standards of ABS, and ABS shall remain the sole judge thereof. Nothing contained in this Certificate or in any notation made in contemplation of this Certificate shall
be deemed to relieve any designer, builder, owner, manufacturer, seller, supplier, repairer, operator or other entity or any warranty express or implied.
164
APPENDIX
The following is an example of ABS Survey Report (AB Report Vendor), issued in accordance with
Section 4, Table 1.
The contents of the Survey Report are to be specific to the equipment and its respective design parameters
and approval.
165
Appendix 5
Customer Name:
12345678
Attending Office:
Report Number:
HS1234567
Certification Of:
Bonnet Assembly
Manufacturer:
Survey Location:
Equipment Data:
EXAMPLE
This is to Certify that the undersigned surveyor(s) to this Bureau did, at the request of the customer, carry out the
________________________________________
Reviewed By:
________________________________________
NOTE: This report evidences that the survey reported herein was carried out in compliance with one or more of the Rules, guides, standards or other criteria of ABS and is issued
solely for the use of ABS, its committees, its clients or other authorized entities. This Report is a representation only that the vessel, structure, item or material equipment, machinery or
any other item covered by this Report has been examined for compliance with, or has met one or more of the Rules, guides, standards or other criteria of American Bureau of Shipping.
The validity, applicability and interpretation of this report are governed by the Rules and standards of ABS, and ABS shall remain the sole judge thereof. Nothing contained in this
Report or in any notation made in the contemplation of this Report shall be deemed to relieve any designer, builder, owner, manufacturer, seller, supplier, repairer, operator or other
entity of any warranty express or implied.
AB Report Vendor
166
APPENDIX
Owner:
Report Number:
HS03179
Port of:
Houston
Date:
P.O. No.:
AA-BB-CCC
Address:
Name of Drilling Unit:
XYZ-001
ABS OPN/VID:
0123456
EXAMPLE
Details of survey
_______________________
ABS Surveyor
NOTE:
This Certificate evidences compliance with one or more of the Rules, Guides, standards or other criteria of ABS and is issued solely for the use of ABS, its committees, its
clients or other authorized entities. This Certificate is a representation only that the structure, item of material, equipment, machinery or any other item covered by this
Certificate has met one or more of the Rules, Guides, standards or other criteria of ABS as of the date of issue. Parties are advised to review the Rules for the scope and
conditions of classification and to review the survey records for a fuller description of any restrictions or limitation on the vessels service or surveys. The validity, applicability
and interpretation of this Certificate are governed by the Rules and standards of ABS, and ABS shall remain the sole judge thereof. Nothing contained in this Certificate or in
any notation made in contemplation of this Certificate shall be deemed to relieve any designer, builder, owner, manufacturer, seller, supplier, repairer, operator or other entity
or any warranty express or implied.
167